0% found this document useful (0 votes)
13 views

Material Quantity

The document outlines the steps to calculate material quantities for C-25 concrete and plastering, including mix ratios, material densities, and adjustments for dry volume. For C-25 concrete, it provides specific quantities for cement, sand, aggregate, and water based on a 1:2:3 mix ratio. Additionally, it details the calculation for cement plastering, including the required amounts of cement, sand, and water for a 1m² area with a 12mm thickness using a 1:4 mix ratio.

Uploaded by

Lij Abel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views

Material Quantity

The document outlines the steps to calculate material quantities for C-25 concrete and plastering, including mix ratios, material densities, and adjustments for dry volume. For C-25 concrete, it provides specific quantities for cement, sand, aggregate, and water based on a 1:2:3 mix ratio. Additionally, it details the calculation for cement plastering, including the required amounts of cement, sand, and water for a 1m² area with a 12mm thickness using a 1:4 mix ratio.

Uploaded by

Lij Abel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Material Quantity

Concrete

Step-1: Understand C-25 Concrete Mix ratio

Step 2: Define Material densities

Step 3: Calculate the total dry volume

Step-4: Determine Material Quantities Using the Mix ratio

For example for C-25 Concrete, we can calculate the quantity of cement, sand and aggregate as follows

Given Parameters:

 Mix ratio- 1:2:3


 Density of cement- 1440kg/m3
 Density of sand- 1600kg/m3
 Density of aggregate- 1450kg/m3
 Water density- 1000kg/m3
 Water- 0.5*cement weight

Dry Volume: Concrete shrinks due to voids, so we multiply by 1.54 to get the dry volume:

Dry Volume= 1*1.54=1.54m3

There for the quantity of cement, sand and aggregate will be:

i. Cement: 1/6*1.54*1= 0.385m3


ii. Sand: 2/6*1.54*1= 0.513
iii. Aggregate: 3/6*1*1.54= 0.77

Density: Mass/Volume

Cement (consider wastage and water-cement ratio)

0.385*1440=555kg divide by the kg of 1 bag which is 50kg to get the total bag.

Sand

0.513m3*1600kg/m3= 820kg

Aggregate

0.77m3*1450=1117kg

Water

w/c=0.5
w=555*0.5= 278kg=278 liters
Plastering

1. Step 1: Calculate the Volume of Plaster


2. Plaster Volume=Area×Thickness\text{Plaster Volume} = \text{Area} \times \
text{Thickness}Plaster Volume=Area×Thickness =1×0.012=0.012 m3= 1 \times 0.012 =
0.012 \text{ m}^3=1×0.012=0.012 m3
3. To account for wastage and voids, we increase the volume by 25%:
4. Total Dry Volume=0.012×1.25=0.015 m3\text{Total Dry Volume} = 0.012 \times 1.25 =
0.015 \text{ m}^3Total Dry Volume=0.012×1.25=0.015 m3
5.

6. Step 2: Calculate Cement and Sand Quantities


7. Mix Ratio = 1:4 (Cement: Sand)
Total mix proportion = 1 + 4 = 5
8. Cement Quantity
9. Cement Volume=15×0.015=0.003 m3\text{Cement Volume} = \frac{1}{5} \times 0.015
= 0.003 \text{ m}^3Cement Volume=51×0.015=0.003 m3
Cement Weight=0.003×1440=4.32 kg\text{Cement Weight} = 0.003 \times 1440 = 4.32 \
text{ kg}Cement Weight=0.003×1440=4.32 kg
Cement Bags=4.3250=0.086 bags(≈1bagper11.6m2)\text{Cement Bags} = \frac{4.32}
{50} = 0.086 \text{ bags} (\approx 1 bag per 11.6 m²)Cement Bags=504.32
=0.086 bags(≈1bagper11.6m2)
10. Sand Quantity
11. Sand Volume=45×0.015=0.012 m3\text{Sand Volume} = \frac{4}{5} \times 0.015 =
0.012 \text{ m}^3Sand Volume=54×0.015=0.012 m3 Sand Weight=0.012×1600=19.2 kg\
text{Sand Weight} = 0.012 \times 1600 = 19.2 \
text{ kg}Sand Weight=0.012×1600=19.2 kg
12. Water Quantity
13. Assuming a water-cement ratio of 0.5:
14. Water=4.32×0.5=2.16 liters\text{Water} = 4.32 \times 0.5 = 2.16 \
text{ liters}Water=4.32×0.5=2.16 liters
15.

16.Final Answer: Material for 1m² of Cement Plastering (12mm Thick, 1:4
Mix)

Material Quantity
Cement 4.32 kg (≈ 0.086 bags)
Sand 19.2 kg (≈ 0.012 m³)
Water 2.16 liters