Training Manual
Training Manual
DETAILING
TRAINING
MANUAL
1 of 99
INDEX
6 GLOSSARY 16 - 20
8 DETAILING PROCEDURES 21 - 21
11 DRAWING PRESENTATION 24 - 25
STRUCTURAL DETAILING STANDARDS
12 25 - 47
12.1 – 12.8
13 CHECKING PROCEDURES 48- 48
15 ERROR TYPE 55 - 56
17 STANDARD CONNECTIONS 58 - 88
18 WELDING STANDARDS 89 - 93
19 BOLTING STANDARDS 94 - 99
20 NOTES
2 of 99
1. INTRODUCTION
Design drawings are the drawings generated by the Architects / Engineers. They are
generally the floor plan layouts, Elevation of the buildings, & Section details. The design drawing
provides all the basic data required for preparation of shop drawings such as Bottom of base plate
level, Top of steel elevation, Top of concrete elevation, floor levels, Section sizes of beams &
columns, Column & Beam connection details, Type of connection etc.
Columns, Beams, Channels & Angles are known as structural members. Hence structural
steel detailing means detailing of these members for their inter connectivity and assembly so that
they can be fabricated in shops with all the necessary connections and shipped to site so that they
can be assembled easily.
3 of 99
• MC- Shape: They have a slope other then 162/3 percent (2 on 12) on the inner flange. (Also
known as miscellaneous channels)
These shapes are designated by mark C or MC. For example a C12X25. C- shape that is
nominally 12-inch deep and weighs 25 lbs/ft.
2.3 Angles
• Angles (also known as L- shape) have legs of equal thickness and either equal or unequal
leg sizes. Angles are designated by the mark L. For example L4X3X1/2 is an angle with one
4 inch leg, one 3 inch leg and ½ inch thickness.
2.4 Structural Tees (WT-, MT-, and ST- Shapes)
• WT- shapes: Made from W- shapes.
• MT- shapes: Made from M- shapes.
• ST- shapes : Made from S- shapes.
These shapes are designated by mark WT-, MT- or ST-. For example a WT12X27.5 is a
structural tee split from W24X55. WT- shape that is nominally 12-inch deep and weighs 27.5
lbs/ft.
2.5 Hollow Structural Sections (HSS)
• Rectangular (including square) HSS, which have an essentially rectangular (or square)
cross section, except for rounded corners, and uniform wall thickness, except at the weld
seam
• Round HSS, which have essentially round cross section and uniform wall thickness except
at the weld seam
These shapes are designated as HSS. For example HSS 10.000X0.500 is nominally 10 inch in
diameter with ½ inch wall thickness.
2.6 Double Angles
• These shapes are designated by the mark 2L, the size and thickness of the their legs
(inches) and their orientation when the angle legs are not equal size (LLBB or SLBB). For
example a 2L4X3X1/2 LLBB has two angles with one 4 inch leg and one 3 inch leg and the
4 inch legs are back-to-back a 2L4X3X1/2 SLBB is similar, except the 3 inch legs are back-
to-back. In both cases, the legs are ½ inch thick.
4 of 99
3. APPLICABLE SPECIFICATIONS, CODES AND STANDARDS
1. LRFD Specifications: The 1999 AISC Load and Resistance Factor Design Specification for
Structural Steel Buildings
2. HSS Specification: The 2000 AISC Specification for the Design of Steel Hollow Structural
Sections.
3. RCSC Specifications: The 2000 Research Council on Structural Connections Specification
for Structural Joints Using ASTM A325 or A490 Bolts.
4. AWS D1.1: Structural Steel Welding Code from American Welding Society
5. OSHA Specifications: Occupational Safety and Health Administration Specification for the
construction Industry.
4.1 W- Shapes
• The preferred material specification for W-shape is ASTM A992 (Fy=50 ksi and Fu=65 ksi)
• W-shapes with higher yield stress can be obtained by specifying
1. ASTM A572 grade 60 or 65,
2. ASTM A913 grade 60, 65 and 70.
• W- shapes with atmospheric corrosion resistance (weathering)
1. ASTM A588 grade 50
2. ASTM A242 grade 42
• Other material specification applicable to W-shape include
1. ASTM A36
2. ASTM A 529 grade 50 and 55
3. ASTM A 572 grade 42and 50
4. ASTM A 913 grade 50
4.2 M- Shapes, S- Shapes HP-Shapes and Channels
• The preferred material specification for M- shape is ASTM A36 (Fy=36 ksi and Fu=58 ksi)
• M-shapes with higher yield stress can be obtained by specifying
1. ASTM A572 grade 42, 50, 55, 60 and 65
2. ASTM A529 grade 50 and 55
3. ASTM A913 grade 50, 60, 65 or 70
• M- shapes with atmospheric corrosion resistance (weathering)
1. ASTM A588 grade 50
2. ASTM A242 grade 50
5 of 99
4.3 Angles
• The preferred material specification for Angles is ASTM A36 (Fy=36 ksi and Fu=58 ksi)
• Angles with higher yield stress can be obtained by specifying
1. ASTM A572 grade 42, 50, 55, 60 and 65
2. ASTM A529 grade 50 and 55
3. ASTM A913 grade 50, 60, 65 or 70
• Angles with atmospheric corrosion resistance (weathering)
1. ASTM A588 grade 50
2. ASTM A242 grade 46 or 50
4.4 Rectangular (Square) and Round HSS
• The preferred material specification for HSS is ASTM A500 grade B (Fy=46 ksi and Fu=58
ksi) although ASTM A500 grade C (Fy= 50 ksi; Fu= 62 ksi)
• HSS-shapes other material specifications applicable
1. ASTM A501
2. ASTM A618
• HSS- shapes with atmospheric corrosion resistance (weathering)
1. ASTM A847
4.5 Structural Plates
• The preferred material for structural plates is ASTM A36 (Fy= 36 ksi for plate thickness
equal to or less then 8 inch; Fy=32 ksi otherwise; Fu=58 ksi)
• Structural plates with higher yield and tensile strength
1. ASTM A572 grade 42, 50, 55, 60 or 65
2. ASTM A529 grade 50 or 55
3. ASTM A514 grade 90 or 100
4. ASTM A852
• Structural plate with atmospheric corrosion resistance (weathering)
1. ASTM A588 grade 42, 46 or 50
2. ASTM A242 grade 42, 46 or 50
6 of 99
6. GLOSSARY
16 of 99
Non-Shrinking sand cement mixture used under base plates
15 N S GROUT
to obtain uniform bearing surface.
Outstanding leg, The leg of a structural angle which is
16 OSL
projecting toward or away from you when viewing
An angle used around the sides of a floor to contain the
17 POUR STOP
concrete when it is being poured.
SHIPMENT OF
18 Issuing of detail drgs
DRAWINGS
20 GA Gauge
30 FV Field Verify
17 of 99
31 FOW Face of Wall
Both Sides
37 B/S
38 WP Working Point
46 THK Thick
47 TYP Typical
18 of 99
48 TYP UN Typical Unless Noted
49 CL Center Line
BEVELED
56 Tapered washers
WASHERS
62 RD Running Dimension
19 of 99
65 WP/E Working Point to End
66 BEV Beveled
Download
Detail Study
Time & Cost Estimate
Quality Checking
20 of 99
8. DETAILING PROCEDURES
1. After study of contract/sample drawings the entire group should decide the drawing pattern
& standards to be followed. (If required prototype drawing is prepared) (Ref drafting
standards in page. 26).
2. The detailer should approach the project engineer for any clarifications and the point should
be freezed.
3. Any modifications or decision taken should be informed to all the members of the group. The
Project engineers must check the drawing register to ensure that he has the latest revision
of all Contract drawings.
4. Preparation of anchor bolt drawings (A1, AB1….) and erection drawings (E1, E2.…) with
sections and other miscellaneous items.(But without erection marks)
5. Project engineers will divide the portion to be detailed and assign it to the respective
detailers.
6. Detailers will start off with preparation of drawings. Project engineers should check the
erection drawing for grid dimension, member shapes, elevations, erection markings and
other required details. Also give erection marks.(Shipment mark)
7. Detailers are supposed to incorporate the erection marks. They should check the drawing on
screen and enter the check list. These drawings should be submitted along with the checklist
to the project engineers/checkers.
8. Project engineers should enter the drawing list (For description, drawn by Etc.) and checks
the drawings as per check list .
9. Detailers should incorporate all the comments marked by the checkers and finally checkers
should ensure that all the comments are incorporated by manually checking it on the screen.
10. Project engineers should take care that the final drawings are ready for shipment.
11. Material grade should be used as per contract drawing & to be mentioned in the general
note. If the material used in the drawing is different from that mentioned in the general note,
then it should be called off in remark column of bill of materials.
21 of 99
9. STANDARD SHEET PREFIX.
22 of 99
10. DETAILING CAD- STANDARDS
DIMTXT 1/8”
DIMASZ 1/8”
DIMTSZ 1/16”
DIMEXE 1/16”
DIMEXO 1/16”
DIMTAD 1
DIMSCALE 1”
DIMCLRD 3
DIMCLRE 3
DIMCLRT 7
If drawing scale varies, dimscale also varies according to the drawing scale
(DRAWING SCALE = DIM SCALE).
Keeping Drawing Scale 1:1 As Far As Possible.
UNITS = ARCHITECTURAL
STYLES =
ROMANS (ROMANS.SHX) for general text & dim.
ROMAND (ROMAND.SHX) for header text like sections, views, etc.
(1.5 times general text).
23 of 99
11. DRAWING PRESENTATION
3. Bill of material and the title block should be on the right side of the drawing sheet as per the
client’s requirement.
4. Sections will be taken on main elevations from the right looking left or top to bottom. Further
sections will again be off the main elevation (unless unavoidable) and no sections off
sections (unless unavoidable).
6. Simple opposite handing on drawings is acceptable. Give separate ship mark for opposite
hand items (do not use “x”). Opposite hand and Noted is not acceptable and will not be
used.
7. All the dimensions should be present in the detail drawing from the fabricators point of view.
8. All welding symbols should be followed as per relevant codes, to be practiced in a given
project.
9. Maintain 1:1 drawing scale for details & sections. However some section have to be drawn
in a bigger scale for clarity.
10. Follow Section Sizes, Weld size, Bolt & Bolt Holes, Paint & Galvanizing Specification as per
contract drawing.
11. Cut length of plates should preferably rounded off to ¼” unless avoidable.
12. Plate Description in BOM: The thickness and width are specified as fractional inch
dimension and the length is specified in feet and inches. E.g. PL ½ x 8 ½ x 1’-4”, PL ¾ x 18
x 3’-0”. However this has to be deviated depending on contract sample drawings.
13. Do not duplicate Item Numbers. Keep a tally of last item number allotted. This is very
important for Item Number marking.
14. Ensure that Item Numbers for all components are indicated on drawings and covered in
“BOM” and match.
15. Ensure that Diameter of all holes is identified either through general notes or through explicit
call-off.
S TEEL DETAILING TRAINING MANUAL
24 of 99
16. Always follow standard Pen thickness, Colors, Standard Text height.
19. While drawing marking plan of beams, do not forget to show the view directions for detailing
of beams. (I.e. give the beam mark at bottom left hand of the beam.)
21. Any dimensional ambiguity in contract drawing/design drawing, the dimension or detail is
highlighted for verification.
22. Before shipping, Checker/Project Engineer should ensure that all the corrections are
incorporated in the final drawings.
5) Direction mark (North arrow). In case project north is used, reference to actual North
should be given.
6) Typical detail showing amount of grout and anchor bolt projection above concrete
footing or pier is to be given (Ref. Page 24).
8) Beam anchors and bearing plate should be shown in respective floor framing plans (Ref.
Page 24).
25 of 99
12.2 Erection plan
4) Any shipping mark piece (angles, plates etc.) sizes, marks and elevations.
6) Elevations to bearings.
7) Sections necessary for erections should be cut using a letter and sheet number
designation (A/E3) unless section is on that sheet, then sheet reference may be dropped.
8) Please note that most miscellaneous structure may be detailed without erection drawings
provided that a reference location is given beneath detail referring to architectural or
structural contract drawings.
11) Sections need only be used in order to show field work (such as field welding), items
that cannot be shown clearly on plans (odd conditions) or other information necessary to
erect the steel. Remember, erection drawing’s main function is to aid in the erection of
the steel.
27 of 99
12.3 Embeds
1) Embeds are
a) Column anchor bolts
b) Beam anchor bolts
c) Joist, beam and column bearing plates that are cast in concrete or block walls
d) Beam and beam & plate lintels supported by and supporting concrete or masonry
e) Angle lintels supported by and supporting concrete or masonry
f) Pipe bollards and rail sleeves
g) Any item built into concrete or masonry
3) Embed items should be picked up quickly in order to get them to the job site before the
concrete and masonry begins
4) Embeds in most case will not require paint, especially where they come in contact with
concrete or require field weld.
12.4 Columns
1. Columns must be cut square at bottom of shaft and should be noted FIN or finish on details
and in bill of material.
2. Stub dimensions
a. All hole groups must be stubbed from end of shaft, not from bottom of base plate.
b. One stub per hole group is sufficient provided that holes are equally Spaced.
c. All pieces welded to column should be stubbed from end of shaft.
3. Appropriate weld symbols for each condition should be shown at least once on each sheet.
4. North “N” mark should be shown on the column.
5. If column is butt welded with base plate, edge preparation should be shown. (Ref. Page 39)
6. Reference elevations relating back to erection drawings should be used to help in detailing
and checking.
7. Columns are generally to be drawn in vertical position.
8. Grid locations should be noted in ( ) under column mark.
9. In case of vertical bracing gussets dimensions from working point (W.P) to the first hole is to
be shown. Single part detail of bracing gusset to be detailed if required.
10. A view as to be taken to show the offset of shear plate from center line (C.L) (Ref. Page 39)
11. Gap between Clip angles welded to column should be equal to beam web thickness plus
1/8”.
12. In tubular sections with through plates give slot size with stub dimension.
29 of 99
12.5 Beams
2. Reference dimensions relating back to erection drawings should be used to help in detailing
and checking.
3. Stub dimensions
a) All hole groups must be stubbed from back of framing angle, end plates or end of
material.
4. One stub per hole group is sufficient provided that holes are equally Spaced.Normal set
back from back of framing angles to end of beam is ½”
a) All pieces welded to beams should be stubbed from back of clip, end plate or end of
material.
5. Appropriate weld symbols for each condition should be shown at least once on each sheet.
Weld size used for connecting clip angles / plates to beam should be 1/16” less than web
thickness of beam (UNO).
6. Camber should be noted on details as well as in the BOM. Grinding symbol to be shown
wherever required. In case of full moment connection edge preparation details to be shown.
7. Coping dimensions to be given from end of clip. Also cope value to be rounded to nearest
¼”.
8. In “TS” beams with through plates, slot size and stub dimension should be given. Ensure
that it is closed by an end or closure plate on either ends.
9. Always coordinate with the bolt holes connecting with the other beams, bracings and
columns
10. For bracing gussets give dimension from working point to the first hole with slope.
11. If the end connections are bolted, then field bolts should be sent along with the beams.
13. In sloped beam with clip angle connections working point and slopes should be mentioned
clearly. The working point should be in the same plane.
14. The detailing of beams will always be from bottom to top & left to right.
15. Stub dimensions should be given to centerline for stiffeners and end of plate for shear plates
32 of 99
12.6 Bracing
5. For double angle bracings provide spacer plate as per contract drawings.
6. For welded bracings working line is along center of gravity and for bolted bracings it is along
bolt line.
36 of 99
DOUBLE ANGLE BRACING DETAIL
12.7 Miscellaneous
12.7.1 Stairs
i. Stairs should be detailed using architectural drawings for concept, while bearing
in mind that all job specifications, State building codes and Handicap codes
must be used.
ii. Stringers should be detailed with enough information to facilitate lay out in the
shop.
i. Pipe rail 1-1/4 diameter std. (1-1/2 O.D) shall be typical with the same
size post (U.N.O). Post shall be preferably at 6’-0” o.c. and 8’-0”
maximum.
iv. Detail post and rails with sufficient information to facilitate shop layout.
12.7.3 Ladders
i. Continuous angles, bent plates, pour stop etc. which are not detailed
along with structural members can be shipped loose of 20ft length. These
members are cut at site to suit site conditions.
ii. Lintel angles, bollard posts, shelf angles, screed angles, Door & Window
jambs, bearing plates etc. are detailed as miscellaneous items.
40 of 99
WEDGE ANC.)
13. CHECKING PROCEDURES
1. Project Engineers/Checkers sho uld thoroughly study the contract drawings (structural &
architectural), the connection details, scope of work, specifications & other related
documents.
2. He should check the drawing register to ensure that he has the latest revision of all
drawings.
3. Project Engineers/Checkers should study the sample drawings & guide the detailers to
follow the same.
4. He should ensure that the drawing check print is submitted to him along with the detailer’s
checklist.
5. Use yellow pencil for checking & red pen for marking the comments on the drawing sheet.
6. Project Engineers/Checkers should check the drawing & simultaneously tick the items
mentioned in the checklist (refer Page ).
7. Check whether all items are detailed as per contract drawing/scope of work & to client’s
requirement and also cross check with the erection drawings.
8. Check for all dimensions present in the drawing from the fabricator’s point of view.
9. For any assumptions in dimensions/levels or new connections, mark verify.
10. While calculating bolt quantity, check that the numbers are not repeated.
11. Project Engineers/Checkers should check the drawing presentation & standards as
mentioned in Section IV.
12. Bill of materials to be checked for member shapes & length, assembly numbers, item marks
& numbers, unit weights, grade of material etc.
13. Check that no item marks/shipment marks are duplicated.
14. Check for the orientation of beams/columns in the erection drawing as per the detail.
15. Coordination of drawings is very important checking procedure.
16. After checking, the check prints to be signed with date by the respective P.E/checker &
given to the detailer for correction.
17. The P.E/checkers should explain the comments with reason marked on the sheet to the
detailers so that the same mistakes do not occur again.
18. Final corrections to be checked manually on the screen & ensured that all corrections are
incorporated.
19. The drawings ready for shipment should be transferred to the respective directories & finally
to the master computer (refer page 4).
48 of 99
14. PROJECT QUALITY SYSTEMS
POINT DESCRIPTION
A N/A
NO.
1 Study of Contract drawings.
Is the prototype drawing considered for preparation of drawings?
Is the prototype drawing taken from the correct path given by the project engineer?
2
"Are the layers, drafting standards like pen colors, fonts etc. checked in the prototype
drawing & followed there by?
Description of the project & other information followed as per
prototype drawing?
Drawing number
Drawing title
3 Title Block
Drawn by the name & date
Checked by name
"Notes in title block (like painting specification, bolts, steel grade etc.)
4 Grid marking and dimensions
5 North Direction / Project North Symbol.
6 Column size and Orientation.
Anchor bolt mark and elevation(elevation to top of grout or U/S of base plate or top of
7
leveling plate whichever applicable)
8 Anchor bolt patterns at all columns.
9 Number of anchor bolts & detail of the same
10 Number of leveling plates & detail of the same
11 Section Marks & Views.
12 Grout thickness.
13 Anchor bolt projection.
14 Anchor bolt diameter & hole diameter.
15 Check if OSHA regulation is complied with (minimum 4 anchor bolts to be provided)
16 General notes.
17 Title below each section or plan.
18 Weld size & symbol.
"If any details are to be verified, is that detail marked with in cloud & verification notes
19
marked?"
Weld size & symbol. Is the dimensioning pattern followed as per client’s standard &
20
as per project technical specification?
"If any view, plan or detail is to be stretched (only for representation purpose), check
21
whether the dimensions are edited so that they do not change on stretching.
22 Are all existing structure put in reference layer & shown in light lines?
23 Spell check
24 Is the timesheet entered for this drawing?
49 of 99
14.2 CHECKLIST FOR ERECTION DRAWINGS
POINT DECRIPTION
A N/A
NO.
1 Study of Contract drawings.
2 Is the prototype drawing considered for preparation of drawings?
Is the prototype drawing taken from the correct path given by the project engineer?
Are the layers, drafting standards like pen colors, fonts etc. checked in the prototype
drawing & followed there by?
3 Title Block Description of the project & other information followed as per
prototype drawing?
Drawing number
Drawing title
Drawn by the name & date
Checked by name
Notes in title block (like painting specification, bolts, steel grade etc.)
50 of 99
14.3 CHECKLIST FOR BEAM DRAWINGS
POINT DECRIPTION
A N/A
NO.
1 Study of Contract drawings.
2 Is the prototype drawing considered for preparation of drawings?
Is the prototype drawing taken from the correct path given by the project engineer?
Are the layers, drafting standards like pen colors, fonts etc. checked in the prototype drawing
& followed there by?
3 Title Block Description of the project & other information followed as per prototype
drawing?
Drawing number
Drawing title
Drawn by the name & date
Checked by name
Notes in title block (like painting specification, bolts, steel grade etc.)
4 Beam size, number of Beams
Beam ship/assembly mark, (with ""As shown""/""Opp hand"") Beam orientation as per the
5
erection drawing?
6 Beam orientation as per the erection drawing?
7 Is Grid to grid dimension followed as per erection drawing?
Are the deduction values w.r.t grid to grid dimension given at either end of the beam & are
8
coordinated with the respective connections?
Is the cutting length calculated properly especially in sloped beams and curved beams (i.e.
whether a layout is drawn to scale & checked).
9
In sloped and curved beams, care should be taken to give the maximum cutting length
required from the fabrication point of view.
10 Check whether coping required at the ends & cope value given as per client's requirements.
Is the running dimension ""RD"" indicated as per the client requirement.(i.e. from the end of
beam or clip angle)
Is the running dimension given correctly for the first hole in the web/flange and for other parts
11 like shear plates, stiffener, misc. plates , angle etc.
In RD calculation for the intermediate shear plate connection, is care taken to clear half web
thickness of the connecting beam.
End connections of beam coordinated with respective column/beam. Are intermediate
12 connections like clip angle holes/shear plates in the beam coordinated with respective
beams?
Are required sections/views taken in the beam main view properly & marked?
Is the sectional detail properly oriented and detailed?
13 Check for the opposite hand section & marking.
In sections, are the distance from center line of beam to holes & other cutting dimensions
given?
14 Elevation of the beam marked (if required)as per the client's requirement.
15 Item marks given for all items, without any duplication.
16 Descriptions of items are given only at one location.
Item marking system is followed as per client's requirements & as per project technical
17
specifications.
S TEEL DETAILING TRAINING MANUAL
51 of 99
Item mark is entered in the mark sheet maintained by your project engineer, if the item mark
18
is unique.
19 Is closure plate given in the tubular section beams?
Check whether the member is painted or galvanized. Is it indicated correctly for each
20
assembly
21 Is “NO PAINT” marked with details (for field weld, SC bolts or Fire proofing etc.)
If a skew beam/slope beam is connected to column, is the layout drawn to scale & checked
22
correctly? Is the triangulation given?
In skew beams connected to column/beam, check for fouling of beam flange and proper
23
provision of coping in the beam.
If the hole diameter is different from that mentioned in general notes, is it called off
24
separately?
25 For SC bolts, over sized holes provided in plates (not in beam)?
If beams are connected to column web and column flange, check for fouling of bolts and
26
check for the staggered bolting.
27 Are shop weld symbols with weld size shown wherever required?
28 If any details are to be verified, is that detail marked within cloud & verification notes marked?
Is the dimensioning pattern followed as per client’s standard & as per project technical
29
specifications?
30 Title below each plan & section.
If any view, plan or detail is to be stretched (only for representation purpose),
31
Check whether the dimensions are edited, so that they do not change on stretching.
Bill of Is the bill of material pattern (i.e way of giving member shape description,
materials numbering either alphabetically or nos.) followed per client’s requirements?
Is the field bolt quantity (total or for each assembly as per client’s
requirement) calculated correctly & indicated.
33 Check for the drawing presentation.
34 General notes.
35 Spell Check
36 Is the timesheet entered for this drawing?
52 of 99
14.4 CHECKLIST FOR COLUMN DRAWINGS
POINT DECRIPTION
A N/A
NO.
1 Study of Contract drawings.
2 Is the prototype drawing considered for preparation of drawings?
Is the prototype drawing taken from the correct path given by the project engineer?
Are the layers, drafting standards like pen colors, fonts etc checked in the prototype
drawing & followed there by.
3 Title Block Description of the project & other information followed as per
prototype drawing?
Drawing number
Drawing title
Drawn by the name & date
Checked by name
Notes in title block (like painting specification, bolts, steel grade etc.)
53 of 99
co-ordinate with beam.
Check whether the member is painted or galvanized. Is it indicated correctly for each
20
assembly
21 Is “NO PAINT” marked with details (for field weld, SC bolts or fire proofing etc.)
If a skew beam/sloped beam is connected to column, is the layout drawn to scale &
22
checked correctly? Is the triangulation given?
If the hole diameter is different from the mentioned in general notes, Is it called off
23
separately?
24 For SC bolts are over sized holes provided in plates (not in column)?
When beams are connected (with moment plate connection) at all sides of column,
25
especially in circular & tubular, check whether there is no fouling of moment plates.
26 If beams are connected at all four sides of column, check for fouling of bolts.
27 Are shop weld symbols shown wherever required?
28 Weld size & symbol
If any details are to be verified, is that detail marked within cloud & verification notes
29
marked?
Is the dimensioning pattern followed as per client’s standard & as per project
30
technical specification?
31 Title below each plan & section.
32 If any view, plan or detail is to be stretched
Bill of Is the bill of material pattern (i.e way of giving member shape
materials description, numbering either alphabetically or nos.) followed per
client’s requirements?
Is the item marks for each assembly arranged in alphabetical order.
Is all the ship/assembly mark & numbered entered
Is the description & length of assembly coordinated with the details in
drawing
Is the all the item for each assembly entered
Is the numbers, description of item coordinated with the details in
33
drawing
Is the item marking pattern followed as per client’s requirement.
Is the remarks column entered (like assembly steel grade,
“FITTED” stiffeners, “SHIP LOOSE” etc.)
Check whether description for similar items are to be repeated
(as per client’s requirements)
Is the shop bolt quantity calculated correctly & indicated for each
assembly
Is the field bolt quantity (total or for each assembly as per client’s
requirement) calculated correctly & indicated.
34 Check for the drawing presentation.
35 General notes.
36 Spell Check
37 Is the timesheet entered for this drawing?
54 of 99
15. ERROR TYPE
SL.NO. ERROR TYPE REASON / EXPLANATION / REMARK
55 of 99
1. Not considering members of same details.
2 Calculation mistakes
6 Quality
3. Items added during the time of shipment and forgot to
change quantity.
56 of 99
θ θ
θ
SKEWED, SLOPED AND CANTED BEAM
CONNECTIONS
SKEWED, SLOPED AND CANTED BEAM
CONNECTIONS
SKEWED, SLOPED AND CANTED BEAM
CONNECTIONS
SHOP WELDED, FIELD BOLTED CONSTRUCTION
SHOP WELDED, FIELD BOLTED CONSTRUCTION
MOMENT CONNECTIONS
19. BOLTING STANDARDS
Note: These bolt hole dimensions are standard Unless Otherwise Noted in the Design/Contract
drawings.
94 of 99