The document outlines the schedule for the construction of the Ground Floor Central Store, detailing various activities, their durations, and dependencies from February 24 to March 12, 2025. Key tasks include site clearance, structural work, and finishing activities such as plumbing and electrical work. The project is set to start on February 24, 2025, with a completion milestone on March 12, 2025.

Uploaded by

Er Rakesh Behera
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

PM

The document outlines the schedule for the construction of the Ground Floor Central Store, detailing various activities, their durations, and dependencies from February 24 to March 12, 2025. Key tasks include site clearance, structural work, and finishing activities such as plumbing and electrical work. The project is set to start on February 24, 2025, with a completion milestone on March 12, 2025.

Uploaded by

Er Rakesh Behera
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Central Store Classic Schedule Layout 23-Feb-25 10:05

Activity ID Activity Name Original Calendar Start Finish Activity Type Qtr 1, 2025
Duration
Feb
Ground Floor Central Store 14 GROUND CAL 24-Feb-25 12-Mar-25

Ground Floor.Plan And Structural P.S 14 GROUND CAL 24-Feb-25 12-Mar-25


A1000 START PROJECT 4 GROUND CAL 24-Feb-25 27-Feb-25 Task Dependent
A1010 PLANNING SECTION 2 GROUND CAL 10-Mar-25 12-Mar-25 Task Dependent
A1020 STRUCTURAL AND ARCH.WORK 3 GROUND CAL 24-Feb-25 27-Feb-25 Task Dependent STRUCTUR
11 CONST
Ground Floor.Plan And Structural.Construction Work GROUND CAL 24-Feb-25 08-Mar-25
A1030 SITE CLEARANCE 2 GROUND CAL 24-Feb-25 26-Feb-25 Task Dependent SITE CLEARANCE
A1040 LAYOUT 1 GROUND CAL 24-Feb-25 24-Feb-25 Task Dependent LAYOUT
A1050 EARTH WORK 2 GROUND CAL 24-Feb-25 26-Feb-25 Task Dependent EARTH WORK
A1060 P.C.C 2 GROUND CAL 24-Feb-25 25-Feb-25 Task Dependent P.C.C
A1070 FOOTING 2 GROUND CAL 24-Feb-25 26-Feb-25 Task Dependent FOOTING
A1080 PLINTH BEAM 2 GROUND CAL 24-Feb-25 26-Feb-25 Task Dependent PLINTH BEAM
A1090 FILLING OF EARTH 2 GROUND CAL 24-Feb-25 26-Feb-25 Task Dependent FILLING OF EARTH
A1100 COLUMNS 6 GROUND CAL 24-Feb-25 03-Mar-25 Task Dependent
A1110 SLABS AND BEAMS 11 GROUND CAL 24-Feb-25 08-Mar-25 Task Dependent
A1120 WALLS 8 GROUND CAL 24-Feb-25 04-Mar-25 Task Dependent
A1130 PLASTERING 10 GROUND CAL 24-Feb-25 06-Mar-25 Task Dependent
8 GROUND
Ground Floor.Plan And Structural.Construction Work.Finishing CAL 24-Feb-25
Work F.W 04-Mar-25
A1140 PLUMBING WORK 6 GROUND CAL 24-Feb-25 01-Mar-25 Task Dependent
A1150 PAINTING 6 GROUND CAL 24-Feb-25 01-Mar-25 Task Dependent
A1160 ELECTRICAL WORK 4 GROUND CAL 24-Feb-25 27-Feb-25 Task Dependent
A1170 MARBLES AND TILES 8 GROUND CAL 24-Feb-25 04-Mar-25 Task Dependent
A1180 OTHER FINISHING WORK 6 GROUND CAL 24-Feb-25 03-Mar-25 Task Dependent
0 GROUND
Ground Floor.Plan And Structural.Construction Work.Finishing CAL 24-Feb-25
Work.Hand Over HOS 24-Feb-25 24-Feb-25, Ground Floor.Plan And Structural
A1190HOS 0 GROUND CAL 24-Feb-25 Finish Milestone HOS,

Actual Level of Effort Remaining Work Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Central Store Classic Schedule Layout 23-Feb-25 10:05
Qtr 1, 2025
Feb Mar
12-Mar-25, Ground Floor Central Store

12-Mar-25, Ground Floor.Plan And Structural P.S


START PROJECT
PLANNING SECTION
STRUCTURAL AND ARCH.WORK
08-Mar-25, Ground Floor.Plan And Structural.Construction Work CONST
SITE CLEARANCE

EARTH WORK

PLINTH BEAM
FILLING OF EARTH
COLUMNS
SLABS AND BEAMS
WALLS
PLASTERING
04-Mar-25, Ground Floor.Plan And Structural.Construction Work.Finishing Work F.W
PLUMBING WORK
PAINTING
ELECTRICAL WORK
MARBLES AND TILES
OTHER FINISHING WORK
oor.Plan And Structural.Construction Work.Finishing Work.Hand Over HOS

Actual Level of Effort Remaining Work Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation