Manhole
Manhole
This is also referred to as utility hole, inspection chamber, access chamber, sewer
hole, smell hole, flab hole.
It is the top opening to an underground utility vault. Used to house an access point
for making connections, inspection, valve adjustments.
Manhole is usually provided with cover for protection. The cover is a removable
plate forming the lid over the opening of a manhole to prevent anyone or anything
from falling in and to keep out unauthorized persons and material.
There are concrete manholes. A time what is needed is the installation. The new
manhole design comprises a precast concrete monolithic base unit complete with
channel. It is water tight to remove possible leakage.
Dyke / Levees
A harbor or harbour or haven, is a body of water where ships, boats and berges
can seek shelter from stony weather, or are stored for future use.
ports are different from harbours. A port is a facility for loading and unloading
vessels. Ports are usually located in harbors.
4. The money estimates and the intangibles or irreducible are finally used in
making a choice
Example
Two alternative plans are considered for a section of an aqueduct. plan A uses a
tunnel, plan B uses a section of lined canal and a section of steel flume. In plan A,
the estimated first cost of tunnel is ₦ 450,000.00, its estimated annual maintenance
cost is ₦4,000.00 and its estimated life is 100yr,
Estimated first costs and lives for the elements of plan B are canal (not including
lining), ₦120,000.00, 100 yr, canal lining ₦ 50,000.00, 20yr, flume, ₦ 90,000.00,
50yr. The annual maintenance cost is ₦10,500.00. The interest rate to be used in
the economy study is 6 percent per annum. The study period is 100yr. All salvage
values are assumed to be negligible. There are no estimated revenue differences or
difference in water loss
Solution
(i+ ί) n
❑
Recovery factor, R.F = ί
[
( i+ί ) n
❑−1 ]
plan A
= 27, 081
R.E = 0.06018
plan B
:. vt = (1+r) tpv
Example
1 ₦100 -₦100
2 ₦200 ₦100
3 ₦400 ₦400
4 ₦500 ₦600
5 ₦500 ₦800
Solution
PV is present value
l is interest rate
Plan A
For year 1
FV 100
PV = ( 1+ ί ) n = ( 1+0.04 ) = ₦96.2
200
For year 2, pv = ( 1.04 ) 2 = ₦ 184.9
❑
400
For year 3, pv = ( 1.04 ) 3 = ₦ 355.6
❑
500
For year 4, Pv = ( 1.04 ) 4 =₦ 427.4
❑
500
For year 5, pv = ( 1.04 ) −¿❑ ¿ ₦ 410.96
¿
=96.2+184.9+355.6+427.4+410.96
= ₦ 1,475.06
For project B
−100
For year 1, pv = ( 1.04 ) 1 = -₦96.2
❑
100
=¿
For year 2, pv = ( 1.04 ) 2 ₦92.5
❑
400
For year 3, pvv = ( 1.04 ) 3 = ₦355.6
❑
600
=¿
For year 4,pv = ( 1.04 ) 4 ₦512.9
❑
800
For year 5, pv = ( 1.04 ) 5 = ₦657.5
❑