Ch11 P18 Build a Model
Ch11 P18 Build a Model
Webmasters.com has developed a powerful new server that would be used for corporations’ Internet activities. It
would cost $10 million at Year 0 to buy the equipment necessary to manufacture the server. The project would
require net working capital at the beginning of each year in an amount equal to 10% of the year's projected sales; for
example, NWC0 = 10%(Sales1). The servers would sell for $24,000 per unit, and Webmasters believes that variable
costs would amount to $17,500 per unit. After Year 1, the sales price and variable costs will increase at the inflation
rate of 3%. The company’s nonvariable costs would be $1 million at Year 1 and would increase with inflation.
The server project would have a life of 4 years. If the project is undertaken, it must be continued for the entire 4
years. Also, the project's returns are expected to be highly correlated with returns on the firm's other assets. The
firm believes it could sell 1,000 units per year.
The equipment would be depreciated over a 5-year period, using MACRS rates. The estimated market value of
the equipment at the end of the project’s 4-year life is $500,000. Webmasters’ federal-plus-state tax rate is 40%. Its
cost of capital is 10% for average-risk projects, defined as projects with a coefficient of variation of NPV between 0.8
and 1.2. Low-risk projects are evaluated with a WACC of 8%, and high-risk projects at 13%.
a. Develop a spreadsheet model, and use it to find the project’s NPV, IRR, and payback.
Intermediate Calculations 0 1 2 3 4
Units sold
Sales price per unit (excl. depr.)
Variable costs per unit (excl. depr.)
Nonvariable costs (excl. depr.)
Sales revenue
Required level of net operating working capital
Basis for depreciation $10,000
Annual equipment depr. rate 20.00% 32.00% 19.20% 11.52%
Annual depreciation expense
Ending Bk Val: Cost – Accum Dep'rn $10,000
Page 1
Salvage value $500
Profit (or loss) on salvage
Tax on profit (or loss)
Net cash flow due to salvage
Years
Cash Flow Forecast 0 1 2 3 4
Sales revenue
Variable costs
Nonvariable operating costs
Depreciation (equipment)
Oper. income before taxes (EBIT)
Taxes on operating income (40%)
Net operating profit after taxes
Add back depreciation
Equipment purchases
Cash flow due to change in NOWC
Net cash flow due to salvage
Net Cash Flow (Time line of cash flows)
b. Now conduct a sensitivity analysis to determine the sensitivity of NPV to changes in the sales price, variable
costs per unit, and number of units sold. Set these variables’ values at 10% and 20% above and below their base-
case values. Include a graph in your analysis.
Page 3
Deviation NPV at Different Deviations from Base
from Sales Variable
Base Case Price Cost/Unit Units Sold
-20% $0 $0 $0
-10% $0 $0 $0
0% $0 $0 $0
10% $0 $0 $0
20% $0 $0 $0
Range
c. Now conduct a scenario analysis. Assume that there is a 25% probability that best-case conditions, with each of
the variables discussed in Part b being 20% better than its base-case value, will occur. There is a 25% probability of
worst-case conditions, with the variables 20% worse than base, and a 50% probability of base-case conditions.
Page 4
Sales Unit Variable
Scenario Probability Price Sales Costs NPV
Expected NPV =
Standard Deviation =
Coefficient of Variation = Std Dev / Expected NPV =
d. If the project appears to be more or less risky than an average project, find its risk-adjusted NPV, IRR, and
payback.
Risk-adjusted WACC =
Risk adjusted NPV =
IRR =
Payback =
e. On the basis of information in the problem, would you recommend that the project be accepted?
Page 5
1,000
$24.00
$17.50
Page 6