17508 (1)
17508 (1)
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
Page No: 1 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
2 Marks
Page No: 2 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
2) Feeder reactor
1 Mark
3) Generator reactor
1 Mark
Partially
Labeled
diagram
3 Marks
Un-Labeled
diagram
2 Marks
1 a) (iv) State any four properties of good protective system.
Ans:
Properties of good protective system:
i) Selectivity: It is the ability of protective system to select correctly that part of
system in trouble and disconnect the faulty part without disturbing the rest of the
system.
ii) Speed: The relay system should disconnect the faulty section as fast as possible
to prevent the electrical apparatus from damage and for system stability. Each point
iii) Sensitivity: It is the ability of the relay system to operate with low value of 1 Mark
actuating quantity. (any four
iv) Reliability: It is the ability of the relay system to operate under points)
predetermined conditions. = 4 Marks
v) Simplicity: The relay system should be simple so that it can be easily
maintained.
vi) Economy: The most important factor in the choice of particular protection
Page No: 3 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
scheme is the economic aspect. The protective gear should not cost more
than 5% of the total cost of equipment to be protected.
1 b) Attempt any ONE of the following: 6
1 b) (i) Draw circuit diagram for men merz price protection scheme for Delta-Delta (D-
D) connected 3 phase power transformer.
Ans:
Merz price protection scheme for Delta-Delta(D-D) connected 3 phase
Power Transformer:
Labeled
diagram
6 Marks
Partially
Labeled
diagram
5 Marks
Un-Labeled
diagram
4 Marks
1 b) (ii) Two 11kV, 3 phase, 5000kVA generators having reactances of 20% operate in
parallel. The generator supply power to transmission line through 3000kVA
transformer of ratio 22kV/33kV having leakage reactance of 6%. Calculate
Fault kVA on H.T. side of transformer.
Ans:
1 Mark for
reactance
diagram
Page No: 4 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
= (20||20)+10 = 10 + 10
% X = 20 %
Rated current at base KVA
I = (5000 x 1000) / (√3 x 33 x 1000)
I = 87.477 Amp.
ISC = I x (100 / % X) 2 Marks for
= 87.477 x (100 / 20) stepwise
ISC = 437.385 amp solution of ISC
S.C. KVA = Base KVA x (100/ % X)
= 5000 x (100 /20)
= 25000 KVA 1 Mark for
S.C. MVA = 25 MVA SC MVA
2 Attempt any FOUR of the following: 16
2 a) Draw symbol of
(i) Isolator
(ii) Circuit breaker
(iii) Earthing switch
(iv) Lightning arrester
Ans:
(i) Isolator :
1 Mark for
(ii) Circuit breaker: each valid
symbol
=
(iii) Earthing switch: 4 Marks
(iv)Lightning arrester:
Page No: 5 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
2 Marks for
diagram
Page No: 6 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
Partially
Labeled
diagram
3 Marks
Un-Labeled
diagram
2 Marks
Page No: 7 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
2 Marks for
diagram
2 Marks for
diagram
Explanation:
During the operation of the breaker, the moving contact separates from the fixed
contact resulting in arcing between them. The production of arc is due to the
ionization of metal ions and depends very much upon the materials of contacts.
The arc is quickly extinguished because the metallic vapours, electrons and ions 2 Marks for
produced during arc are diffused in a short time and seized by the surface of explanation
moving and fixed members and shields. The arc gets extinguished quickly as
vacuum has good recovery of dielectric strength. The arc extinction occurs at a
small vacuum gap of about 0.6 to 0.7cm.
3 c) Write function of Buchholz relay and state application of it for transformer
protection
Ans:
Function of Buchholz relay:
It is used for the protection of transformers from the faults occurring inside the
transformer. Short circuit faults such as inter-turn faults, incipient winding 2 Marks
faults, core faults etc. may occur due to the impulse breakdown of the
insulation. To protect transformer against these faults, Buchholz relay is used.
Page No: 8 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
Labeled
diagram
4 Marks
Partially
Labeled
diagram
3 Marks
Un-Labeled
diagram
2 Marks
S1 and S2 are the turns of one of the same phase of transformer winding.
Page No: 9 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
2 Marks for
diagram
Partially
Labeled
diagram
3 Marks
Un-Labeled
diagram
2 Marks
Page No: 10 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
4 a) iv) Explain in brief the operation of microprocessor based overcurrent relay used
for protection system.
Ans:
Microprocessor Based Overcurrent Relay:
The ac voltage proportional to the load current is converted into dc through a
precision rectifier. Thus the microprocessor accepts dc voltage proportional to
the load current. The schematic diagram is shown in the figure. The output of
rectifier is fed to the multiplexer. The output of multiplexer is fed to the A/D
converter to obtain the signal in digital form. The A/D converter ADC 0800 is 2 Marks for
used for this purpose. Explanation
The microprocessor sends signal to the ADC for starting the conversion. The
microprocessor reads the end of conversion signal to examine whether the
conversion is over or not. As soon as conversion is over, the microprocessor
reads the current signal in digital form and then compares it with the pickup
value. The microprocessor first determines the magnitude of the fault current
and then selects the corresponding time of operation from the look up table.
Then it goes in delay subroutine and sends a trip signal to the circuit breaker
after the predetermined time delay.
2 Marks for
diagram
Page No: 11 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
3 Marks for
Diagram
4 b) ii) State the different causes of Abnormalities and faults in Induction motor. Write
the operation of single phase preventer.
Ans:
Different Causes of Abnormalities and Faults in Induction motor:
Squirrel Cage Induction Motors:
A) Electrical / magnetic sections:
1) Electrical supply failure due to single phasing, under voltage, unbalanced
voltages and reversal of phases.
2) Short circuit faults between turns of a stator coil due to failure of insulation.
3) Short circuit faults between stator coils due to failure of insulation.
4) Short circuit faults between stator coil/s and body of motor due to failure of
insulation.
5) Open circuit in stator winding/coils or their terminal connections.
6) Loose or broken rotor bars.
7) Damaged core stampings/teeth.
B) Mechanical section:
1) Unbalanced rotor.
2) Damaged bearings.
3) End play in shaft, bent shaft.
4) Cooling/ventilation system failures, damaged fan.
5) Failure/disturbances of alignment. Each point ½
6) Foundation arrangement disturbed.
Mark (any 6
Slip Ring Induction Motors:
A) Electrical / magnetic sections: points)
1) Electrical supply failure due to single phasing, under voltage, unbalanced = 3 Marks
voltages and reversal of phases.
2) Short circuit faults between turns of a coil on stator or rotor due to failure of
insulation.
3) Short circuit faults between coils due to failure of insulation.
4) Short circuit faults between coil/s and body of motor due to failure of
insulation.
5) Open circuit in stator or rotor winding/coils or their terminal connections.
6) Damaged core stampings/teeth of stator or rotor.
B) Mechanical section:
1) Unbalanced rotor.
2) Damaged bearings.
3) Grooved slip rings.
4) Worn out brushes leading to abnormal operation with sparking etc.
Page No: 12 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
1 Mark for
Diagram
Single phasing preventers are generally used for small / medium capacity
motors. Single phasing preventers are connected in secondary of line CTs.
These mainly contain a negative sequence filter. The output of negative
sequence filter is fed to the level detector, which further sends tripping 2 Marks for
command to starter or CB. When one of the three input lines get disconnected operation
because of any reason, ultimately the NC contact gets opened which stops the
motor to avoid further damage when single phasing occurs.
5 Attempt any FOUR of the following 16
5 a) Give any two advantages and two disadvantages of SF6 CB.
Ans:
Advantages of SF6 CB:
i) Due to superior arc quenching property, they have very short arcing time. 1 Mark for
ii) As SF6 gas is non-inflammable, no risk of fire. each of any
iii) Noiseless operation. two
iv) It does not pollute the atmosphere. advantages
v) Very much suitable in coal mines etc. = 2 Marks
vi) They have minimum maintenance cost.
vii) The same gas is recycled and reused.
viii) There are no carbon deposits on contact tips.
ix) It is very much suitable for high voltage applications.
x) Because of very high dielectric strength, effective arc quenching is 1 Mark for
possible. each of any
Disadvantages of SF6 CB: two dis-
i) SF6 gas is very costly. Hence this CB is expensive. advantages
ii) SF6 gas has to be reconditioned after every operation. = 2 Marks
5 b) Compare kitkat fuse and HRC fuse. (any four points)
Ans:
Comparison of Kitkat fuse and HRC fuse:
Sr. No. Kitkat fuse HRC fuse
1 Slow operation Fast operation
2 Less accurate More accurate
Page No: 13 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
Any one
Labeled
diagram
4 Marks
Any one
Partially
labeled
diagram
3 Marks
Any one
Unlabeled
diagram
2 Marks
Page No: 14 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
2 Marks for
diagram
Explanation:
It consists of a pivoted aluminium disc free to rotate in the air gap of an
electromagnet. One half of each pole of the magnet is surrouded by a copper
band known as shaded ring. The alternating flux s in the shaded portion of the 2 Marks for
poles will, owing to the reaction of the current induced in the ring lags behind description
the flux u in the unshaded portion by an angle α. These two ac fluxes produce
the necessary torque to rotate the disc.
5 f) Explain in brief the necessity of insulation co-ordination.
Ans:
Necessity of insulation co-ordination: 1 Mark for
The insulation strength of various Graph
equipment like transformers, circuit
breakers etc. should be higher than that of
lightning arresters and other surge
protective devices. The Insulation Co- 3 Marks for
ordination is thus the matching of the volt Explanation
time flash over and break down
characteristcs of equipment and protective devices in order to obtain maximum
protective margin at a reasonable cost.
e.g. In figure above A can be the insulation level (BIL) of the lightning arrestor
while B will be the insulation level (BIL) of the transformer. Similarly other
devices BILs should be above A.
6 Attempt any FOUR of the following 16
6 a) Draw neat circuit diagram of Buchholz relay.
Ans: Labeled
diagram
4 Marks
Partially
Labeled
diagram
3 Marks
Un-Labeled
diagram
2 Marks
Page No: 15 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
2 Marks for
diagram
2 Marks for
diagram
Page No: 16 of 17
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION
(Autonomous)
(ISO/IEC-27001-2013 Certified)
__________________________________________________________________________________________
Summer– 2018 Examinations
Model Answer Subject Code: 17508 (SAP)
2 Marks for
diagram
Page No: 17 of 17