0% found this document useful (0 votes)
2 views

Copy of hw_6_Time_Study_II_Sol

The document outlines a homework assignment focused on time study methods in industrial engineering, detailing various tasks involving worker-machine interactions and performance ratings. It includes calculations for normal and standard times, production rates, and worker efficiency based on observed times and allowances. Several scenarios are presented, requiring the application of timing methods to determine production outcomes and worker performance metrics.

Uploaded by

Ony Ouss
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

Copy of hw_6_Time_Study_II_Sol

The document outlines a homework assignment focused on time study methods in industrial engineering, detailing various tasks involving worker-machine interactions and performance ratings. It includes calculations for normal and standard times, production rates, and worker efficiency based on observed times and allowances. Several scenarios are presented, requiring the application of timing methods to determine production outcomes and worker performance metrics.

Uploaded by

Ony Ouss
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

King Saud University

College of Engineering
Department of Industrial Engineering

Homework #6: Time Study

1. The continuous stopwatch timing method was used to obtain the observed times
for a worker-machine task. Only one cycle was timed. The data are recorded in
the table below.

Worker element Time (min) PR Machine element Time (min)


a (1.24) 1.24 100%
b (3) 4.24 120% c (3.3) 4.54
d (0.55) 5.09 80%

Elements a, b, and d are worker controlled elements. Element c is machine


controlled element. Elements a and d are external to the machine controlled
element, while element b is internal to the machine controlled element. Every four
cycles, there is an irregular worker element that takes 1.32 min performance
rated at 100%. The PFD allowance is 15% and the machine allowance is 30%.
Determine:
a. The normal time for the cycle.
b. The standard time for the cycle.
c. If a worker’s efficiency is 100%, how many units would be produced in one
8-hour shift?
d. If the actual time worked during the shift was 6.86 hours, and a worker’s
performance rating was 125%, how many units would have been
produced?

Sol: (38 points)


a. Tn = [1.24 * 1 + 0.55 * 0.8 + (1.32 / 4) * 1] + Max {(3 * 1.2) & 3.3} = 5.61 min

b. Tstd = 2.01(1 + 0.15) + + Max {(3.6 (1 + 1.5) & 3.3 (1 + 0.3)} = 6.6015 min

c. Qs = 8 (60) / 6.6015 = 72.71  72 units

d. Tobs = 2.01 / 1.25 + Max {(3.6 / 1.25) & 3.3} = 4.908 min

Qact = 6.86 (60) / 4.908 = 83.86  83 units

2. The snapback timing method in direct time study was used to obtain the times for
a worker-machine task. The recorded times are listed in the table below.

Element a b c d e f
Observed time (min) 0.14 0.25 0.18 0.45 0.2 0.62

Element d is a machine controlled element and the time is constant. Elements a,


b, c, e, and f are operator controlled and were performance rated at 90%.
Element f is an irregular element, performed every five cycles. The operator
controlled elements are all external to the machine controlled element d. The
machine allowance is zero, and the PFD allowance is 13%. Determine:

Tamer M Khalaf, PhD Page 1 of 4 Monday, 16 April, 2012


King Saud University
College of Engineering
Department of Industrial Engineering

a. The normal time for the cycle.


b. The standard time for the cycle.
If a worker’s actual time spent working during an 8-hour shift was 7.08 hours, and
400 units of output were produced during this time. Determine:
c. The worker’s performance rating during the operator-controlled portions of
the cycle.
d. The worker’s efficiency during this shift.

Sol: (31 points)


a. Tn = {[0.14 + 0.25 + 0.18 + 0.2 + (0.62 / 5)] * 0.9} + 0.45 = 1.2546 min

b. Tstd = 0.8046 (1 + 0.13) + 0.45 = 1.359198 min

c. Tobs-cycle = 7.08 (60) /400 = 1.062 min


Tobs-worker = 1.062 - 0.45 = 0.612 min
PR = (0.8046 / 0.612) * 100 = 131.47 %

d. Qs = 8 (60) / 1.359198 = 353.149  353 units


 = (400 / 353) * 100 = 113.3 %

3. For a worker-machine task, the continuous timing method was used to obtain the
times indicated in the table below.

Element a b c d e
Observed time (min) 0.3 0.65 1.65 1.9 2.5
0.3 0.35 1 1.25 0.6

Element c is a machine controlled element and the time is constant. Elements a,


b, d, and e are operator controlled and were performance rated at 100%.
Element d is performed simultaneously with element c. The machine allowance is
16%, and the PFD allowance is 16%. Determine:
a. The normal time for the cycle.
b. The standard time for the cycle.
If an operator worked at 140% of standard performance during actual production
and two parts were produced each cycle, determine:
c. The number of parts produced if the total time worked during an 8-hour
shift was 7.4 hours.
d. The worker’s efficiency for this shift.

Sol: (38 points)


a. Tn = 0.3 + 0.35 + 0.6 + Max {1.25 & 1} = 2.5 min

b. Tstd = 1.25 (1 + 0.16) + Max {1.25 (1 + 0.16) & 1 * (1 + 0.16)} = 2.9 min

c. Tobs-cycle = (1.25 / 1.4) + Max {(1.25 / 1.4) & 1} = 1.893 min


Ncycle-act = [7.4 (60) / 1.893] = 234.548  234 cycles
Qact = 2 * 234 = 468 parts

d. Ncycle-std = [8 (60) / 2.9] = 165.517  165 cycles


Qs = 2 * 165 = 330 parts
 = (468 / 330) * 100 = 141.8 %

Tamer M Khalaf, PhD Page 2 of 4 Monday, 16 April, 2012


King Saud University
College of Engineering
Department of Industrial Engineering

4. For a certain repetitive task, the snapback timing method was used to obtain the
average work element times and performance ratings listed in the table below.

Work element a b c d e
Observed time (min) 0.47 0.58 0.7 0.75 2.1
Performance rating 90% 80% 110% N/A 85%

Elements a, b, and c are worker controlled elements. Element d is machine


controlled element and its time is the same each cycle (N/A means performance
rating is not applicable). Element c is performed while the machine is performing
its cycle (element d). Element e is a worker controlled irregular element
performed every five cycles. The machine is idle during elements a, b, and e.
One part is produced each cycle. The machine allowance is 15%, and the PFD
allowance is 15%. Determine:
a. The normal time for this cycle.
b. The standard time for this cycle.
If a worker’s performance rating during actual production was 130% and the
actual time spent working during an 8-hour shift was 7.3 hours, determine:
c. The number of units produced.
d. The worker’s efficiency.

Sol: (41 points)


a. Tn = {0.47 * 0.9 + 0.58 * 0.8 + [(2.1 / 5) * 0.85]} + Max {(0.7 * 1.1) & 0.75} =
2.014 min

b. Tstd = 1.244 (1 + 0.15) + Max {(0.77 (1 + 0.15) & 0.75 (1 + 0.15)} =


2.3161 min

c. Tobs-cycle = (1.244 / 1.3) + Max {(0.77 / 1.3) & 0.75} = 1.706923 min
Qact = 7.3 (60) / 1.706923 = 256.6012  256 parts

d. Qs = 8 (60) / 2.3161 = 207.2449  207 parts


 = (256 / 207) * 100 = 123.67 %

5. The work element times for a repetitive work cycle are listed in the table below,
as determined in a direct time study using the snapback timing method.

Work element a b c d
Observed time (min) 0.75 0.30 1.62 1.05

Elements a and b are operator controlled elements. Element c is machine


controlled element and its time is constant. Element d is a worker controlled
irregular element performed every ten cycles. Elements a and b were
performance rated at 90%, and element d was performance rated at 75%. The
worker is idle during element c, and the machine is idle during elements a, b, and
d. One product unit is produced each cycle. A 15% allowance factor is applied to
the total cycle time.
a. Determine the standard time for this cycle.
If a worker produced 190 units in an 8-hour shift during which 7 hours were
actually worked, determine:

Tamer M Khalaf, PhD Page 3 of 4 Monday, 16 April, 2012


King Saud University
College of Engineering
Department of Industrial Engineering

b. The worker's efficiency.


c. The worker’s performance rating during the operator paced portion of the
cycle.

Sol: (28 points)


a. Ts = {[(0.75 + 0.3) * 0.9] + [(1.05/10) * 0.75] + 1.62} * (1 + 0.15) = 3.04 min

b. Qs = 8 (60) / 3.04 = 157.88  157 units


 = (190 / 157) * 100 = 121.02 %

c. Tobs-cycle = 7 (60) / 190 = 2.210526 min


Tobs-worker = 2.210526 – 1.62 = 0.590526 min
Tn-worker = [(0.75 + 0.3) * 0.9] + [(1.05/10) * 0.75] = 1.02375
PR = (1.02375 / 0.590526) * 100 = 173.36 %

Tamer M Khalaf, PhD Page 4 of 4 Monday, 16 April, 2012

You might also like