Generator Circuit Breaker ‐ Site Acceptance Test Procedures (SAT)-Rev01

This document outlines the Site Acceptance Test Procedures (SAT) for the Generator Circuit Breaker (GCB) at the Rabigh Reinforcement Independent Power Plant, commissioned by the Saudi Electricity Company. It details the commissioning process, safety precautions, and specific tests required to ensure the GCB meets project specifications and operates reliably. The document includes a revision history and a table of contents for easy navigation.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views10 pages

Generator Circuit Breaker ‐ Site Acceptance Test Procedures (SAT)-Rev01

This document outlines the Site Acceptance Test Procedures (SAT) for the Generator Circuit Breaker (GCB) at the Rabigh Reinforcement Independent Power Plant, commissioned by the Saudi Electricity Company. It details the commissioning process, safety precautions, and specific tests required to ensure the GCB meets project specifications and operates reliably. The document includes a revision history and a table of contents for easy navigation.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Employer

Saudi Electricity Company

Main Contractor

THE CONSORTIUM OF SIEMENS ENERGY GLOBAL


GMBH & CO. KG.& ELSEWEDY ELECTRIC PSP
Project

Reinforcement of Rabigh Power Plant

01 16/01/2025 Incorporating Client comments MH EA RY


00 12/11/2024 Issued for approval MH EA RY
Rev. Date Details of revision Created Checked Approved
Contract
Scale NTS Size A4 Origin. No.xx Rev. A No.
-----------
Originator Title

Generator Circuit Breaker (GCB)


‐ Site Acceptance Test Procedures (SAT)

Document no. Rev.


2011‐BAC‐EDC030‐000034
01

Page
Copyright © Elsewedy Electric for Power Systems Projects. All rights reserved. The reproduction, disclosure or use of this
document or its contents is forbidden without express written authority from Elsewedy Electric for Power System Project.
1/10
Reinforcement of Rabigh Power Plant Saudi Electricity Company

CONSORTIUM OF
ELSEWEDY ELECTRIC-PSP AND SIEMENS ENERGY

PROJECT SPECIFIC PROCEDURE

Generator Circuit Breaker (GCB)


‐ Site Acceptance Test Procedures (SAT)

Project : RABIGH REINFORCEMENT INDEPENDENT POWER PLANT

Employer : SAUDI ELECTRICITY COMPANY (SEC)

Contractor : CONSORTIUM OF ELSEWEDY ELECTRIC-PSP AND SIEMENS ENERGY

Project Commissioning
01 16 January 2025 Commissioning Engineer Project Manager
Manager
Rev Date Prepared by Reviewed by Approved by

2011-BAC-EDC030-000034 Rev.01 Page 2 of 10


Reinforcement of Rabigh Power Plant Saudi Electricity Company

REVISION RECORD SHEET

i. Changes in this document after Rev. 0 will be highlighted by means of color highlighting/cloud or vertical line at
the left-hand side of the change text

Rev. Prepared Reviewed Approved


Date Description of Revision
No. by by by

00 12 November 2024 Issued for Approval and implementation MH EA RY


01 16 January 2025 Incorporating Client comments MH EA RY

MH: Mahmoud Hassan


EA: Ehab Anwar
RY: Rafea Youssef

2011-BAC-EDC030-000034 Rev.01 Page 3 of 10


Reinforcement of Rabigh Power Plant Saudi Electricity Company

TABLE OF CONTENTS

1.0 INTRODUCTION ........................................................................................................................................................ 5


2.0 PURPOSE .................................................................................................................................................................. 5
3.0 SCOPE........................................................................................................................................................................ 5
4.0 ABBREVIATIONS ....................................................................................................................................................... 5
5.0 REFERENCES ........................................................................................................................................................... 5
6.0 PRE- REQUISITE ....................................................................................................................................................... 6
7.0 SAFETY / ENVIRONMENTAL PRECAUTIONS ......................................................................................................... 6
8.0 COMMISSIONING ...................................................................................................................................................... 7
9.0 ATTACHMENTS ....................................................................................................................................................... 10

2011-BAC-EDC030-000034 Rev.01 Page 4 of 10


Reinforcement of Rabigh Power Plant Saudi Electricity Company

1.0 INTRODUCTION
This procedure covers the scope of commissioning work and certification of the Generator Circuit breaker (GCB) of
Rabigh Reinforcement Independent Power Plant.

2.0 PURPOSE
The purpose of this commissioning procedures is:
1) To establish systematic identification methods for the system and subsystem components.

2) This identification includes checking physical condition and ensure equipment conformity with the project
requirements.

3) To confirm that the system parts of GCB are installed according to the project specifications.

4) To provide the methods and means for commissioning of this system thoroughly and safely within its design
boundaries.

5) Checking the system subsystem protection for safe and reliable operation.

3.0 SCOPE
3.1 The subsystems under the scope of this procedure are as followings:
1) Generator Circuit Breaker includes:

- 3x GT Generator Circuit Breaker.

- 1x ST Generator Circuit Breaker.

4.0 ABBREVIATIONS

4.1 CCC - Commissioning Completion Certificate


4.2 ECC - Erection Clearance Certificate
4.3 KKS - Identification System for Power Plants
4.4 PTW - Permit to Work
1 4.5 GCB - Generator Circuit Breaker
4.6 SA - Surge Arrester

5.0 REFERENCES

5.1 2011-B-EFA010-010003 - Over All Single Line Drawing


- GT-Generator Circuit Breaker - Schematic, Wiring and
5.2 2011-BAC01-EMA010-305515
Connection Diagrams
- ST-Generator Circuit Breaker - Schematic, Wiring and
5.3 2011-BAC01-EMA010-305516
Connection Diagrams
5.4 2011-BAC01-EDA010-305523 - GT-Generator Circuit Breaker Technical Data Sheet

2011-BAC01-EDA010-305524 - ST-Generator Circuit Breaker Technical Data Sheet


5.5

2011-BAC-EDC030-000034 Rev.01 Page 5 of 10


Reinforcement of Rabigh Power Plant Saudi Electricity Company

6.0 PRE- REQUISITE


6.1 Erection Clearance Certificate (ECC) issued for the relevant system
1) Certificates in the turnover packages endorsed by construction team civil, and electrical engineers declaring that
the construction, electrical installation, and testing work is completed and the system is available for
commissioning.
2) All equipment installation with necessary identification KKS and labeling.
3) Electrical power is made available for system commissioning.
4) All protection and functional interlocks of electrical/mechanical equipment have been tested.
5) All instrumentation available for commissioning.
6) Punch points are accepted by all parties and points concerning safety of personnel and equipment’s safe operation
are cleared (Category A).
6.2 Preparation Works
1) PTW to be prepared for system energization.
2) The necessary documentation required to start equipment commissioning to be available such as:
a) Single line diagrams electrical
b) Equipment’s data sheet.
c) Panel Schematic.
d) Commissioning check lists & test forms.

7.0 SAFETY / ENVIRONMENTAL PRECAUTIONS


7.1 Safety
1) No work will be undertaken, regardless of the urgency, unless it fully complies with site safety and environmental
procedures.
2) Before the start of any testing, it shall be confirmed that all power supplies to the system have been isolated or that
they are in a known condition. The commissioning engineer is responsible for the safety of those personnel working
on the system. Check for the presence of harmful electrical or mechanical potential energy before starting work.
3) Confined or enclosed space entry procedures (Permit to Work) are to be reviewed and adhered to by all personnel
involved where applicable.
4) Project Lockout/Tag-out (LOTO) must be adhered to.
5) Task Safety Precaution Table

Task Safety Precautions


System Walk-down  Ensure that area is adequately lighted for safe
access
 Enforce good housekeeping
 Cordon off the test boundary points with
barrier tape and Test in Progress signs.
Commissioning team members to restrict
access to only authorized employees only
involved with test.

2011-BAC-EDC030-000034 Rev.01 Page 6 of 10


Reinforcement of Rabigh Power Plant Saudi Electricity Company

8.0 COMMISSIONING

The objective of this procedure is to provide the procedural steps necessary to prepare this system for operation.

8.1 Visual Inspection and General Checks:

Type of
S/n Description Check Result
1 Nameplate information verified Visual
2 Earthing system connections check as approved drawing Visual
3 Cleanliness inside Panel Visual
4 Earthing of GCB Structure and pole frame Visual
5 Density indicator healthiness Visual
6 CB operation counter Visual
7 CT and VT connections and tightness Visual
8 Door Handles, keys & Hinges Visual
9 Mechanical position indicator Visual
10 Connection between GCB enclosure and IPB enclosure Visual
8.2 SF6 Pressure Gauge Test.
8.2.1 Pressure Gauge Calibration Test
Check operating and resetting pressure.
Operating pressure (Po), Resetting pressure (Pr), Setting pressure (Ps)
Po = Ps±0.2bar
Setting Operating Resetting
Temp.
Compartment Description pressure Ps pressure pressure Result
°C
(bar) Po (bar) Pr (bar)
1st low-pressure alarm
GCB nd
2 low pressure alarm (T1)
2nd low pressure alarm (T2)

8.2.2 Pressure Gauge Test

Compartment Result Remarks Compartment


Alarm (OK / Not OK)
GCB
Trip (OK / Not OK)

8.2.3 SF6 Leakage Test

Compartment Result Remarks


GCB (OK / Not OK)

8.3 Control and Secondary Wiring Check

Secondary wiring shall be checked to ensure that all connections are made in accordance with the Schematic
drawing. Relays and other devices should be checked by actual operation, if feasible. Those circuits for which
operation is not feasible shall be checked for continuity. A check shall be made for the proper sequence of
operation of mechanically operated auxiliary switches and devices.

Wiring Check (OK / NOT OK)

Local Control Panel

2011-BAC-EDC030-000034 Rev.01 Page 7 of 10


Reinforcement of Rabigh Power Plant Saudi Electricity Company

8.4 Electrical Resistance of Current Path Test

The DC resistance of the current-carrying circuit from terminal to terminal of each pole unit in the closed
position shall be measured with at least 100 A flowing in the circuit.
Injected
R- PHASE (micro Ω) Y- PHASE (micro Ω) B- PHASE (micro Ω)
Current
Measured Designed Measured Designed Measured
Designed Value
value Value value Value value
100 A DC

Accepted Criteria: R measured ≤ R Designed * 1.2

8.5 IR Values Measurements Before and After HV Test

REF R-YBE (GΩ) Y-RBE (GΩ) B-YRE (GΩ)


Before HV Test
After HV Test

8.6 Dielectric Tests: Power Frequency Withstand Tests


HV Test Shall Be Performed with the Below Conditions:
8.6.1 Live parts (circuit breaker, disconnector) to ground

Applied Voltage (KV) Leakage


Content Time (min) Result Remarks
0.8 * 60 Current (A)
PH- R to Earth 1
PH- S to Earth 1
PH- T to Earth 1
Acceptance Criteria: NO Breakdown

8.7 Timing Test

Timing tests are made to determine the time required for circuit breakers or components to operate during open,
close, and close-open operations. C.B Timing Test at rated voltage and rated gas density pressure
REF R- PHASE (mS) Y- PHASE (mS) B- PHASE (mS)
Trip Coil 1
Trip Coil 2
Close Time
- Acceptance Criteria:
The measured values should be in conformance with the values in the factory acceptance test.
The instrument print-out should be attached.

1 8.8 Current Transformer Test


8.8.1 CT insulation Resistance test

Phase Applied Voltage IR Value (Giga Ohms) Result

CT Primary -GND 5kV


(1S1-1S2)-GND 1kV
(2S1-2S2)-GND 1kV
Criteria: The value of Insulation should be more than 1MegOhm/kV.

2011-BAC-EDC030-000034 Rev.01 Page 8 of 10


Reinforcement of Rabigh Power Plant Saudi Electricity Company

8.8.2 CT Ratio, Polarity, Winding Resistance, and Excitation Curve


Test Procedure

- Connect the CT analyzer as per the figure.

- Insert the CT data (Serial, Manufacture, Ratio,


protection class) into the CT analyzer.

- Start the test and review the Test result with


the actual CT data.

- Device printout shall be attached.

Core Ratio Class Winding Resistance Burden Polarity


1S1-1S2
1S1-1S2
Criteria: the accepted criteria shall be as per IEC61869-2, IEC60044-1.

- The measured values should be in conformance to the values in the factory acceptance test.
- Device printout shall be attached.
1 8.9 Voltage Transformer Test
8.9.1 VT Insulation Resistance Test

- The purpose is to ensure the insulation resistance of VTs which are installed inside the MV Switchgear

Test Procedure

- Disconnect the primary neutral point from earth.

- Apply the test voltage between:

- Primary-Earth.

- Primary-Secondary

- Between Secondary Cores

VT Applied
Connection R-Phase (GΩ) Y-Phase (GΩ) B-Phase (GΩ)
Designation Voltage/ MIN
Pri. to earth 5KV/1MIN

Pri. to Sec. 2.5KV/1MIN


VT-1
Sec. to Earth 500V/1MIN

Sec. to Sec. 500V/1MIN


Criteria: The value of Insulation should be more than 1MegOhm/kV.
8.9.2 VT Ratio, Polarity, Winding Resistance
Test Procedure

- Connect the VT analyzer as per the figure.

- Insert the VT data (Serial, Manufacture, Ratio, protection class) into the VT analyzer.

- Start the test and review the Test result with the actual VT data.

- Device printout shall be attached.

2011-BAC-EDC030-000034 Rev.01 Page 9 of 10


Reinforcement of Rabigh Power Plant Saudi Electricity Company

Winding
VT Designation Ph Ref. Core No. Terminal Measured ratio Error% Polarity
Resistance
R-Phase Core 1 a-n

VT1 Y-Phase Core 2 a-n

B-Phase Core 3 a-n


Criteria: the accepted criteria shall be as per IEC 61869-3.
- The measured values should be in conformance to the values in the factory acceptance test.
- Device printout shall be attached.

9.0 ATTACHMENTS

9.1 ATTACHMENT #1 - Devices Print out.

Details Contractor Owner Engineer Owner


Tested by Witness by Reviewed by
Name
Designation
Signature
Date

2011-BAC-EDC030-000034 Rev.01 Page 10 of 10