Revised SOP For Enlistment of Products of Explosive Manufacturer
Revised SOP For Enlistment of Products of Explosive Manufacturer
A. Background:
CIL is the largest consumer of commercial explosives in India. The procurement of explosives
and accessories in CIL is done through a centralized tendering process for all the subsidiaries
of CIL.
CIL maintains an approved product list of explosives and accessories as per specific
requirements of mines of CIL. To participate in the tendering process of explosives and
accessories, for the prospective bidders, it is a prerequisite to get their product
included/enlisted in the CILs approved product list. In order to broaden its vendor base, CIL
allows manufacturers to include/enlist their products in CIL approved product list following
specific guidelines/SOP. This SOP provides the guidelines for the inclusion of the new
products of explosive and accessories manufacturers to CIL approved list.
1. Only explosives and accessories products that are enlisted in CIL’s approved product list
shall be eligible for consideration for procurement.
2. Procurement of Explosives by Subsidiaries: In exceptional cases, if a Subsidiary has
been permitted to procure Explosives directly, it shall procure only the items that are on
CIL’s approved Product List.
3. For inclusion of new explosives and accessories products in CIL’s approved product list,
the PESO authorized explosives manufacturers shall apply to ED (Prod.), CIL along with
the notarized copies of documents mentioned in Annexure- A with copy to GM (Prod.),
CIL. (Copy of Annexure – A enclosed)
The applications for enlistment can be made in any month of the year*. However, in the
year when tenders for regular Rate Contracts are published, in such cases:
(i) The applications for enlistment of Bulk Explosives should be received by the
month of April of the same calendar year (i.e., tender publishing year) and
(ii) The applications for Cartridge Explosives and Accessories should be received by
the month of January month of the same year as above (i.e., tender publishing
year).
If any application received beyond this period for relevant product/ year, the same will be
considered after the conclusion of the relevant tender.
For this purpose advertisement on CIL’s website will be published suitably 6-8 months in
advance, so that the exercise is completed before closing date of the concerned tender.
*Note: Regular Rate Contracts are normally for 2 year period and the current/ ongoing
RC is from 2023-25 i.e., in this case the year means 2025.
1
4. The application made by the manufacturer shall be initially examined by the Production
Division associated with MM and the Finance Division for shortfall of documents if any.
5. After the receipt of complete documents, approval of DT, CIL shall be taken for
processing the application and for constitution of a multi- disciplinary committee
consisting of one executive each from Production Division, MM Division, Finance
Division, CIL and Blasting Division, CMPDI.
6. The committee constituted as above will physically inspect the explosives manufacturers’
plant/factory/silo/support plant and will verify the documents submitted by the
manufacturers/applicant with that of the original ones. The committee shall assess the
infrastructure and financial capability of the firm and clearly recommend the same in the
inspection report for further processing for field trials and tests.
7. The committee/team will then submit the inspection report of the explosive plant /factory
visit to ED (Production), CIL / GM (Prod), CIL.
8. Based on the report/recommendations of the committee and if agreed by ED(Prod),CIL
/GM(prod), CIL, as the case may be, communication will be sent to the explosive
manufacturers through email/letter to contact GM/HOD (Business Development), CMPDI
for further field trial and testing. A copy of this communication will also be sent to GM
(Blasting) CMPDI by ED (Prod.), CIL /GM (Prod.), CIL, as the case may be.
9. Upon receipt of the communication from CIL as above, the manufacturer shall contact
GM/HOD (Business Development) CMPDI and shall pay the requisite fee amount for test
and trial of their products as prescribed by CMPDI. All the communications made to the
manufacturer/applicant by CMPDI shall also be marked to ED (Production), CIL, GM
(Prod.), CIL and GM (Blasting), CMPDI.
10. Upon receipt of communication from GM/HOD (Business Development) CMPDI regarding
the compliance by manufacturer/applicant, GM (Blasting), CMPDI shall identify a suitable
mine for field test and trial of the product in consultation with GM/HOD of
Production/Explosives Dept. of CIL & Subsidiary Companies.
2
to ED (Prod.), CIL with a copy to GM (Blasting), CMPDI and retest shall be allowed only
once with the approval of competent authority. Application for retest received beyond 30
days will not be accepted and in such cases, the applicant needs to apply afresh and all
above procedures will be followed.
15. All the manufacturers of the products appearing on CIL’s approved product list, shall
submit the documents as per SOP every four years from the date of
enlistment/renewal/relisting, as the case may be, for renewal/re-listing of the products in
CIL’s approved product list.
16. If any new Plant/Silos/support plant have been undertaken during the intervening period,
the same need to be submitted with renewal/relisting application and all such new
additions will be inspected by duly constituted committee and after recommendation, the
product shall continue to be in the CIL’s approved Product list. The continuation of the
product in the CIL’s approved Product list will be communicated to the manufacturer post
approval.
17. No fresh test & trials of the product will be conducted in renewal/relisting cases as above.
Only the relisted products during the last four years as above, shall be considered during
the tender evaluation.
18. In the cases, where the authorization of the product has been suspended due to any
reasons, the manufacturers shall immediately inform regarding the same.
And
In the cases, where the authorization of the product has been withdrawn by PESO/DGMS
3
in the intervening period of re-enlistment on account of Indian and other Standards
Revisions incorporating various changes including testing and quality control systems or
any other reasons, then in such cases, fresh application and complete procedure for
enlistment of product will be applicable.
19. Permission of DGMS is required to be submitted if the plant/factory/silo/support plant is
located in the premises of mine.
20. Financial and commercial documents are to be excluded if the firm applies for enlistment
of another product in the same financial year. However, other documents shall be
submitted along with the application and the inspection of the team shall be as per the
documents submitted in this case.
21. SOP for field trials and tests of the explosives and accessories product is enclosed as
Annexure – B.
22. The product approval granted for enlistment/renewal/relisting, as the case may be, in CIL’s
approved product list, among others shall be subject to the applicable provisions of the
Explosive Act’ 1884 and allied legislations, Mines Act, 1952 and allied legislations, DGMS
Circulars, guidelines, instructions, etc. issued there under. The explosives product
enlisted/renewed/relisted, as the case may be, in CIL’s approved product list, may be
withdrawn, if at any point of time, it is observed that the manufacturer has concealed any
information which has resulted in contravention of the aforesaid statutory stipulations or
the information shared for enlistment/renewal/relisting, as the case may be, as per
relevant annexure, is fabricated/forged/manipulated.
23. The amended approved SOP for product enlistment/re-enlistment supersedes all the
earlier approved SOPs of CIL for product enlistment of explosives and accessories.
24. In case of any dispute arises on the provisions of the SOP, the interpretation and decision
of the Director (Technical), CIL will be final. Further, any proposed
changes/addition/modification/revision in the SOP/guidelines will be effected with the
approval of the Director (Technical), CIL.
25. CIL reserves the right to alter, amend or withdraw partly or fully any of the provisions of
the SOP/guidelines, as and when needed
***************************
4
Annexure - A
List of Documents for enlistment/re-enlistment of Explosives & Accessories
Products
5
Sl. List of Documents Remarks
no
Facility of transportation of explosives (with Explosives vans and BMDs details
13 documentary evidence of PESO approval, RC, with statutory documents
fitness certificate, PUC and Insurance)
All the details of the plant and
14 Plant & Machinery facilities for quality testing
of product Machinery with the details of
quality testing being done.
List of Quality testing employees, their Complete list
15
qualification and experience
List of Mining Personnel’s ,their qualification Complete list
16
and experience
Product Literature and Technical Data sheet of
17
the product applied
Production of the product applied , in last 3
18
years including current year, as applicable
List of Existing Customer, if any, for the product
19
applied , order copies, supply proof and
performance certificate by Customer
Municipality Tax/ Panchayat Tax All applicable to be submitted
20
Electric Bill/Lease Rent Documents
Facility for Alternative Source of Power
21
Supply/Back up source of supply (with relevant
documentary evidence)
The applied product should
22 ISO certificate
be mentioned in the
certificate
Certificate of Incorporation along with
23
Memorandum and Articles of Association (in case
of companies)
Partnership Deed and extracts from Registrar of
24
firms. If available ( in case of partnership firms)
25 Udyam Certification in case of MSME’s
27 Copy of PAN no
6
Annexure - A (1)
ED (Production)
CIL, Kolkata
Subject: Financial credibility certificate in respect of M/s………………………… (Name of the firm with
address) for the purpose of enlistment of a new product of explosives and accessories with Coal
India Limited, Kolkata.
Sir/Madam,
This is to certify that M/s ………………………… (Name of the firm with address) are maintaining
Current/Saving Account No……………………with this bank branch for the last ……………….. Years. The
firm has been provided with a credit limit of Rs………………………..
This is certified that the regularity in repayment of loan by the firm is satisfactory.
This is further certified that the bank is ready to provide sufficient loans for business expansion of
the present project/starting of a new project.
Yours faithfully
( )
7
Annexure - B
The steps to be followed during performance evaluation of new Cord Relay supplied by any
manufacturer during blasting trials are enumerated below:
2) Taking up the matter with the concerned subsidiary requesting to provide suitable mine /
mines for carrying out the field trials where Cord Relay of other manufacturers are already in
use so that, the performance of new Cord Relay product can be comparatively assessed with
the performance of existing Cord Relay used by the mines where Blasting trials will be
conducted. Testing should be carried out in all possible scenarios viz. dry face condition,
watery face condition containing mud and broken rock.
3) Quantity to be tested
A minimum quantity of 300 No’s is to be supplied free of cost by the manufacturer for carrying
out Blasting trials. A minimum of 6 to 7 rounds of blasting trials are required for evaluation of
a new product of Cord Relay.
4) The following Technical Parameters should be examined on the surface before putting it to
actual blasting trials to ascertain the quality of the new product. The test results of the new
product must lie within the limiting range in respect of all technical parameters specified in
the Running contract under the head “Technical parameters for Random Testing”.
If any of the test results falls outside the range, the product shall not be recommended for
use in the mines of Coal India Limited and if re-testing is required for the failed product, the
procedure as specified in “Revised SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be followed.
b. Transmission Test:
Under this test, a minimum quantity of 25 No’s of Cord Relay should be connected in series
using detonating fuse / cord and fired. All the 25 No’s of Cord Relay should be fired without
any misfire.
d. Quantities to be Tested:
8
e. Sensitivity:
The sensitivity test should be determined by firing the cord relays in different lines (either in
the main line or in the branch line) with a detonating fuse. All Cord- relays shall fire.
The test results of the new product of Cord Relay shall be properly documented and should
be duly signed by representative of mine, representative of respective manufacturer and
representative of CMPDI and shall be enclosed in the Final report as Annexure-I.
There should not be any Misfire during blasting trials. If there takes place any Misfire during
blasting trials, the product should not be recommended for use in the mines of Coal India
Limited and if re-testing is required for the failed product, the procedure as specified in
“Revised SOP for inclusion of new products of Explosive manufacturers in CIL approved
product list of Explosives & Accessories” shall be followed.
5) Records of blasting trials should be properly documented along with observations, if any and
should be duly signed by representative of mine, representative of respective manufacturer
and representative of CMPDI and should be enclosed in the Final Report as Annexure-II.
SI.
Particulars Yes No
No.
9
Annexure – I
9. Final result:
10
Annexure–II
11
4 Volume of toe (m3) :
5 Muck-pile profile :
6 Throw :
7 Ease of digging :
8 Misfire (if any) :
12
STANDARD OPERATING PROCEDURE
FOR EVALUATING THE PERFORMANCE OF NEW BULK EXPLOSIVE DURING
BLASTING TRIALS BY CMPDI IN MINES OF COAL INDIA LIMITED
The steps to be followed during performance evaluation of New Bulk explosives supplied by any
manufacturer during blasting trials are enumerated below:
2) Taking up the matter with the concerned subsidiary requesting to provide suitable mine /
mines for carrying out the field trials where bulk explosives are already in use so that the
performance of new bulk explosives can be comparatively assessed with the performance
of existing bulk explosives used by the mines where blasting trials will be conducted. Testing
should be carried out in all possible scenarios viz. dry hole condition, watery hole condition
containing mud and broken rock. The bulk explosives should be used in mine having bench
height at least up to 9m, so that the explosives can be loaded in blast holes as top and bottom
charge column. The Cast Booster (Emulsion) or Cast Booster (PETN/TNT) may be used,
however the Cast Booster (Emulsion) should be preferably used during blasting trials, if
available in mine.
3) Quantity to be tested
A minimum quantity of 30 MT shall be supplied free of cost by the manufacturer for carrying
out blasting trials. A minimum of 6 to 7 rounds of blasting trials are required for evaluation of
new product of bulk explosives.
4) The following Technical Parameters should be examined on the surface under unconfined
condition before putting it to actual blasting to ascertain the quality. The test results of the
new product must lie within the limiting range in respect of all technical parameters specified
in the Running contract under the heading “Technical parameters for Random Testing”.
If any of the test results falls outside the range, the product shall not be recommended for
use in the mines of Coal India Limited and if re-testing is required for the failed product, the
procedure as specified in “Revised SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be followed.
Velocity of detonation should be determined with a Digital / Electronic VOD meter under
unconfined conditions.
13
c. Density of Explosive
● Fresh
● After 24 hrs Sleepage
Density of the explosive should be determined by the water displacement method.
The sensitivity of the explosive should be checked by employing a 100g cast booster along
with the bulk explosive encapsulated in cartridge form to perform the test.
The test results of the new product shall be properly documented and should be duly signed
by representative of mine, representative of respective manufacturer and representative of
CMPDI and shall be enclosed in the final report as Annexure-I.
5) Blast design and Initiation patterns should be suggested by the technical representatives of
the manufacturer according to Hardness of the strata and height of the bench. Hardness of
the strata of the corresponding bench is determined with dedicated instruments.
After each blasting trial the mucking operation should be observed and analyzed using Digital
Image Analysis Technique. There should not be any Misfire during blasting trials. If there
takes place any Misfire during blasting trials. During the trial period the electronic counter,
which is an integral part of the BMD system must function accurately and reliably. Any
malfunctioning in the electronic counter will lead to termination of the blasting trials and the
product should not be recommended for use in the mines of Coal India Limited the product
should not be recommended for use in the mines of Coal India Limited and if re-testing is
required for the failed product, the procedure as specified in “Revised SOP for inclusion of
new products of Explosive manufacturers in CIL approved product list of Explosives &
Accessories” shall be followed.
In order to determine the actual / exact quantity of explosives loaded / poured into all the
blast holes during charging operation, the following methodology should be practiced during
blasting trials.
a) The Pump truck / BMD vehicle should be weighed at the weigh bridge of the
respective mine before charging operation and after completion of charging operation
in presence of the representative of mine, representative of respective manufacturer
and representative of CMPDI to ascertain the quantity of the explosives consumed
during charging operation and after completion of charging operation. The difference
of the weighment before charging operation and after completion of charging
operation will indicate the explosives quantity used during the charging operation.
While finalizing the Weight of the Explosive, the water left in the water tank shall also
be deducted.
14
b) The counter fitted to the body of the BMD vehicle should be checked before start of
the charging operation and at the end of charging operation during each blasting trial.
The difference in the counter reading showing the cumulative quantity discharged
from the pump truck / loaded into all the blast holes should be computed accurately.
c) The total quantity of explosives consumed during the charging operation will be the
Higher value obtained by observing the methodology mentioned at point no. a) and
b) and should be used for determination of the powder factor. This methodology will
be applicable only during introduction of new bulk explosives product.
In order to record the explosives quantity along with the accessories consumed during
charging operation during blasting trial, the loading sheet appearing at Annexure-II
should be used.
7) Blasting trials record should be properly documented along with observations, if any and
should be duly signed by representative of mine, representative of respective manufacturer
and representative of CMPDI and should be enclosed in the final report as Annexure-III.
-----x-----
15
Check List to be followed during Blasting trials of
New Bulk Explosive
SI.
Particulars Yes No
No.
Blasting trial were carried out in all possible scenarios viz. dry face /
2 hole condition, watery face / hole condition containing mud and broken
rock.
VOD of both the fresh sample and after sleepage sample of the New
7
bulk explosive were measured under unconfined conditions.
Densities of both the fresh sample and after sleepage sample of the
8
explosive were measured.
Booster-sensitivity of both the fresh sample and after sleepage
9
Sample of the explosive were examined.
10 Hardness of strata was measured by any dedicated instruments.
Powder factor, fragmentation, throw, muck pile profile and percentage
11 of oversized boulder w.r.t. loading equipment were observed during
mucking operation.
12 Were there any misfires observed during blasting trials?
16
Annexure-I
TEST RESULTS OF NEW BULK EXPLOSIVE
1. Name of the manufacturer:
2. Name of the product:
3. Colour of product:
4. Sample no.:
5. Date of sampling:
6. Date of testing:
7. Type of density modifier:
8. Name of mines/magazines
from where samples were
drawn:
Specified limit
9. Test Conducted Results Remarks
as per RC
(i) Physical Condition Shall be Good
Velocity of a) Fresh ≥3500
(ii) detonation b) After
(m/sec) ≥3500
sleepage
a) Fresh 1.15 ± 0.05
Density
(iii) b) After
(g/cc) 1.15 ± 0.05
sleepage
As per 4 (d) of
a) Fresh SOP
Booster
(iv)
sensitivity b) After As per 4 (d) of
sleepage SOP
17
18
Annexure–III
19
G Sketch Showing the Pattern of Holes, Placement of Nonel / Cord Relay /
Electronic Detonator/DF and Sequence of Delay
H Section of Holes Showing the Charge Distribution and the Height of Stemming
Column
20
Appendix–1
a. Take the Bulk Explosives of unknown VOD into the 83 mm poly lay flat tube in a cartridge
form.
b. Take a pair of twisted cables (Preferably Green and Red). Green cable as Start Probe and
Red Cable as Stop Probe and keep both the probes (Start & Stop Probe) in open circuit as
shown in figure. (enclosed)
c. Now tie two of these cables to bulk explosives cartridge at a distance of 10cm/15 cm/20 cm
(Probe Distance) as per given figure.
d. After Binding cables on Explosive sample, measure the distance between the cables and
make sure that the distance should not increase or decrease as per the distance set for the
Explosive sample to be tested.
e. There will be 2 ends for Start Probe (Green) and 2 ends for Stop Probe (Red) as shown in
Figure.
f. Take a 3 core (Preferably one green, one red and one black) Cable (1.5mm Square copper
wire) in required length to safeguard Operator and instrument (Preferably 100m)
g. One end of the Start Probe (Green) and One End of the Stop Probe (Red Cables) are to be
joined and make 4 cores to 3 core
h. The Probes taken from cartridge (Start, Stop and Common) are to be connected to 100m, 3
core cable (Green to Green, Red to Red and remaining Green and Red to Black)
i. Other end of the 3-core cable has to be connected to the Digital/ Electronic VOD Meter, Start
probe to Start Pin, Stop Probe to Stop Pin and Common Probe to Common Pin. By this, the
total circuit will be in open condition.
j. Now put on the unit by pressing the “ON” button and input the required data to the Digital/
Electronic VOD meter.
k. Finally, the Bulk Explosive Sample has to be connected with the Nonel /Detonating Fuse with
cast Booster to initiate it.
l. The cast Booster has to be inserted into the Bulk sample towards the start probe (Green
Probe) and to be inserted in such a fashion that the Cast Booster should not be very near to
the start probe (a little far from it) and the other end of the detonator will be connected to
Exploder.
m. Now, press the Test Button on the unit.
n. After taking proper shelter, blaster shall initiate the sample.
o. After blasting the result will be displayed on the screen.
21
p. Note down the reading of measured VOD shown in the screen in presence of Manufacturer’s
Representatives and subsidiary’s representatives.
q. After testing of VOD by Digital/Electronic VOD meter, the display result shall be captured by
screenshot.
2. PRECAUTIONS
22
e. Also measure the volume of water displaced by explosives sample. Divide the mass of
explosives sample (in gm) by the volume of explosives sample (in ml) to obtain density. The
generalized formula is mentioned below.
Density of explosives sample (ρ) in gm/cc = m / v
Where,
m= mass of explosives sample (in gm)
v= volume of explosives sample (in ml)
The explosive sample was collected in a poly lay flat tube of 83mm dia. from the BMD
vehicle in the field. The Bulk explosive sample should fire with 100 gm cast booster
(PETN)/ 150gm cast booster (Emulsion) in bulk explosive sample encapsulated in
cartridge form.
23
STANDARD OPERATING PROCEDURE
FOR EVALUATING THE PERFORMANCE OF NEW NON-PERMITTED LARGE DIA (NPLD)
EXPLOSIVE DURING BLASTING TRIALS BY CMPDI IN MINES OF COAL INDIA LIMITED
The steps to be followed during performance evaluation of new NPLD explosives supplied by any
manufacturer during trial Blasting are enumerated below:
2) Taking up the matter with the concerned subsidiary requesting to provide suitable mine/
mines for carrying out the field trial where NPLD explosives are already in use so that the
performance of new NPLD explosives can be comparatively assessed with the performance
of existing NPLD explosives used by the mines where trial Blasting will be conducted. Testing
should be carried out in all possible scenarios viz. dry hole condition, watery hole condition
containing mud and broken rock. The NPLD Explosives should be used in mines having
bench height at least up to 9m so that the explosives can be loaded in blast holes as top and
bottom charge column. Drilling, blasting and initiation patterns should be technically
suggested by the technical representatives of the manufacturer. The cartridge should contain
the weight as claimed by the manufacturer.
3) Quantity to be tested
A minimum of 30 MT of NPLD Column Explosive & 10 MT of NPLD Booster Explosive shall
be supplied free of cost by the manufacturer for carrying out blasting trials. A minimum of 6
to 7 rounds of blasting trials are required for evaluation of new product of NPLD Explosives.
4) The following Technical Parameters should be examined on the surface under unconfined
condition before putting it to actual blasting to ascertain the quality. The test results of the
new product must lie within the limiting range in respect of all technical parameters specified
in the Running contract under the heading “Technical parameters for Random Testing”.
If any of the test results falls outside the range, the product shall not be recommended for
use in the mines of Coal India Limited and if re-testing is required for the failed product, the
procedure as specified in “Revised SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be followed.
c. Density of Explosive
Density of Explosive should be determined by Water Displacement Method.
d. Air Gap Sensitivity (AGS): Air Gap sensitivity is checked by maintaining a gap of 2 cm
between the donor and receiver cartridge. In order to Pass the AGS test, the receiver
cartridge should be able to get initiated in the specific gap of 2 cm from the donor cartridge.
24
e. Cap Sensitivity & Booster Sensitivity
Cap Sensitivity should be ascertained by firing the cartridge with Electric / Electronic
Detonator. The Column Explosive cartridge shall be able to get initiated by Booster cartridge
with Detonator inserted within, when initiated.
5) Blast Design and Initiation patterns should be suggested by the technical representatives of
the Manufacturer according to Hardness of the strata and Height of the Bench. Hardness of
the strata of Blasting Bench is determined with dedicated instruments.
6) Performance Evaluation of new explosive should be ascertained on the basis of blast
performance achieved during trial blasting by observing Powder Factor, Fragmentation,
Throw, Muck pile Profile, Percentage of oversized boulders w.r.t. loading equipment
deployed at the bench. A new explosive must meet the benchmark Powder Factor criterion
set by Subsidiary/Coal India Limited for the mine/patch/bench/method of production, as the
case may be.
After each last the mucking operation should be observed and analyzed using Digital Image
Analysis Technique. There should not be any Misfire during trial blasting. If there takes place
any Misfire during blasting trial, the product should not be recommended for use in the mines
of Coal India Limited and if re-testing is required for the failed product, the procedure as
specified in “Revised SOP for inclusion of new products of Explosive manufacturers in CIL
approved product list of Explosives & Accessories” shall be followed.
In order to determine the actual / exact quantity of explosives loaded / poured into all the
blasting trial records should be properly documented along with observations, if any and
should be duly signed by representatives of mine officials, representative of respective
manufacturer and representatives of CMPDI and should be enclosed in the final report as
Annexure-II.
-----x-----
Blasting trial was carried out in all possible scenarios viz. dry
2 hole condition, watery hole condition containing mud and
broken rock.
25
A minimum of 30 MT of NPLD Column Explosive & 10 MT of
NPLD Booster Explosive was supplied free of cost by the
5
manufacturer.
26
Annexure – I (a)
Specified limit as
8 Test Conducted Results Remarks
per RC
(i) Physical Condition Shall be good
(ii) Velocity of detonation (m/sec) ≥4000
(iii) Density (g/cc) 1.15 ± 0.05
As per 4 (d) of
(iv) Air Gap Sensitivity Test
SOP
As per 4 (e) of
(v) Cap Sensitivity Test
SOP
9. Final result:
27
Annexure – I (b)
Specified limit as
8 Test Conducted Results Remarks
per RC
(i) Physical Condition Shall be good
(ii) Velocity of detonation (m/sec) ≥3500
(iii) Density (g/cc) 1.15 ± 0.05
As per 4 (d) of
(iv) Air Gap Sensitivity Test
SOP
As per 4 (e) of
(v) Booster Sensitivity Test
SOP
9. Final result:
28
Annexure–II
RECORD OF BLASTING TRIAL OF NEW NPLD EXPLOSIVE
29
G Sketch Showing the Pattern of Holes, Placement of Nonel / Cord Relay /DF
Electronic Detonator and Sequence of Delay
H Section of Holes Showing the Charge Distribution and the Height of Stemming
Column
30
Appendix-1
1. STEPS TO MEASURE VOD OF NPLD BOOSTER/ PRIME WITH DIGITAL/ ELECTRONIC
VOD METER
31
o. Note down the reading of measured VOD shown in the screen in presence of Manufacturer’s
Representatives and subsidiary’s representatives.
p. After testing of VOD by Digital/Electronic VOD meter, the display result shall be captured by
screenshot.
b. Take the NPLD (COLUMN) of unknown VOD and one Booster/Prime NPLD explosives for
initiation of NPLD column explosives
c. Take a pair of twisted cables (Preferably Green and Red). Green cable as Start Probe and
Red Cable as Stop Probe and keep both probes (Start & Stop Probe) in open circuit as
shown in figure. (enclosed).
d. Now tie two of these cables to NPLD Column explosives cartridge at a distance (Exactly) of
10cm/15 cm/20 cm (Probe Distance) as per given figure.
e. After binding cables on the NPLD Column cartridge, measure the distance between the
cables and make sure that the distance should not increase or decrease as per the distance
set for the explosive sample to be tested.
f. There will be 2 ends for Start Probe (Green) and 2 ends for Stop Probe (Red) as shown in
Figure.
g. Take a 3 core (Preferably one green, one red and one black) Cable (1.5mm Square copper
wire) in required length to safeguard the Operator and instrument (Preferably 100m).
h. One end of the Start Probe (Green) and one end of the Stop Probe (Red Cables) are to be
joined and make 4 cores to 3 cores.
32
i. The Probes taken from NPLD Column cartridges (Start, Stop and Common) are to be
connected to 100m, 3 core cable (Green to Green, Red to Red and remaining Green and
Red to Black).
j. Other end of the 3-core cable has to be connected to the Digital/ Electronic VOD Meter, Start
Probe to Start Pin, Stop Probe to Stop Pin and Common Probe to Common Pin. By this, the
total circuit will be in open condition.
k. Now put on the unit by pressing the “ON” button and input the required data to the Digital/
Electronic VOD meter.
l. Finally, the NPLD Column cartridge has to be kept in close contact with NPLD Booster/ Prime
to initiate it.
m. The Nonel/ detonating Fuse has to be inserted into the NPLD Booster/ Prime cartridge.
n. Now press the Test Button on the Unit.
o. After taking proper shelter, the blaster shall initiate the sample.
p. After blasting, the result will be displayed on the screen.
q. Note down the reading of measured VOD shown in the screen in presence of Manufacturer’s
Representatives and subsidiary’s representatives.
r. After testing of VOD by Digital/Electronic VOD meter, the display result shall be captured by
screenshot.
33
3. MEASUREMENT OF DENSITY OF NPLD (BOOSTER/COLUMN) EXPLOSIVE BY WATER
DISPLACEMENT METHOD
Air gap sensitivity was checked by maintaining a gap of 2 cm for emulsion explosives
between the donor and receiver cartridge. In order to pass the AGS the receiver cartridge
should get initiated in the specified gap of 2 cm for emulsion explosives from the donor
cartridge.
34
STANDARD OPERATING PROCEDURE
FOR EVALUATING THE PERFORMANCE OF NEW PERMITTED SMALL DIA (PSD) DURING
BLASTING TRIALS BY CMPDI IN MINES OF COAL INDIA LIMITED
The steps to be followed during performance evaluation of new PSD explosives supplied by any
manufacturer during trial Blasting are enumerated below:
2) Taking up the matter with the concerned subsidiary requesting to provide suitable mine/
mines for carrying out the field trial where PSD explosives are already in use so that the
performance of new PSD explosives can be comparatively assessed with the performance
of existing PSD explosives used by the mines where blasting trials will be conducted. Testing
should be carried out in all possible scenarios viz. dry hole condition, watery hole condition
containing mud and broken rock. The cartridge should contain the weight as claimed by the
manufacturer. In case of any permitted explosive product having valid PESO and DGMS
approval for degree one and included under the proven list of CIL for degree one gassiness,
it should not be treated as new product for evaluating the performance of explosive if there
is no change in the chemical composition. In case of any change / modification / alteration in
the chemical composition of the product or introduction of any new formulation duly approved
by PESO and DGMS, it should be treated as new product.
3) Quantity to be tested
Minimum 200 Kg shall be supplied free of cost by the manufacturer for carrying out blasting
trials. A minimum of 15 to16 rounds of blasting trials are required for evaluation of a new
product of Permitted Small Dia. Explosive (PSD).
4) The following Technical Parameters should be examined on the surface under unconfined
condition before putting it to actual blasting to ascertain the quality. The test results of the
new product must lie within the limiting range in respect of all technical parameters specified
in the Running contract under the heading “Technical parameters for Random Testing”.
If any of the test results falls outside the range, the product shall not be recommended for
use in the mines of Coal India Limited and if re-testing is required for the failed product, the
procedure as specified in “Revised SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be followed.
c. Density of Explosive
Density of Explosive should be determined by Water Displacement Method.
35
e. Continuity of Detonation (COD):
Continuity of detonation should be checked by rolling the cartridge inside a manila paper and
a train of 1m length of explosive column is fired with electric / electronic detonator. For
passing the continuity of detonation (COD) the entire explosive column should get fired.
f. Cap-Sensitivity:
Cap-sensitivity should be ascertained by firing the cartridge with electric / electronic
detonator.
The test results of the new product shall be properly documented and should be duly signed
by representative of mine, representative of respective manufacturer and representatives of
CMPDI and shall be enclosed in the final report as Annexure-I.
Then after each blasting trial, the mucking operation should be observed and analyzed using
Digital Image Analysis Technique. There should not be any Misfire during trial blasting. If
there takes place any Misfire during blasting trial, the product should not be recommended
for use in the mines of Coal India Limited and if re-testing is required for the failed product,
the procedure as specified in “SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be
followed.
7) In order to determine the actual / exact quantity of explosives loaded into all the blasting
trials, the records should be properly documented along with observations, if any and should
be duly signed by representatives of mine officials, representatives of respective
manufacturer and representatives of CMPDI and should be enclosed in the final report as
Annexure-II.
-----x----
36
Checklist to be followed during Blasting trials of
New Permitted Small Dia. (PSD) Explosive
SI.
Particulars Yes No
No.
37
Annexure – I
Specified limit as
8 Test Conducted Results Remarks
per RC
Slurry / Emulsion
(i) Physical Condition
type
(ii) Velocity of detonation (m/sec) 3500 ± 400
(iii) Density (g/cc) 1.15 ± 0.05
As per 4 (d) of
(iv) Air gap Sensitivity Test
SOP
As per 4 (e) of
(v) Continuity of Detonation Test
SOP
As per 4 (f) of
(vi) Cap-Sensitivity Test
SOP
As per 4 (g) of
(vii) Water Resistance Test
SOP
9. Final result:
38
Annexure–II
39
F Sketch Showing the Pattern of Holes, Placement of Detonator and Sequence of
Delay
40
Appendix-1
a. Take the PSD explosives of unknown VOD and roll the PSD explosive samples inside a
manila paper and make a train of 1 m length of PSD explosive of unknown VOD to the testing
site.
b. Take a pair of twisted cables (Preferably Green and Red). Green cable as Start Probe and
Red Cable as Stop Probe and keep both probes (Start & Stop Probe) in open circuit as
shown in figure (enclosed).
c. Now tie two of these cables to PSD explosives at a distance (Exactly) of 10cm/15 cm/20 cm
(Probe Distance) as per given figure.
d. After binding cables on PSD explosives, measure the distance between the cables and make
sure that the distance should not increase or decrease as per the distance set for the
explosive sample to be tested.
e. There will be 2 ends for Start Probe (Green) and 2 ends for Stop Probe (Red) as shown in
Figure.
f. Take a 3 core (Preferably one green, one red and one black) Cable (1.5mm Square copper
wire) in required length to safeguard Operator and instrument (Preferably 100m)
g. One end of the Start Probe (Green) and one end of the Stop probe (Red Cables) are to be
joined and make 4 cores to 3 cores.
h. The Probes taken from PSD explosives (Start, Stop and Common) are to be connected to
100m, 3 core cables (Green to Green, Red to Red and remaining Green and Red to Black).
i. Other end of the 3-core cable has to be connected to the Digital/ Electronic VOD Meter, Start
Probe to Start Pin, Stop probe to Stop Pin and Black to Common Pin. By this, the total circuit
will be in open condition.
j. Now put on the unit by pressing the “ON” button and input the required data to the Digital/
Electronic VOD meter.
k. Finally, the PSD explosives have to be connected with the Nonel/ Detonating Fuse to initiate
it.
l. The Nonel/ Detonating Fuse has to be inserted into the PSD explosives towards the Start
probe (Green Probe) and to be inserted in such a fashion that the Nonel/ Detonating Fuse
should not be very near to the start probe (a little far from it) and the other end of the detonator
will be connected to Exploder.
m. Now press the Test Button on the Unit.
n. After taking proper shelter, the blaster shall initiate the sample.
41
o. After blasting, the result will be displayed on the screen.
p. Note down the reading of measured VOD shown in the screen in presence of Manufacturer’s
Representatives and subsidiary’s representatives.
q. After testing of VOD by Digital/Electronic VOD meter, the display result shall be captured by
screenshot.
42
3. MEASUREMENT OF AIR GAP SENSITIVITY
Air gap sensitivity was checked by maintaining a gap of 2 cm for emulsion explosives
between the donor and receiver cartridge. In order to pass the AGS the receiver cartridge
should get initiated in the specified gap of 2 cm for emulsion explosives from the donor
cartridge.
4. MEASUREMENT OF CONTINUATION OF DETONATION
Take the PSD explosives and roll the PSD explosive samples inside a manila paper and
make a train of 1 m length of PSD explosive. 1m of Permitted sample should be initiated with
No. 6/8 strength Detonator.
43
STANDARD OPERATING PROCEDURE
FOR EVALUATING THE PERFORMANCE OF NEW CAST BOOSTER DURING BLASTING
TRIALS BY CMPDI IN MINES OF COAL INDIA LIMITED
The steps to be followed during performance evaluation of new Cast booster supplied by any
manufacturer during blasting trials are enumerated below:
1) Verification of Necessary Documents submitted by the manufacturer pertaining to
● Valid Manufacturing License of the product granted by PESO
● DGMS Permission, if applicable
● Product Literature
2) Taking up the matter with the concerned subsidiary requesting to provide suitable mine /
mines for carrying out the field trials where Cast booster is already in use so that the
performance of new Cast booster can be comparatively assessed with the performance of
Cast booster used by the mines where blasting trials will be conducted. Testing should be
carried out in all possible scenarios viz. dry hole condition, watery hole condition containing
mud and broken rock. The cartridge should contain the weight as claimed by the
manufacturer.
3) Quantity to be tested
Minimum 60 kg of Cast Booster (PETN / TNT) or 60 kg of Cast Booster (Emulsion) is to be
supplied free of cost by the manufacturer for carrying out blasting trials. A minimum of 6 to 7
rounds of blasting trials are required for evaluation of the new product of Cast booster.
4) The following Technical Parameters should be examined on the surface under unconfined
condition before putting it to actual blasting to ascertain the quality. The test results of the
new product must lie within the limiting range in respect of all technical parameters specified
in the Running contract under the heading “Technical parameters for Random Testing”.
If any of the test results falls outside the range, the product shall not be recommended for
use in the mines of Coal India Limited and if re-testing is required for the failed product, the
procedure as specified in “Revised SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be followed.
c. Cap-sensitivity: The sensitivity of the Cast booster should be checked by employing cast
booster along with the bulk explosive encapsulated in cartridge form to perform the test.
When initiated the Cast Booster shall get initiated & it shall in turn be able to detonate the
Bulk Explosive cartridge.
d. Water Resistance: At first the cast booster shall be immersed in water for 24 hours, it
should be able to get fired when fired with electric / electronic detonator.
There should not be any Misfire during trial blasting. If there takes place any Misfire during
trial blasting, the product should not be recommended for use in the mines of Coal India
44
Limited and if re-testing is required for the failed product, the procedure as specified in
“Revised SOP for inclusion of new products of Explosive manufacturers in CIL approved
product list of Explosives & Accessories” shall be followed.
5) Trial Blast records should be properly documented along with observations, if any and should
be duly signed by representatives of mine, representatives of respective manufacturer and
representative of CMPDI and should be enclosed in the final report as Annexure-II.
SI.
Particulars Yes No
No.
Blasting trials were carried out in all possible scenarios viz. dry
2 face / hole condition, watery face / hole condition containing
mud and broken rock.
Was the Cast booster containing the weight as claimed by the
3
manufacturers?
A minimum quantity Cast Booster (as mentioned below) was
supplied free of cost by the manufacturer.
4
Cast Booster (PETN / TNT): 60 Kg
Cast Booster (Emulsion) : 60 Kg
5 A minimum of 6 to 7 rounds of blasting trials were conducted.
45
Annexure – I (a)
Specified limit as
8 Test Conducted Results Remarks
per RC
(i) Physical Condition Shall be good
(ii) Velocity of detonation (m/sec) ≥ 6000
(iii) Density (g/cc) 1.50 – 1.60
As per 4 (d) of
(iv) Cap-Sensitivity Test
SOP
As per 4 (e) of
(vii) Water Resistance Test
SOP
9. Final result:
46
Annexure – I (b)
Specified limit as
8 Test Conducted Results Remarks
per RC
(i) Physical Condition Shall be good
(ii) Velocity of detonation (m/sec) ≥ 4800
(iii) Density (g/cc) 1.15 – 1.25
As per 4 (d) of
(iv) Cap-Sensitivity Test
SOP
As per 4 (e) of
(vii) Water Resistance Test
SOP
9. Final result:
47
Annexure–II
RECORD OF BLASTING TRIAL OF NEW CAST BOOSTER
48
G Section of Holes Showing the Charge Distribution and the Height of Stemming
Column
49
Appendix-1
a. Take the Cast Booster of unknown VOD and roll the Cast Booster samples inside a manila
paper and make a train of 1 m length of Cast Booster of unknown VOD to the testing site.
b. Take a pair of twisted cables (Preferably Green and Red). Green cable as Start Probe and
Red Cable as Stop Probe and keep both probes (Start & Stop Probe) in open circuit as
shown in figure (enclosed).
c. Now tie two of these cables to Cast Booster at a distance (Exactly) of 10cm/15 cm/20 cm
(Probe Distance) as per given figure.
d. After binding cables on cast Booster samples, measure the distance between the cables and
make sure that the distance should not increase or decrease as per the distance set for the
sample to be tested.
e. There will be 2 ends for Start Probe (Green) and 2 ends for Stop Probe (Red).
f. Take a 3 core (Preferably one green, one red and one black) Cable (1.5mm Square copper
wire) in required length to safeguard Operator and instrument (Preferably 100m)
g. One end of the Start Probe (Green) and one end of the Stop Probe (Red Cables) are to be
joined and make 4 cores to 3 core.
h. The Probes taken from Cast Booster (Start, Stop and Common) are to be connected to
100m, 3 core cable (Green to Green, Red to Red and remaining Green and Red to Black).
i. Other end of the 3-core cable has to be connected to the Digital/ Electronic VOD Meter, Start
Probe to Start Pin, Stop Probe to Stop Pin and Black to Common Pin. By this, the total circuit
will be in open condition.
j. Now put on the unit by pressing “ON” button and input the required data to the Digital/
Electronic VOD meter.
k. Finally, the Cast Booster has to be connected with the Nonel/ detonating Fuse to initiate it.
l. The Nonel/ Detonating Fuse has to be inserted into the Cast Booster towards the start probe
(Green Probe) and to be inserted in such a fashion that the Nonel/ Detonating Fuse should
not be very near to the start probe (a little far from it) and the other end of the detonator will
be connected to Exploder.
m. Now press the Test Button on the Unit.
n. After taking proper shelter, blaster shall initiate the sample.
o. After blasting the result will be displayed on the screen.
p. Note down the reading of measured VOD shown in the screen in presence of Manufacturer’s
Representatives and subsidiary’s representatives.
50
q. After testing of VOD by Digital/Electronic VOD meter, the display result shall be captured by
screenshot.
Water resistance is ascertained by firing the cast booster with detonator after immersing it in
water.
51
STANDARD OPERATING PROCEDURE
FOR EVALUATING THE PERFORMANCE OF
NEW DETONATING FUSE DURING
BLASTING TRIALS BY CMPDI IN MINES OF COAL INDIA LIMITED
The steps to be followed during performance evaluation of new Detonating Fuse (DF) supplied by
any manufacturer during Blasting trials are enumerated below:
2) Taking up the matter with the concerned subsidiary requesting to provide suitable mine /
mines for carrying out the field trials where Detonating Fuse (DF) of other manufacturers is
already in use so that the performance of new Detonating Fuse product can be comparatively
assessed with the performance of existing Detonating Fuse used by the mines where
Blasting trials will be conducted. Testing should be carried out in all possible scenarios viz.
dry face / hole condition, wet face / hole condition containing mud and broken rock.
3) Quantity to be tested
A minimum length of 5000 m is to be supplied free of cost by the manufacturer for carrying
out Blasting trials. A minimum of 6 to 7 rounds of blasting trials are required for evaluation of
new product of Detonating Fuse.
4) The following technical parameters should be examined on the surface under unconfined
condition before putting it to actual blasting to ascertain the quality. The test results of the
new product must lie within the limiting range in respect of all technical parameters specified
in Running Contract under the head “Technical parameters for Random Testing”.
If any of the test results falls outside the range, the product shall not be recommended for
use in the mines of Coal India Limited and if re-testing is required for the failed product, the
procedure as specified in “Revised SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be followed.
b. Diameter:
The nominal diameter of the detonating fuse when measured as prescribed in 3.2 of IS -
6609 should be within 4.5 to 5.5 mm.
There should not be any Misfire during trial blasting. If there takes place any Misfire during
blasting trials, the product should not be recommended for use in the mines of Coal India
52
Limited and if re-testing is required for the failed product, the procedure as specified in
“Revised SOP for inclusion of new products of Explosive manufacturers in CIL approved
product list of Explosives & Accessories” shall be followed.
5) Records of blasting trials should be properly documented along with observations, if any and
should be duly signed by representative of mine, representative of respective manufacturer
and representative of CMPDI and should be enclosed in the Final Report as Annexure II.
SI.
Particulars Yes No
No.
53
Annexure – I
Specified limit as
8 Test Conducted Results Remarks
per RC
(i) Physical Condition Shall be good
(ii) Nominal Diameter (mm) 4.5 - 5.5
(iii) Unconfined VOD (m/sec) ≥ 6000
As per 4(d) of
(iv) Transmission of Detonation
SOP
9. Final result:
54
Annexure–II
55
F Sketch Showing the Pattern of Holes, Placement of Nonel / DF/ Cord Relay /
Electronic Detonator and Sequence of Delay
G Section of Holes Showing the Charge Distribution and the Height of Stemming
Column
56
Appendix-1
57
2. MEASUREMENT OF DIAMETER
The nominal diameter of the detonating fuse was measured by Vernier calipers. The Dia.
Detonating fuse should lie within limit as per RC of CIL.
The Detonating Fuse is laid down as a main line and branching is laid at different angles from
the main line by making a loop (as prescribed in 3.7 of IS-6609 (Part I-1972)). When fire, there
shall be no failure in DF either in the main line or in the branch line.
58
STANDARD OPERATING PROCEDURE
FOR EVALUATING THE PERFORMANCE OF NEW NONEL DURING
BLASTING TRIALS BY CMPDI IN MINES OF COAL INDIA LIMITED
The steps to be followed during performance evaluation of new NONEL supplied by any
manufacturer during trial Blasting are enumerated below:
2) Taking up the matter with the concerned subsidiary requesting to provide suitable mine /
mines for carrying out the field trials where NONEL of other manufacturers are already in use
so that, the performance of new NONEL product can be comparatively assessed with the
performance of existing NONEL used by the mines where trial Blasting will be conducted.
Testing should be carried out in all possible scenarios viz. dry hole condition, watery hole
condition containing mud and broken rock. NONEL should be used to provide designed delay
time as Inter- deck delay, inter-hole delay and inter-row delay during trial blasting.
3) Quantity to be tested
A minimum of 5500 m of length or 600 No’s of quantity, whichever is larger, is to be supplied
free of cost by the manufacturer for carrying out Blasting trials. A minimum of 6 to 7 rounds
of blast are required for evaluation of the new product of NONEL.
4) The following Technical Parameters should be examined on the surface under unconfined
condition before putting it to actual blasting to ascertain the quality. The test results of the
new product must lie within the limiting range in respect of all technical parameters specified
in the Running contract under the head “Technical parameters for Random Testing”.
If any of the test results falls outside the range, the product shall not be recommended for
use in the mines of Coal India Limited and if re-testing is required for the failed product, the
procedure as specified in “Revised SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be followed.
b. Strength Test:
The Strength test should be determined by the lead plate method. The test procedure
followed should be in accordance with requirements as laid down in IS: 6609 of 1973. After
the blast the dent / crater produced on the lead plate should correspond to at least C.3 class.
59
e. Load Test:
Load Test should be carried out to determine the capability of the shock tube to withstand
dynamic load while charging explosives in a shot hole. Two 125 mm cartridges each weighing
6.25 kg should be tied along with shock tube and kept on hanging for 15 minutes. It should
be then brought out and the shock tube should be examined for any physical deformity such
as cracks, elongation etc. If it is found in order, then above tested shock tube should be fired
on the surface.
The test results of the new product shall be properly documented and should be duly signed
by representatives of mine officials, respective manufacturer’s representatives and CMPDI
representatives and shall be enclosed in the Final report as Annexure I.
There should not be any Misfire during trial blasting. If there takes place any Misfire during
trial blasting, the product should not be recommended for use in the mines of Coal India
Limited and if re-testing is required for the failed product, the procedure as specified in
“Revised SOP for inclusion of new products of Explosive manufacturers in CIL approved
product list of Explosives & Accessories” shall be followed.
5) Trial Blast records should be properly documented along with observations, if any and should
be duly signed by representatives of mine, representatives of respective manufacturer and
representative of CMPDI and should be enclosed in the Final Report as Annexure-II.
60
Checklist to be followed during Blasting trials of
New Nonel
SI.
Particulars Yes No
No.
61
Annexure – I
9. Final result:
62
Annexure–II
63
F Sketch Showing the Pattern of Holes, Placement of Nonel and Sequence of
Delay
64
STANDARD OPERATING PROCEDURE
FOR EVALUATING THE PERFORMANCE OF
NEW ELECTRONIC DETONATOR DURING
BLASTING TRIALS BY CMPDI IN MINES OF COAL INDIA LIMITED
The steps to be followed during performance evaluation of new Electronic Detonator supplied by
any manufacturer during blasting trials are enumerated below:
2) Taking up the matter with the concerned subsidiary through CIL requesting to provide
suitable mine / mines for carrying out the field trial where Electronic Detonator of other
manufacturers is already in use so that the performance of new Electronic Detonator product
can be comparatively assessed with the performance of existing Electronic Detonator used
by the mines where Blasting trials will be conducted. Testing should be carried out in all
possible scenarios viz. dry hole condition, watery hole condition containing mud and broken
rock. Electronic Detonator should be used to provide designed delay time during trial
blasting.
3) Quantity to be tested
A minimum quantity of 500 No’s is to be supplied free of cost by the manufacturer for carrying
out Blasting trials. A minimum of 6 to 7 rounds of blasting trials are required for evaluation of
a new product of Electronic Detonator.
4) The following Technical Parameters should be examined on the surface under unconfined
conditions before putting it to actual blasting trials to ascertain the quality. The test results of
the new product must lie within the limiting range in respect of all technical parameters
specified in the Running contract under the heading “Technical parameters for Random
Testing”.
If any of the test results falls outside the range, the product shall not be recommended for
use in the mines of Coal India Limited and if re-testing is required for the failed product, the
procedure as specified in “Revised SOP for inclusion of new products of Explosive
manufacturers in CIL approved product list of Explosives & Accessories” shall be followed.
The Strength test should be determined by the lead plate method. The test procedure
followed should be in accordance with requirements as laid down in the following procedure.
When the detonators are subjected to the test as prescribed in 4.6 of IS 6609 (Part 3), the
general electronic detonators shall produce dent on the lead plate corresponding to at least
C-3 class [4.6.3.3 of IS 6609 (Part 3)]
Whereas, permitted electronic detonators shall produce dent on the lead plate corresponding
65
to at least B-3 class [4.6.3.3 of IS 6609 (Part 3)].
e. Snatch Test:
When subjected to the snatch test as prescribed in 4.3 of IS 6609 (Part 3), the detonators
shall not fire when a jerk is applied to the lead wires.
f. Drop Test
When subjected to a drop test as prescribed in 4.2 of IS 6609 (Part 3), none of the detonators
shall detonate on impact and after the test, each tested sample shall be checked again for
its firing characteristic. All detonators shall be functional after the drop test.
The 10 No’s Electronic Detonators shall be immersed in water continuously for 24 hours.
Then they shall be subjected to the firing test, when tested all the Electronic Detonators shall
be able to fire without fail
As the Electronic Detonators are supplied with Connectors, bus wires, Logger and Blaster,
hence the connected accessories should be visually checked for the following features-
i. Connectors should have good quality and effective contact with bus wire.
ii. Bus-wires should be good strength to not snapped during blasting
iii. Logger and blaster should be Password protected access
iv. Fire cap is not charged until the “Pre-Fire” command is sent
v. Built in automatic defuse feature
vi. Detection and alert of short circuit events
vii. On field self-diagnostic tests
viii. Detonator attendance verification prior to blasting
Logger should have facility to transfer the log events with Hole ID, Delay Timing either
through Bluetooth or any data transfer protocol.
The test results of the new product shall be properly documented and should be duly signed
by representative of mine, representative of respective manufacturer and representative of
CMPDI and shall be enclosed in the Final Report as Annexure-I.
There should not be any Misfire during trial blasting. If there takes place any Misfire during
blasting trials, the product should not be recommended for use in the mines of Coal India
Limited and if re-testing is required for the failed product, the procedure as specified in
66
“Revised SOP for inclusion of new products of Explosive manufacturers in CIL approved
product list of Explosives & Accessories” shall be followed.
5) Records of blasting trials should be properly documented along with observations, if any and
should be duly signed by representative of mine, representative of respective manufacturer
and representative of CMPDI and should be enclosed in the Final Report as Annexure-II.
67
Annexure – I
9. Final result:
68
Annexure–II
69
F Sketch Showing the Pattern of Holes, Placement of Electronic Detonator and
Sequence of Delay
70