Generator Circuit Breaker ‐ Site Acceptance Test Procedures (SAT)-Rev01
Generator Circuit Breaker ‐ Site Acceptance Test Procedures (SAT)-Rev01
Main Contractor
Page
Copyright © Elsewedy Electric for Power Systems Projects. All rights reserved. The reproduction, disclosure or use of this
document or its contents is forbidden without express written authority from Elsewedy Electric for Power System Project.
1/10
Reinforcement of Rabigh Power Plant Saudi Electricity Company
CONSORTIUM OF
ELSEWEDY ELECTRIC-PSP AND SIEMENS ENERGY
Project Commissioning
01 16 January 2025 Commissioning Engineer Project Manager
Manager
Rev Date Prepared by Reviewed by Approved by
i. Changes in this document after Rev. 0 will be highlighted by means of color highlighting/cloud or vertical line at
the left-hand side of the change text
TABLE OF CONTENTS
1.0 INTRODUCTION
This procedure covers the scope of commissioning work and certification of the Generator Circuit breaker (GCB) of
Rabigh Reinforcement Independent Power Plant.
2.0 PURPOSE
The purpose of this commissioning procedures is:
1) To establish systematic identification methods for the system and subsystem components.
2) This identification includes checking physical condition and ensure equipment conformity with the project
requirements.
3) To confirm that the system parts of GCB are installed according to the project specifications.
4) To provide the methods and means for commissioning of this system thoroughly and safely within its design
boundaries.
5) Checking the system subsystem protection for safe and reliable operation.
3.0 SCOPE
3.1 The subsystems under the scope of this procedure are as followings:
1) Generator Circuit Breaker includes:
4.0 ABBREVIATIONS
5.0 REFERENCES
8.0 COMMISSIONING
The objective of this procedure is to provide the procedural steps necessary to prepare this system for operation.
Type of
S/n Description Check Result
1 Nameplate information verified Visual
2 Earthing system connections check as approved drawing Visual
3 Cleanliness inside Panel Visual
4 Earthing of GCB Structure and pole frame Visual
5 Density indicator healthiness Visual
6 CB operation counter Visual
7 CT and VT connections and tightness Visual
8 Door Handles, keys & Hinges Visual
9 Mechanical position indicator Visual
10 Connection between GCB enclosure and IPB enclosure Visual
8.2 SF6 Pressure Gauge Test.
8.2.1 Pressure Gauge Calibration Test
Check operating and resetting pressure.
Operating pressure (Po), Resetting pressure (Pr), Setting pressure (Ps)
Po = Ps±0.2bar
Setting Operating Resetting
Temp.
Compartment Description pressure Ps pressure pressure Result
°C
(bar) Po (bar) Pr (bar)
1st low-pressure alarm
GCB nd
2 low pressure alarm (T1)
2nd low pressure alarm (T2)
Secondary wiring shall be checked to ensure that all connections are made in accordance with the Schematic
drawing. Relays and other devices should be checked by actual operation, if feasible. Those circuits for which
operation is not feasible shall be checked for continuity. A check shall be made for the proper sequence of
operation of mechanically operated auxiliary switches and devices.
The DC resistance of the current-carrying circuit from terminal to terminal of each pole unit in the closed
position shall be measured with at least 100 A flowing in the circuit.
Injected
R- PHASE (micro Ω) Y- PHASE (micro Ω) B- PHASE (micro Ω)
Current
Measured Designed Measured Designed Measured
Designed Value
value Value value Value value
100 A DC
Timing tests are made to determine the time required for circuit breakers or components to operate during open,
close, and close-open operations. C.B Timing Test at rated voltage and rated gas density pressure
REF R- PHASE (mS) Y- PHASE (mS) B- PHASE (mS)
Trip Coil 1
Trip Coil 2
Close Time
- Acceptance Criteria:
The measured values should be in conformance with the values in the factory acceptance test.
The instrument print-out should be attached.
- The measured values should be in conformance to the values in the factory acceptance test.
- Device printout shall be attached.
1 8.9 Voltage Transformer Test
8.9.1 VT Insulation Resistance Test
- The purpose is to ensure the insulation resistance of VTs which are installed inside the MV Switchgear
Test Procedure
- Primary-Earth.
- Primary-Secondary
VT Applied
Connection R-Phase (GΩ) Y-Phase (GΩ) B-Phase (GΩ)
Designation Voltage/ MIN
Pri. to earth 5KV/1MIN
- Insert the VT data (Serial, Manufacture, Ratio, protection class) into the VT analyzer.
- Start the test and review the Test result with the actual VT data.
Winding
VT Designation Ph Ref. Core No. Terminal Measured ratio Error% Polarity
Resistance
R-Phase Core 1 a-n