Lecture 2. - Specifications - Writing - 15.10.2022
Lecture 2. - Specifications - Writing - 15.10.2022
Lecture 2
Civil Engineering Practice
How to write Specifications
Section Format is a nationally approved, industry-accepted standard that provides a defined procedure for
organization of the specifications section. It provides guidelines for the arrangement of information within
the technical section of specifications. The concise orderly method reduces the chance for omissions or
duplication of information and it assists users of the document by consistently locating similar information in
the same place in each Section. Section Format has three separate parts:
Part 1 – General:
This section describes administrative, procedural and temporary requirements specific to this section
of specifications.
Part 2 – Products:
This section describes, in detail, the materials, products, equipment, systems or assemblies to be
used in the project.
Part 3 – Execution:
This section describes, in detail, any preparatory actions and how the products shall be incorporated
into the project.
Section Format and Page Format
To go along with Section Format is Page Format. Page Format is a standardized presentation of text
for each page of a specification Section. It provides a concise and orderly arrangement of Articles,
Paragraphs and Subparagraphs and it addresses the physical arrangement on the page, such as
margins, indents, headers and footers. The following list is the levels of organization for Page
Format:
Page 1 of 5
L. Ogutu October 2022 Civil Engineering Practice
October 2022
Examples are Kenya Bureau of Standards, BS and any other relevant codes of practice. In order
to reduce the length of your specification do not copy the clauses but just refer to them since it
is well communicated to the contractor.
g. Trade catalogues / brand names
Examples are Barolo welded tubes, Mareba tiles, Cabro blocks, paving blocks such as the Dogra.
Sometimes, this section is included as particular specifications in some contract documents. This may fall
under the following headings:
a. Extent of contract
i. This is similar to the list of principle quantities in CESSM e.g. 20 km of road, 5 bridges plus
side drains, road markings and road furniture and maintenance for 12 months.
ii. List of six documents not eight
b. Legal Provision
This shows the compliance with any existing statutes and regulations e.g. NEMA requirements.
c. General matters affecting the cost of the job
Labour issues
Health and safety, accidents and welfare
Order of works and working hours
Water and electricity supply
Information from the exploration sources and pits
Access to the site
Page 2 of 5
L. Ogutu October 2022 Civil Engineering Practice
October 2022
Before beginning clearance in any area the Contractor shall give seven days’ written notice of his
intention to the Engineer who will determine the extent and limits of such clearance.
Page 3 of 5
L. Ogutu October 2022 Civil Engineering Practice
October 2022
Topsoil shall mean the surface layer of soil which by its humus content supports vegetation and
is unsuitable, as a formation to roads and concrete structures or as a backfill or bedding
material. The extent and depth of topsoil that needs removal shall be agreed with the Engineer.
Topsoil shall be set aside for re-use or disposal as directed by the Engineer.
Trees to be removed shall be uprooted or cut down as near to the ground level as possible.
Bushes, undergrowth, small trees stumps and tree roots shall, where directed by the Engineer,
be grubbed out. All holes left by the stumps or roots shall be backfilled with suitable material in
a manner approved by the Engineer.
b Excavation for Foundations of Structures
A bottom layer of excavation of not less than 75mm thickness shall be left undisturbed and
subsequently, taken out by hand immediately before concrete or other work is placed.
Formations which are to receive concrete blinding or a drainage layer shall be covered with such
blinding or layer immediately the excavation has been completed, inspected and approved by
the Engineer.
Surfaces against which permanent works are to be placed shall be kept free of oil, water, mud or
any material.
No concrete or other materials shall be placed until formations have been approved. Adequate
notice shall be given to the Engineer to enable him to examine the formation.
c Backfilling of Excavations
Backfilling shall be thoroughly compacted in layers not exceeding 150mm compacted thickness
and by means which will not damage the Works. Backfilling of reinforced concrete structures
shall be with suitable material approved by the Engineer. “Granular material” as backfill is
defined as unconsolidated quarry dust, gravel, sand or similar in which the clay or silt content is
not predominant. The use of angular crushed stone shall not be permitted.
d Cement concrete
Cement concrete shall be prepared by mixing graded coarse aggregates with fine aggregates and
cement in specified proportions with required quantity of water.
Page 4 of 5
L. Ogutu October 2022 Civil Engineering Practice
October 2022
Page 5 of 5
L. Ogutu October 2022 Civil Engineering Practice