Lifting Plan Format AIS Panel
Lifting Plan Format AIS Panel
B. MATERIAL DISCRIPTION: -
1) Name of Material -
AIS PANEL
2) Weight of material -
2T
3) Dimension -
W 4.1 Ft, L 11.4 Ft, H 9.9 Ft
4) Availability of lifting instructions from OEM, Anchor
points(Y/N), specify if yes-
Yes
5) Point of Central of Gravity (CG), Please Draw and mentioned with detail:
F. SLINGING METHOD/ HITCH TYPE (Tick the method below and specify further information’s):
Straight Hitch: Choker Hitch: Basket Hitch: ✘ Basket Hitch: Basket Hitch:
Pre-Inspection, do mock test of crane functions, present certificates, and crane document
Crane Operator 1 for verification.
Follow instructions
1
Welder/ Gas Cutter (If required)- Specify:
Sr.No MAKE / TYPE of SLING IDENTIFICATION NO CAPACITY LENGTH & DIAMETER Validity of TPI Cert.
Polester Belt Sling 401299 5T L-5, W- 125MM
Polester Belt Sling 401322 5T L-5, W- 125MM
I. LOAD CALCULATION : -
Weight of material 2 Ton
Safe factor (5%) 0.1 Ton
Weight of wire rope/ web slings 0.01
Ton
Weight of D shackles 0.002 Ton
Weight of crane hook 0.1 Ton
Total weight 2.21 Ton
C (Ancillaries Weight) : 10
J. CRANE DETAILS :-
Make of Crane :- AEC
Boom Length 5.6 Mtr.
Radius 3.6 Mtr.
SWL as per load chart 6 Ton.
SWL in % as per load chart 37%
Axle weight (in ton) Ton.
2
Actual Ground bearing
pressure= Load on 1 0.552
outrigger/4
Note: - 1) For getting the value of Ground bearing capacity, need to check the soil strata report.
2) For safe lifting operation, Ground bearing pressure value should not be more than the Ground bearing capacity value.
K. JOB SPECIFIC RISK ANALYSIS:
S No Activity/ Area Risk Mitigations Plan
1 Reching farana at site Hit by moving bus in DTC A trafic marshal was deputed
Depot at site with red flag
lifting area is barricated & all
Personal can hit by the the staff was instructed to
2 Hangging load
suspended lload not go near the suspended
load
web sling can break during the TPI of all used web sling is
3 braking of web sling liftin and can damage property checked. Physical check also
of injury to the personals done.
a incompitent operator can
4 incompitant operator all the documents of the
damage the property or
operator was verified
personals
N. SUPPORTING FORMATS:
1. Siemens or Customer Permit to Work System
2. Pre-Task Plan: to be filled with help of competent lifting supervisor / certified crane operator, after collecting necessary lifting details like; radius,
height, weight and lifting technique. much before lifting.
3. Checklist for planning of lifting activity: to be filled a days before lifting and submit to PM & EHS along with crane document for approval.
4. Pre- Task briefing (TBT)on plan, responsibilities, and site-specific risk
O. REFERENCES:
1. Siemens Safety Essentials
2. Siemens Critical to Safety Requirements (CTS 05 & 06)
……………..End of Report…………..
3
Yes
No
NA