Summary of Report
Page 2 of 13
1. Business Requirement
a) As per process audit observations of MM module at XYZ are many transactions in the
system with respect to material movement for the material having standard price 0.
b) Analysis of the same is done and observed that, many materials are getting created af-
ter scheduled cost run.
c) As per SOP for these materials cost run has to be performed before any transaction.
but as per client input sometimes users forget to take cost run.
d) To avoid the same, prima facia solution is to have CK 40 scheduled for multiple times in
one month. But standard practices don’t recommend the same.
e) So, the development is done to provide validation on material movement for material
having standard cost 0.
f) As per business requirement validation is to modify for production order creation
(Save)at transaction CO01 and CO40.
g) Cost estimate to check for every period
h) No validation for MIGO and PGI for material having price control V
2. Testing
Transaction MM01
Page 3 of 13
Test case 1: Cost Center issue
Transaction MIGO
Fill all the required details, check and post the document
Page 4 of 13
At posting error will be triggered regarding cost run requirement and forbids the further transaction.
Following is the screenshot for reference
Page 5 of 13
Test case 2: Sales to production : Production order creation with respect to FG
Transaction MM01
Page 6 of 13
Transaction VA01
Sales order created with all required input and released for further transaction.
Page 7 of 13
MRP run is taken to create production or procurement requirement
MD02
Page 8 of 13
At saving of production order, error will be triggered regarding cost run requirement and forbids the fur-
ther transaction.
Following is the screenshot for reference
Page 9 of 13
Similar error will trigger if production order is created by co01
Test case 3: Sales: with above scenario tested further transaction related to sales will
not be allowed to perform, but in case material is already available with 0 cost main-
tained then we will observe the error at PGI as below.
Page 10 of 13
Transaction Vl01n
At PGI ,error will be triggered regarding cost run requirement and forbids the further transaction.
Following is the screenshot for reference
Page 11 of 13
Test case 4: Purchase: GRN is performed to observe the error by carrying procurement
for BOM Item of the same finished product with 0 standard price maintained. This vali-
dation is for material with procurement type E or X and with standard price control.
Note: Such test data is not available in Development kindly provide the test case for the
same.
Tcode: MM01/MM02
This material is included in BOM and for respective FG sales order is created.
MRP run is taken and Purchase order is created with reference to PR generated
Transaction: ME21N
At Goods receipts posting ,error will be triggered regarding cost run requirement and forbids the further
transaction.
Following is the screenshot for reference
Page 12 of 13
Kindly Test few other materials movements of PGI or GRN with 0 cost material. Ac-
cordingly we can move the respective TR to quality