IOGP PSF Presentation
IOGP PSF Presentation
Introduction to the
IOGP Process Safety Fundamentals (PSF)
January 27, 2022
PAGE 2
6/16/2022 PAGE 2
Presenters
PAGE 3
6/16/2022 PAGE 3
Introduction
To the Onshore Safety Alliance Program
WORKING TOGETHER
to improve safety and reduce serious injuries and fatalities
in U.S onshore operations
Through the OSA, companies are raising the BAR on safety, together.
PAGE 4
6/16/2022 PAGE 4
Safety Share 1: Produced Water Tank Explosion
WHAT HAPPENED?
• Driver arrived between 5:30 and 5:45 am,
hooked truck up to tank manifold, and (at
some point) ascended catwalk to tanks
• Explosion occurs prior to 6:45 am (February,
sunrise at 7:17)
• One tank fails at shell-floor joint, ejected, and
thrown 110 feet (34 m)
• One tank fails at shell-roof joint, roof thrown
165 feet (50 m) WHAT WENT WRONG?
• Catwalk damaged and displaced, throwing • Driver was performing operations before sunrise.
driver from catwalk and outside tank battery,
approximately 30 feet (9 m); fatality. • Investigation indicates that driver likely used lighter,
possibly to check tank level
Safety Share 1: Produced Water Tank Explosion
WHAT HAPPENED?
• A blowout and rig fire occurred shortly after drilling crew members removed the drill pipe from
the well, resulting in the death of five workers.
• While the rig crew tested the bottom hole assembly equipment, the mud pits gained 107 barrels of mud. Mud pit gains are an
indication of a possible natural gas influx into the well. Data indicated that conditions existed that could have allowed a gas
influx into the wellbore during the drill pipe removal operation.
• After the bottom hole assembly was tested, it was lifted out of the wellbore and mud and gas blew upwards out of the well,
igniting and causing a large fire.
Safety Share 2: Pryor Trust Gas Well Blowout
PAGE 9
6/16/2022 PAGE 9
What Makes an Effective PSF?
Day-to-day activities
PAGE
6/16/2022 PAGE 10
10
8 – Russ Holmes
PSFs Complement Life Saving Actions
PAGE 11
6/16/2022 PAGE 11
8 – Russ Holmes
Process Safety Fundamentals 1-4
PAGE
6/16/2022 PAGE 12
12
PSF 1 – Maintain Safe Isolation
PAGE
6/16/2022 PAGE 13
13
PSF 2 – Walk the Line
PAGE
6/16/2022 PAGE 14
14
PSF 3 – Apply Procedures
PAGE
6/16/2022 PAGE 15
15
PSF 4 – Sustain Barriers
PAGE
6/16/2022 PAGE 16
16
Process Safety Fundamentals 5-7
PAGE
6/16/2022 PAGE 17
17
PSF 5 – Control Ignition Sources
PAGE
6/16/2022 PAGE 18
18
PSF 6 – Recognize Change
PAGE
6/16/2022 PAGE 19
19
PSF 7 – Respect Hazards
PAGE
6/16/2022 PAGE 20
20
Process Safety Fundamentals 8-10
PAGE
6/16/2022 PAGE 21
21
PSF 8 – Stay within Operating Limits
PAGE
6/16/2022 PAGE 22
22
PSF 9 – Stop if the Unexpected Occurs
PAGE
6/16/2022 PAGE 23
23
PSF 10 – Watch for Weak Signals
PAGE
6/16/2022 PAGE 24
24
Produced Water Tank Explosion with PSF Knowledge
• We are vigilant about the potential impacts of • Increase hazard awareness for all personnel working at
uncontrolled process safety hazards. site
• We minimise and challenge ignition sources even in • Inert tanks using natural gas
“non-hazardous” areas. • Use a “lead tank” as a secondary separator
• We eliminate ignition sources during breaking • Monitor tank vapor space
containment and start-up and shutdown operations.
Pryor Trust Gas Well Blowout with PSF Knowledge
•
equipment, skills, or procedures
The driller was not effectively trained in using a new electronic trip sheet,
Recognize Change
which is used to help monitor for gas influx
• Equipment was aligned differently than normal during the tripping • We discuss and seek advice on change that occurs
operation, leading to confusion in interpreting the well data which caused gradually over time.
rig workers to miss indications of the gas influx
• Surface pressure was not identified two separate times before opening
the BOP during operations before the blowout,
• Both the day and night driller chose to turn off the entire alarm system,
contributing to both drillers missing critical indications of the gas influx
and imminent blowout
Stop if the Unexpected
• The alarm system was not effectively designed to alert personnel to Occurs
hazardous conditions during different operating states (e.g., drilling,
tripping, circulating, and surface operations) and would have sounded • We pause and ask questions when signals and
excessive non-critical alarms during the 14 hours leading to the blowout
conditions are not as expected.
• Key flow checks to determine if the well was flowing were not performed
before the incident • We stop and alert supervision if the activity is not
• The drilling contractor did not test its drillers’ abilities in detecting proceeding as expected.
indications of gas influx
• The operating company did not specify the barriers required during
operations, or how to respond if a barrier was lost
Incorporating IOGP PSFs within Everyday Operations
PAGE
6/16/2022 PAGE 28
28
How to Use the IOGP PSFs?
PAGE
6/16/2022 PAGE 29
29
IOGP PSF Resources & Tools
Get in touch!
[email protected]
+44 (0)20 3763 9700
PAGE
6/16/2022 PAGE 30
30
Become an OSA Participant!
onshoresafetyalliance.org
PAGE
6/16/2022 PAGE 31
31
Thank You!
PAGE
6/16/2022 PAGE 32
32