To1
To1
Proposed Specifications:
The General Specifications are as Follows:
1. The foundation Concrete is to be of B. B. C. C. (1:6:12)
2. The brick work in plinth & Superstructure is of 1st Class in c.m. (1: 6)
3. The R. C. C. work is to be carried out in the proportion of (1:2:4) by Machine mixing.
4. The wooden doors are to be provided with brass fittings & fixtures & with wooden frame,
5. The Vitrified Tile flooring will be provided,
6. The inside cement plaster will be of 12 cm thick & of proportion (1: 4)
7. The sand faced plaster is to be provided on the exterior surface of walls.
9 The glazed tiles are to be provided in the bath rooms, with a Dado of 80 cm.
9. The underground concealed type wiring is to be provided for Electrification.
10. Govt. Arrangement/Own arrangement is to be done for Water Supply.
11. Govt. Arrangement/Own arrangement is to be done for Sanitation.
12. O.B.D Will be used Inside & Snowcem paint will be used Outside.
The quantities of various materials Required & Labour requirement is Calculated & the cost of
Materials Labour & Services is calculated based upon P. W. D. Schedule of Rates 2011 with
appropriate premiums there upon up to 2021 (on page no. 2&3) & Comes out to be
Rs.9,98,000/
As a result of appraisal & analysis it is considered opinion that the estimated cost of
constriction of above building is ₹.9,98,000/ (Rupees Nine lakh ninety eight thousand only)
Total Plot Area = 592sft.
Proposed G.F. Covered Area 475sft. 45sq.m.
Proposed F.F. Covered Area 254sft. 24sq.m.
Total Proposed Covered Area 729sft. 69sq.m.
ESTIMATE OF MATERIAL
S.No. Item Quantity Rate/unit Amount in Rs.
1 Bricks(in nos.) 22048 7.2 158746
2 Cement in Bags 239 435 103965
3 Steel in Kg 1135 69 78315
4 Timber for Frames & Shutters(cu.m) 1.522 32375 49274
5 Sand (cu.m.) 29 651 18879
6 Coarse Aggregate 20mm & down(cu.m) 12 655 7860
7 Coarse Aggregate 40mm & down(cu.m) 12 871 10452
8 Brick Aggregate (cu.m) 7 818 5726
9 Primer in lit 5 150 750
10 Paint in lit. 7.614 350 2664.9
11 Glass (sq.m.) 4 42 168
12 Bitumen (kg) 116 50 5800
Door and window fittings
(a)Butt Hinges(no.) 100mm 24 50 1200
75 mm 42 35 1470
50mm 22 25 550
(b) Sliding bolts 250mm(no.) 6 25 150
(c )Door Lock (no.) 6 450 2700
(d)Tower bolts(no.) 250mm 10 45 450
150mm 24 40 960
100mm 9 35 315
(e) Door Handles (no.) 100mm 16 35 560
(f) Cup Board Knobs(no.) 2 50 100
(g) Ball Catcher (no.) 10mm 2 25 50
(h) Hook & Eyes(no.) 100mm 28 50 1400
(i) Chain & Hooks(no.) 300mm 4 50 200
(j) Hasp & Staples(no.) 115mm 1 35 35
(k) Fan light Catch (no.) 14mm 4 45 180
13 Rain Water Pipe 100mm 7 45 315
Bend 3 55 165
Plain 3 45 135
Total Rs.4,53,535
ESTIMATE OF LABOUR
No. of Rate /
S.no. Labour Days Day Amount in Rs.
1 Mason 119 600 71400
2 Mazdoor 357 500 178500
3 Carpenter 72 650 46800
4 Painter 7 650 4550
7 Bar Bender 15 650 9750
Total Rs.3,11,000
Total cost of Materials &
Labour Rs.7,64,535
Add 2.50% Sundries 19114
Add 10% Profit & Overheads 76454
Total Rs.8,60,103
COST OF SERVICES
Item Rate per sq .m Amount in Rs.
Water Supply Arrangements 1187 80,716
Sanitary Arrangements 705 47,940
Electrical Arrangement 1058 71,944
Total Rs.2,00,600
EXTRA ITEMS
Item Rate per sq .m Amount in Rs.
For stub column arrangement in walls 715 49335
For Vitrified Tiles flooring 1855 126140
Construction of boundary wall 7'-
0" High with stub columns
Length in rm 125 2735 341875
Total 517350
Grand Total Rs.15,78,053
Work Already done Rs.8,55,750
Amount required to complete the work Rs.7,22,303
Cost of providing cupboards in Bed Rooms at G.F. & F.F. Rs.0
Cost of Modular kitchen at G.F. ( Lump Sum) Rs.2,75,000
Amount required to complete the construction Rs.9,97,303
Say 9,98,000