CS_VO
CS_VO
UNOPS Bangladesh
Gulshan 2, Road 54/A, House #14,
Dhaka, Bangladesh.
Abstract of Quotation
Subject: Quotation for Additional Works for Construction of PSA Plant building at 03 Hospital locations in Bangladesh
016 Lot 01 (Khagrachari, Rangamati &
Bandarban)
Contractor Rate
SL NO. Description
BDT
Part-A Khagrachari 1,418,595
In word: Thirty four lac thirty one thousand three hundred eighteen taka
Hospital locations in Bangladesh -
Remarks
Variation Order of Khagrachari Site
SL Item description Unit Quantity Rate(BDT)
Palisading work during excavation in foundation
trenches beyond 1.5 m depth to protect loss due to
1 damage of property by palisading accepted by the Sqm 38.09 1,361.00
Engineer-in charge
8 Supply, Fitting and fixing of 48 watt Ceiling Maunt LED No's 6 4,500.00
Panel Light fitting consisting bracket, brass holder, and
necessary wiring etc. complete as per sample approved
/RFL THREAD /EQUIVALENT by the Engineer-in-charge.
Analysis Attached
10,500.00
Bill paper needed workshop
Approved by email
270,000.00
Approved by email
9,200.00
Bill paper needed ayub
14,000.00
70,000.00
1,418,594.68
1 Considering Palisading cost
(A) Cost of materials:
(1) Wood 38.09 sqm @ Tk. 410.00
(2) Bamboo 30 Nos @ Tk. 420.00
(3) Nail, gi wire & others materials 1 lot @ Tk. 1,600.00
(4) Carrying 1 lot @ Tk. 2,000.00
Sub total (A)
(B) Labour charge
(1) Skilled technician 5 no's @ Tk. 1,050.00
(2) Semi- skilled technician 10 no's @ Tk. 850.00
Sub total (B)
Overhead
Total costing=
Profit
Overhead
Total costing=
Profit
Overhead
Total costing=
Profit
Overhead
Total costing=
Profit
Overhead
Total costing=
Profit
7 Considering TPDB & ATS cost
(A) Cost of materials & equipments:
(1) 400A Circuit Breaker with Thermal Overload, Short circuit 3 nos @ 61,667.00
Release.
(2) Magnetic Contactor 400A 2 nos @ 75,000.00
(3) 600x25x8 mm Common Busber With Cooper Link For TPDM 2 lot @ 40,000.00
Part & ATS Part
(4) TPMCCB-250A-1Pcs, 40A-1Pcs, 32/40A-3Pcs,16A 4PSPD- 1 lot @ 98,000.00
1Pcs
(5) TPMCB:-10A-1Pcs, 6A-1Pcs 2 nos @ 1,500.00
(6) 2000/2500mmx700mmx700mm Pannel Board With False 1 nos @ 70,000.00
Part, Rubber Gasket, Transparent Glass, 16SWG ms Sheet
(7) Power Analayger, CT,Timer, Relay, Indicator Lamp, Colling 1 lot @ 40,000.00
Fan With Filter,heat, Shrink, Cable Gland & Etc.
(8) Combined Panel Board Wiring, Magnetic Contactor, Circuit 1 lot @ 35,000.00
Breaker, Busber, Fixing & Commisioning Charge
(9) Surge Protection Device(SPD) Type 1 & Type 2 combined 1 lot @ 60,000.00
Sub total (A)
Overhead
Total costing=
Profit & AIT
Overhead
Total costing=
Profit
Overhead
Total costing=
Profit
13 Considering Road Macadam cost
(A) Cost of materials:
(1) Brick 10,000.00 Nos @ Tk. 13.00
(2) Local sand 450.00 cft @ Tk. 50.00
(3) Brick crushing 10,000.00 Nos @ Tk. 2.00
Sub total (A)
(B) Labour charge
(1) Semi- skilled technician(Macadam mixing) 8 no's @ Tk. 950.00
(2) Semi- skilled technician (Macadam filling) 10 no's @ Tk. 950.00
(3) Semi- skilled technician(Macadam levelling & Compaction) 8 no's @ Tk. 950.00
Sub total (B)
Overhead
Total costing=
Profit
15 Considering Ground cutting, levelling and BFS & Brick column support of roof shuttering cost
(A) Cost of materials:
(1) Brick 1,945.00 nos @ Tk. 13.00
Sub total (A)
(B) Labour charge
(1) skilled technician 2 no's @ Tk. 950.00
(2) Semi- skilled technician 6 no's @ Tk. 850.00
Sub total (B)
Overhead
Total costing=
Profit
Overhead
Total costing=
Profit
SL-15: Ground Cutting, Levelling, Filling & BFS Removal of Slab Shuttering C
SL Item Rate
1 Ground Cutting & Levelling & Compaction Manpower 950.00
2 BFS & Brick Column Removal Manpower 950.00
3 Additional Brick Column Support 13.00
Total Price
Contactor's Profil (10%)
Contactor's Overhead Expenses (3.5%)
S.Total=
re Cost Analysis
Reference /Remarks
Cost Analysis
Reference /Remarks
is
Reference /Remarks
ng Door Cost Analysis
Quantity Rate/Costing Remarks
1 30,000.00
1 35,000.00
1 85,000.00
Market Analysis
1 19,000.00
1 20,000.00
1 50,000.00
Total= 239,000.00
Total Price 239,000.00
Contactor's Profil (10%) 23,900.00 Pwd Schedule
Contactor's Overhead Expenses (3.5%) 8,365.00 (Civil), 2022, Basic
Pwd Schedule
Rates, Item-1, Page-
Total Price= 271,265.00 (Civil),
1
2022, Basic
Rates, Item-2, page-1
Discount 1,265.00
S.Total Price= 270,000.00
mbined Pannel Board TPDB & ATS For Khagrachhari Cost Analysis
Unit Price Quantity Total Price
61,667.00 3 185,001
75,000.00 2 150,000
40,000.00 2 80,000
98,000.00 1 98,000
1,500.00 2 3,000
70,000.00 1 70,000
40,000.00 1 40,000
35,000.00 1 35,000
60,000.00 1 60,000
Total 721,001
Profit 15% 108,150
Overhead 3.5% 25,235
S.Total Price= 854,386
t Analysis
Reference /Remarks
Market Analysis
alysis
Reference /Remarks
Rate consider as PWD revised rate
schedule 2022
sis
Reference /Remarks
Market analysis
Remarks
Approved in Barishal
Approved in Barishal
Approved in Barishal
Approved in Barishal
Approved in Barishal
Approved in Barishal
Approved in Barishal
Approved in Barishal
Approved in Cox's Bazar
314,386
Reference /Remarks
Market Analysis
Reference /Remarks
Market Analysis
Variation Order of Rangamati Site
SL Item description Unit Quantity Rate(BDT) Amount(BDT)
Shifting of the electrical line (11 KVA
and 440 Volt) from the PSA plant
1 building location all accepted by Lot 1 250,000.00 250,000.00
Engineer in charge
Approved by Email
ayub
Analysis Attached
ayub
Approved by Email
ayub
Approved by Email
ayub
Analysis Attached
ayub
Analysis Attached
ayub
Analysis Attached
sub con
Analysis Attached
pipe
Approved by Email
raju vai
pipe
Analysis Attached hardware
Analysis Attached
Month of June , July &
August- 2024
AS per BoQ
Analysis Attached mehedi bhai
Additional works rate analysis
(C) Labour charge for aditional boring, testing and fixing in position
(1) Skilled technician(boring) 2.00 no's @ Tk. 1,000.00 each =
(2) Semi- skilled technician(boring) 2.00 no's @ Tk. 850.00 each =
(3) Semi- skilled technician(Additional 2.00 no's @ Tk. 850.00 each =
testing)
Sub total (C) =
Tk.150,000.00
Tk. 80,000.00
Tk. 98,000.00
Tk. 3,000.00
Tk. 70,000.00
Tk. 40,000.00
Tk. 35,000.00
Tk. 60,000.00
Tk.721,001.00
Tk.721,001.00
Tk. 25,235.04
Tk.746,236.04
Tk.108,150.50
Tk.854,386.53
Tk. 950.00
Tk. 500.00
Tk. 1,450.00
Tk. 2,860.00
Tk. 143.00
Tk. 950.00
Tk. 3,953.00
Tk. 138.36
Tk. 4,091.36
Tk. 409.14
Tk. 4,500.49
Tk. 7,085.00
Tk. 1,000.00
Tk. 8,085.00
Tk. 282.98
Tk. 8,367.98
Tk. 836.80
Tk. 9,204.77
Tk. 12,750.00
Tk. 2,500.00
Tk. 1,800.00
Tk. 17,050.00
Tk. 1,050.00
Tk. 950.00
Tk. 2,000.00
Tk. 19,050.00
Tk. 666.75
Tk. 19,716.75
Tk. 1,971.68
Tk. 21,688.43
Tk. 1,445.90
Tk. 1,800.00
Tk. 4,200.00
Tk. 6,000.00
Tk. 8,700.00
Tk. 1,260.00
Tk. 450.00
Tk. 10,410.00
Tk. 2,000.00
Tk. 1,700.00
Tk. 1,700.00
Tk. 5,400.00
Tk. 45,000.00
Tk. 45,000.00
Tk. 66,810.00
Tk. 2,338.35
Tk. 69,148.35
Tk. 6,914.84
Tk. 76,063.19
Tk. 1,267.72
Tk. 6,136.00
Tk. 4,400.00
Tk. 10,536.00
Tk. 5,700.00
Tk. 5,700.00
Tk. 3,800.00
Tk. 15,200.00
Tk. 25,736.00
Tk. 900.76
Tk. 26,636.76
Tk. 2,663.68
Tk. 29,300.44
Tk. 29,942.25
Tk. 910.00
Tk. 30,852.25
Tk. 10,000.00
Tk. 10,000.00
Tk. 40,852.25
Tk. 1,429.83
Tk. 42,282.08
Tk. 4,228.21
Tk. 46,510.29
Tk. 1,436.83
Tk. 30,000.00
Tk. 35,000.00
Tk. 85,000.00
Tk. 19,000.00
Tk. 18,155.00
Tk. 50,000.00
Tk.237,155.00
Tk.237,155.00
Tk. 8,300.43
Tk.245,455.43
Tk. 24,545.54
Tk.270,000.97
Tk. 2,600.00
Tk. 612.00
Tk. 3,212.00
Tk. 1,200.00
Tk. 1,200.00
Tk. 4,412.00
Tk. 154.42
Tk. 4,566.42
Tk. 456.64
Tk. 5,023.06
Tk. 772.78
Tk. 7,175.00
Tk. 7,175.00
Tk. 950.00
Tk. 850.00
Tk. 1,800.00
Tk. 8,975.00
Tk. 314.13
Tk. 9,289.13
Tk. 928.91
Tk. 10,218.04
Tk. 58,800.00
Tk. 16,200.00
Tk. 9,200.00
Tk. 5,000.00
Tk. 89,200.00
Tk. 7,200.00
Tk. 11,400.00
Tk. 18,600.00
Tk.107,800.00
Tk. 3,773.00
Tk.111,573.00
Tk. 11,157.30
Tk.122,730.30
Tk. 40,000.00
Tk. 40,000.00
Rate Analysis of Rangamati Site
SL-1: Electrical Line Shifting Cost Analysis
SL Item Rate/Costing Reference /Remarks
1 Local vendor cost (Contract basis) 250,000.00
As per site costing
Total Price 250000.00
Contactor's Profil (10%) 25000.00
Contactor's Overhead Expenses (3.5%) 8750.00
S.Total= 283750.00
SL-2: Combined Pannel Board TPDB & ATS For Khagrachhari Cost Analy
Sl No Item Description Unit Unit Price
400A Circuit Breaker with Thermal Overload, Short circuit
1 Pcs 61,667.00
Release.
2 Magnetic Contactor 400A Pcs 75,000.00
600x25x8 mm Common Busber With Cooper Link For
3 Set 40,000.00
TPDM Part & ATS Part
TPMCCB-250A-1Pcs, 40A-1Pcs, 32/40A-3Pcs,16A 4PSPD-
4 Lot 98,000.00
1Pcs
5 TPMCB:-10A-1Pcs, 6A-1Pcs Pcs 1,500.00
Costing Remarks
950.00
Market Analysis
500.00
1,450.00
145.00
50.75
1,645.75
Costing Remarks
4,500.00 Market Analysis
4,500.00
450.00
157.50
5,107.50
Costing Remarks
9,200.00 Market Analysis
9,200.00
920.00
322.00
10,442.00
Analysis
Quantity Costing Remarks
60 45,000.00 As per tender rate
15 14,250.00
6 2,520.00 Market analysis
1 3,500.00
65,270.00
1,087.83
6,527.00
2,284.45
74,081.45
Costing Remarks
9,500.00
8,550.00
Market Analysis
4,750.00
Market Analysis
6,500.00
29,300.00
2,930.00
1,025.50
33,255.50
Analysis
Quantity Costing Remarks
28.37 27,944.45
1 2,000.00
Market Analysis
1 7,000.00
4 3,800.00
40,744.45
1,436.18
4,074.44
1,426.06
47,681.13
Rate/Costing Remarks
30,000.00
35,000.00
85,000.00
Market Analysis
19,000.00
20,000.00
50,000.00
239,000.00
239,000.00
23,900.00 Pwd Schedule (Civil),
8,365.00 2022, Basic Rates,
Pwd Schedule (Civil),
Item-1, Page-1
2022, Basic Rates,
271,265.00
1,265.00 Item-2, page-1
270,000.00
Analysis
Rate Amount Remarks
220.00 8,360.00
1,000.00 1,000.00
850.00 850.00
10,210.00 Market Analysis
510.50
2,042.00
Sub.Total= 12,762.50
Cost Analysis
Rate Amount Remarks
3,650.00 69,722.30
1,200.00 12,000.00
1,000.00 10,000.00
1,200.00 6,000.00
20,000.00 20,000.00
5,000.00 5,000.00 Market Analysis
122,722.30
6,424.58
6,136.12
24,544.46
Sub.Total= 159,827.45
BoQ of Culvert work at Rangamati
SL Item Description Unit Quantity Rate
1 Earthwork in excavation in foundation trenches up to 1.5
m depth and maximum 10 m lead: in very stiff (hard) Cum 29.68 530.00
clayey soil/ rubbish etc.
2 Earth filling in foundation trnches and plinth in 150 mm
layer with earth available within 90 m of the building site
to achive minimum dry density of 95% with optimum
moisture content (Modified proctor test) induding
carrying watering, leveling, dressing and compacting to a
specified percentage each layer upto finished level etc. all Cum 1.98 1,050.00
complete and accepted by Engineer-in-charge.
15,728.41
2,079.00
1,133.30
7,166.25
114,995.00
28,207.20
107,068.07
251.06
2,500.00
8,940.00
70,000.00
30,000.00
20,000.00
408,068.29
122,420.49
122,420.49
652,909.26