Lecture 11 - Bill of Quantity - 27.11.2023
Lecture 11 - Bill of Quantity - 27.11.2023
Lecture 11
Civil Engineering Practice
Bills of Quantities I
1.0 Introduction
A bill of quantities is a document which lists all the items necessary for the complete construction of works.
Each item includes a description and a quantity. When a contractor is asked to prepare a tender he is
supplied with all the contract documents.
Bill of Quantities should make it easier for a contractor to price a particular project since all the materials and
work to be carried out is listed. Each contractor should be working from the same information therefore a
fairer system is employed when pricing competitively. Less mistakes should be made compared to an
estimator taking quantities off drawings since is this procedure the estimator is effectively making up his own
bill of quantities.
Page 1 of 7
-L.Ogutu November 2023 Civil Engineering Practice
November 2023
c Working Out
The preparation of the bill involves the calculation of volumes, areas etc., (squaring the
dimensions). Traditionally this was followed by abstracting to collect similar items together on
another sheet called the Abstract Sheet. From this abstract the bill was written. This process is
commonly known as working-up.
d Writing Out
There are certain principles, which should always be followed when writing a bill of quantities. It
should be concise, accurate and well written
i. Descriptions
Each item should be described in enough detail to enable anyone reading the bill of
quantities to be able to locate the item in the works
ii. Accuracy
It is usually necessary to re-measure civil engineering works when they are completed to
determine the exact value of the work, and therefore it is not necessary to calculate the
quantities too accurately when preparing the bill.
iii. Numbering
All items should be measured consecutively page by page
Page 2 of 7
-L.Ogutu November 2023 Civil Engineering Practice
November 2023
1 2 3 4 1 2 3 4
Each dimension sheet is split into two identically ruled parts, each consisting of four columns. The purpose of
each column is as follows:
Column 1
Is termed the timesing column in which multiplying figures are entered when there is more than one
of the particular items being measured.
The timesing column is used when there are several similar items having the same measurements,
and to indicate that the measurement is to be multiplied it will be 'timesed' as shown in the example
below.
Column 2
Is termed the dimension column in which the actual dimensions as scaled or taken direct from the
drawings are entered. There may be one, two or three lines of dimensions in an item depending on
whether it is lineal square or cubic.
The dimensions of the item are entered one below the other in this column. Dimensions should
always be entered in the following order, length, breadth, depth and thickness
Column 3
Referred to as the squaring column in which the length, area or volume obtained by multiplying
together the figures in column 1 and 2 is recorded, ready for transfer to the abstract or bill.
Column 4
Referred to as description column in which the written description of each item is entree. The right
hand side of this wider column is frequently used to accommodate preliminary calculations
Page 3 of 7
-L.Ogutu November 2023 Civil Engineering Practice
November 2023
1 2 3 4 1 2 3 4
10.00 Conc. Class A in beds.
5.00
0.50
d Timesing
If there were three such items, then this dimension would be multiplied by three in the timesing
column, as follows:
1 2 3 4 1 2 3 4
3/ 10.00 Conc. Class A in beds.
5.00
0.50
If it was subsequently found that the fourth bed of concrete of the same dimensions was provided,
then further one could be added in the timesing column by the process known as ‘dotting on’ as
indicated below:
Page 4 of 7
-L.Ogutu November 2023 Civil Engineering Practice
November 2023
1 2 3 4 1 2 3 4
3/ 10.00 Conc. Class A in beds.
1 5.00
0.50
e Abbreviations
Many of the words entered in the abbreviation column are abbreviated in order to save space
and time.
The following abbreviations are often used on the dimension sheets:
▪ B'wrk - brickwork
▪ C.I. cast iron
▪ Ddt - deduct
▪ D.P.C - damp proof course
▪ E.O. - extra over
▪ Ex. excavation
▪ M.S - mild steel
▪ n.e. - not exceeding
▪ P.C prime cost
▪ R.C. - reinforced concrete
▪ S.G.S.W. salt glazed stone ware
▪ W.I. - wrought iron
f Grouping of Dimensions
Where more than one set of dimensions relate to the same description, the dimensions should
be suitably bracketed in order that this shall be made clear
g Order of Taking Off
Items should be entered in a logical order. It is suggested that the following order be used
Page 5 of 7
-L.Ogutu November 2023 Civil Engineering Practice
November 2023
1 2 3 4
½/ Conc. Class A in beds. Area of triangle with a base of 4 m and a height of 3 m
4.00 (area=basex1/2 height)
3.00
22/
7 Area of circle with 2 m radius. (area = 𝜋𝑟 2 )
2.00
2.00
Page 6 of 7
-L.Ogutu November 2023 Civil Engineering Practice
November 2023
Description $
Allow the General Provision Sum of $1,500 to cover the cost of any unforeseen 1,500
works. This sum to be expected at the direction of the Architect.
Provisional sums are included in bills of quantities for items of work which cannot be fully described or
measured in accordance with the rules of the method of measurement at the time of tender.
The following information must be provided with the provisional sum.
▪ The nature of the work
▪ How and where it is to be fixed
▪ Quantities showing the scope and extent of the work
▪ Limitations on method. Sequence and timing.
Page 7 of 7
-L.Ogutu November 2023 Civil Engineering Practice