Calculation.robot

The document outlines various engineering activities related to electrical design, including submissions for AMI design, lightning systems, and grounding calculations. Each activity has an original duration of 3.0 days and shows a performance completion rate of 100%. Additionally, it includes scheduled dates for certain tasks, indicating a well-structured timeline for project execution.

Uploaded by

planning.jal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

Calculation.robot

The document outlines various engineering activities related to electrical design, including submissions for AMI design, lightning systems, and grounding calculations. Each activity has an original duration of 3.0 days and shows a performance completion rate of 100%. Additionally, it includes scheduled dates for certain tasks, indicating a well-structured timeline for project execution.

Uploaded by

planning.jal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Activity ID Activity N Original Du

EE.I AMI Design3.0d


EE.I Lightning 3.0d
EE.I MPLS-TP Ba3.0d
EE.I 13.8 kV & 3.0d
EE.I Grounding 3.0d
EE.I NER Base D3.0d
EE.I Technical s3.0d
EE.I Technical s3.0d
EE.I Control Pa 3.0d
EE.I 125 V Batte3.0d
EE.I DC Single 3.0d
EE.I AC Single 3.0d
EE.I Station Ser3.0d
EE.I Revenue Me 3.0d
EE.I HV Surge A3.0d
EE.I HV Power T3.0d
EE.I Indoor & O3.0d
EE.I Protection 3.0d
Activity ID Activity N Original Du
EE.I AMI Design3.0d
EE.I Lightning 3.0d
EE.I MPLS-TP Ba3.0d
EE.I 13.8 kV & 3.0d
EE.I Grounding 3.0d
EE.I NER Base D3.0d
EE.I Technical s3.0d
EE.I Technical s3.0d
EE.I Control Pa 3.0d
EE.I 125 V Batte3.0d
EE.I DC Single 3.0d
EE.I AC Single 3.0d
EE.I Station Ser3.0d
EE.I Revenue Me 3.0d
EE.I HV Surge A3.0d
EE.I HV Power T3.0d
EE.I Indoor & O3.0d
EE.I Protection 3.0d
WeightageRev.BL3 StaRev.BL3 FinSchedule %Performance % Complete
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 9/2/2023 9/4/2023 100% 100%
0.02 9/5/2023 9/7/2023 100% 100%
0.02 9/9/2023 ### 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 9/2/2023 9/4/2023 100% 100%
0.02 9/5/2023 9/7/2023 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 7/8/2024 ### 100% 100%
0.02 ### ### 100% 100%
0.02 7/8/2024 ### 100% 100%
0.02 ### ### 100% 100%
WeightageRev.BL3 StaRev.BL3 FinSchedule %Performance % Complete
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 9/2/2023 9/4/2023 100% 100%
0.02 9/5/2023 9/7/2023 100% 100%
0.02 9/9/2023 ### 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 9/2/2023 9/4/2023 100% 100%
0.02 9/5/2023 9/7/2023 100% 100%
0.02 ### ### 100% 100%
0.02 ### ### 100% 100%
0.02 7/8/2024 ### 100% 100%
0.02 ### ### 100% 100%
0.02 7/8/2024 ### 100% 100%
0.02 ### ### 100% 100%
Activity ID Activity N Original DuWeightageRev.BL3 StaRev.BL3 Fin
EE.I AMI Design3.0d 0.02 ### ###
EE.I Lightning 3.0d 0.02 ### ###
EE.I MPLS-TP Ba3.0d 0.02 ### ###
EE.I 13.8 kV & 3.0d 0.02 ### ###
EE.I Grounding 3.0d 0.02 ### ###
EE.I NER Base D3.0d 0.02 9/2/2023 9/4/2023
EE.I Technical s3.0d 0.02 9/5/2023 9/7/2023
EE.I Technical s3.0d 0.02 9/9/2023 ###
EE.I Control Pa 3.0d 0.02 ### ###
EE.I 125 V Batte3.0d 0.02 ### ###
EE.I DC Single 3.0d 0.02 9/2/2023 9/4/2023
EE.I AC Single 3.0d 0.02 9/5/2023 9/7/2023
EE.I Station Ser3.0d 0.02 ### ###
EE.I Revenue Me 3.0d 0.02 ### ###
EE.I HV Surge A3.0d 0.02 7/8/2024 ###
EE.I HV Power T3.0d 0.02 ### ###
EE.I Indoor & O3.0d 0.02 7/8/2024 ###
EE.I Protection 3.0d 0.02 ### ###

Activity ID Activity Name


EE.I AMI Design Package Submission
EE.I Lightning System Design Calculations Submission
EE.I MPLS-TP Base Design Submission
EE.I 13.8 kV & 33kV Ring Main Unit Base Design Submission
EE.I Grounding System Design Calculation Submission
EE.I NER Base Design Submission
EE.I Technical submittal for LV Control Cables
EE.I Technical submittal and sizing calculation for MV Power Cables
EE.I Control Panel Submission
EE.I 125 V Battery and Battery Charger Sizing Calculation Submission
EE.I DC Single Line Diagram (DC SLD) Submission
EE.I AC Single Line Diagram (AC SLD) Submission
EE.I Station Service Transformer Sizing Calculation Submission
EE.I Revenue Metering Panel Base Design Submission
EE.I HV Surge Arrestor Design
EE.I HV Power Transformer Base Design Submission
EE.I Indoor & Outdoor Lighting Design Calculation Submission
EE.I Protection Base Design Submission
Schedule %Performance % Complete
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
Activity ID Activity N Original DuWeightageRev.BL3 StaRev.BL3 FinSchedule %
EE.I AMI Design3.0d 0.02 ### ### 100%
EE.I Lightning 3.0d 0.02 ### ### 100%
EE.I MPLS-TP Ba3.0d 0.02 ### ### 100%
EE.I 13.8 kV & 3.0d 0.02 ### ### 100%
EE.I Grounding 3.0d 0.02 ### ### 100%
EE.I NER Base D3.0d 0.02 9/2/2023 9/4/2023 100%
EE.I Technical s3.0d 0.02 9/5/2023 9/7/2023 100%
EE.I Technical s3.0d 0.02 9/9/2023 ### 100%
EE.I Control Pa 3.0d 0.02 ### ### 100%
EE.I 125 V Batte3.0d 0.02 ### ### 100%
EE.I DC Single 3.0d 0.02 9/2/2023 9/4/2023 100%
EE.I AC Single 3.0d 0.02 9/5/2023 9/7/2023 100%
EE.I Station Ser3.0d 0.02 ### ### 100%
EE.I Revenue Me 3.0d 0.02 ### ### 100%
EE.I HV Surge A3.0d 0.02 7/8/2024 ### 100%
EE.I HV Power T3.0d 0.02 ### ### 100%
EE.I Indoor & O3.0d 0.02 7/8/2024 ### 100%
EE.I Protection 3.0d 0.02 ### ### 100%

Activity ID Activity N Original DuWeightageRev.BL3 StaRev.BL3 Fin


EE.I AMI Design3.0d 0.02 ### ###
EE.I Lightning 3.0d 0.02 ### ###
EE.I MPLS-TP Ba3.0d 0.02 ### ###
EE.I 13.8 kV & 3.0d 0.02 ### ###
EE.I Grounding 3.0d 0.02 ### ###
EE.I NER Base D3.0d 0.02 9/2/2023 9/4/2023
EE.I Technical s3.0d 0.02 9/5/2023 9/7/2023
EE.I Technical s3.0d 0.02 9/9/2023 ###
EE.I Control Pa 3.0d 0.02 ### ###
EE.I 125 V Batte3.0d 0.02 ### ###
EE.I DC Single 3.0d 0.02 9/2/2023 9/4/2023
EE.I AC Single 3.0d 0.02 9/5/2023 9/7/2023
EE.I Station Ser3.0d 0.02 ### ###
EE.I Revenue Me 3.0d 0.02 ### ###
EE.I HV Surge A3.0d 0.02 7/8/2024 ###
EE.I HV Power T3.0d 0.02 ### ###
EE.I Indoor & O3.0d 0.02 7/8/2024 ###
EE.I Protection 3.0d 0.02 ### ###
Performance % Complete
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

Schedule %Performance % Complete


100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%
100% 100%