Benacco Kyaka Transmission Tanzania
Benacco Kyaka Transmission Tanzania
Terms of Reference for Provision of Consultancy services for supervision and management
of the proposed 220Kv Benaco-Kyaka Transmission line in Kagera Region, Tanzania.
MAY, 2023
Table of Contents
ACRONYMS ................................................................................................................................. 4
1. Background ........................................................................................................................... 5
2. Project Objectives ................................................................................................................. 5
3. Project Descriptions .............................................................................................................. 5
4. Project Financing .................................................................................................................. 6
5. Project Executing Agency .................................................................................................... 6
6. Project Coordination ............................................................................................................ 6
7. Project Site Organization ..................................................................................................... 7
8. Site Supervision ..................................................................................................................... 7
9. Project Implementation Schedule ....................................................................................... 7
10. Scope of the Consultancy Services.................................................................................... 8
10.1 Objective(s) of the Assignment ......................................................................................... 8
10.2 General Scope of the Consultancy Services ..................................................................... 8
10.2.1 Procurement of Contractors .................................................................................. 9
10.2.2 Supervision and Monitoring .................................................................................. 9
10.2.3 Project Management ............................................................................................... 9
10.2.4 Testing and Commissioning ................................................................................... 9
10.2.5 Capacity building /Skills transfer for TANESCO staff ..................................... 10
10.2.6 Defect Liability Period .......................................................................................... 11
10.3 Payment of Consultant Services ..................................................................................... 11
11. Design Approvals and Supervision ................................................................................ 11
12. Supervision and Quality Control of Construction Works ........................................... 11
13. Environmental Mitigation Measures and Project’s Environmental Follow up ....... 12
14. Factory Test Witnessing .................................................................................................. 13
15. Site Meetings..................................................................................................................... 13
16. Reports .............................................................................................................................. 14
16.1 General ............................................................................................................................... 14
16.2 Inception report .................................................................................................................. 14
16.3 Progress Reports .............................................................................................................. 14
16.4 Project Completion Report: ............................................................................................... 15
16.5 Progress Payments ............................................................................................................. 15
17. Training ............................................................................................................................ 16
2
ToR for Consultancy Service Benaco-Kyaka TL
3
ToR for Consultancy Service Benaco-Kyaka TL
ACRONYMS
4
ToR for Consultancy Service Benaco-Kyaka TL
Terms of Reference
1. Background
Tanzania Electric Supply Company Limited (TANESCO) is a public Power Utility Company
owned by the Government of the United Republic of Tanzania under the Ministry of Energy
(MoE). TANESCO is the System Operator ranging from Power generation, transmission and
distribution in Tanzania Mainland and sells bulk power to Tanzania Island of Zanzibar. TANESCO
is also a Transmission System Operator (TSO) in Tanzania and therefore is responsible for demand
and supply balancing in Tanzania.
Part of Kagera Region Specifically Districts of Kyerwa, Karagwe, Misenyi, Bukoba Municipal
and Bukoba Districts are supplied power from Masaka west substation in Uganda via 132kV
Transmission line under bilateral contract with Uganda Electricity Transmission Company
Limited (UETCL) which will expire in June 2023. The possible way of meeting the demand for
the mentioned Districts is to develop and implement transmission line link at the system voltage
level of 220kV from the proposed Benaco substation in Ngara to Kyaka substation in Misenyi.
The approximate distance is 166.17km.
The study area is rich with minerals such as gold and nickel, fishing, food and commercial crops
such as banana and coffee, fishing, tourism etc hence having reliable and quality power supply can
eventually boost the social and economic development. TANESCO decided to undertake the Full
feasibility study of the proposed project. The propose project will comprise the following
component; -
The study proposed implementation of the project in a phased-approach in tandem with the various
commissioning dates of ongoing and planned transmission and generation projects. In
consideration of the short, medium and long term load forecast presented in the PSMP
(2020Update), the Benaco – Kyaka transmission Project will be designed at 220kV double-circuit
transmission line strung on both side.
2. Project Objectives
The ultimate development objective of the project is to improve power supply through provision
of main grid electricity to the whole Kagera Region, the project will also provide reliability and
affordability of electricity in the country, enhance power evacuation for the proposed 87MW
Kakono HPP and job creation. The project will improve the supply of electricity in Tanzania in
the short to long term by connecting the Power National grid to the isolated grid.
3. Project Descriptions
5
ToR for Consultancy Service Benaco-Kyaka TL
The Project is funded by OPEC Fund for International Development, Abu Dhabi Fund for
Development (ADFD), and Arab Bank for Economic Development in Africa (BADEA) (second
phase), (OPEC, ADFD and BADEA herein referred to as the Financiers) and the Government of
the United Republic of Tanzania (GoT). The Tanzania Electric Supply Company Limited
(TANESCO) will be Implementing Agency on behalf of GoT.
Project Components
Component Name Component Description
Component A-(Lot 1 ): 220kV Construction of 166.17km of high voltage alternating
Transmission Line current (HVAC) 220kV double circuit transmission line
strung with two circuits, running from Benaco to Kyaka
in Kagera region.
4. Project Financing
a. The 220kV Benaco - Kyaka Transmission Line Project and associated substation at
Benaco will be funded by OPEC Fund for International Development, Abu Dhabi
Fund for Development (ADFD), Saudi Fund (SFD) and with a contribution from GoT.
b. The rural electrification and reinforcement of Distribution network (medium and low
voltage distribution lines) around Benaco and Kyaka substations will be funded by
Arab Bank for Economic Development in Africa (BADEA).
The Tanzania Electricity Supply Company (TANESCO) will be the Implementing Agency of the
project.
6. Project Coordination
To ensure effective coordination and implementation of the project, TANESCO will establish
project implementation Team (PIT) for the purpose of implementing the project components
assisted by a competitively recruited Project Supervision and Management Consultant. The
consultant will be responsible for supervision and management of the project implementation
including contractor’s detailed engineering design, construction supervision and monitoring of the
project as well as the implementation of the Environmental and Social Management Plan (ESMP)
under phase II of the consultancy services contract. The overall responsibility of both phase I for
detailed engineering conceptual design, technical studies and investigations and Phase II for the
Project management and supervision lies with the consultant.
6
ToR for Consultancy Service Benaco-Kyaka TL
7.1 The Project site organization shall be set up by the Consultant in order to control all
aspects of the implementation of the Project. All staff of the Project shall be under the
sole responsibility of the Consultant. However, in order to enhance the in-house
capability of TANESCO in Project Management and Supervision, Counterpart Staff
shall be assigned by TANESCO as required to the Project Site Organization
established by the Consultant.
7.2 The main Project coordination office shall be located in Karagwe District. The Project
Coordinator and Project Implementation Team and the Consultant Project Manager
will be located in the same office block in Karagwe.
8. Site Supervision
The Consultant Project Supervision Staff should be available full time during the construction
activity of each lots of the Project.
The Consultant shall assign the following site supervisors during the progress of various
construction activities as required;
(i) Transmission Line: Transmission line erection engineers with civil works monitoring
proven experience for transmission lines. Each lot will have its own independent site
supervisor;
(ii) Substations: Substation electromechanical erection work engineers, substation test
and commissioning engineer, protection, communication, control and commissioning
engineers and substation civil work engineers;
(iii) Environmental and Social Monitoring: Environmentalist and Social Specialist.
TANESCO shall assign competent counterpart staff for the supervision of construction works.
However, the overall responsibility of site supervision shall remain with the Consultant.
7
ToR for Consultancy Service Benaco-Kyaka TL
8
ToR for Consultancy Service Benaco-Kyaka TL
testing and commissioning of 220kV transmission line from Benaco to Kyaka and
associated substations at Benaco. The scope of the consultancy service will include
but not limited to the following:
9
ToR for Consultancy Service Benaco-Kyaka TL
10
ToR for Consultancy Service Benaco-Kyaka TL
It is proposed that the payment of the Consultancy services shall be divided in two Phases as
narrated below;
(i) Lumpsum payment for the design review, preparation of Bidding Documents, and
assistance during procurement of contractor(s);
(ii) Time based payment for the supervision, monitoring and management phase;
The consultant will be responsible for review of contractor’s detailed engineering design,
construction supervision and monitoring of the project as well as the implementation of the
Environmental and Social Management Plan (ESMP). Overall responsibility of the project
supervision and management lies with the consultant.
The Consultant shall assign full time site supervisors during the construction of the transmission
lines and substations. The Consultant and his staffs shall undertake close follow up of site activities
to ensure that all works are constructed, erected and completed in accordance with approved
drawings and specifications and international technical standards.
The Consultant shall supervise the construction of the transmission lines and Substations and Rural
Electrification (Distribution) projects during all the construction periods. The Consultant shall
submit monthly and quarterly progress reports, and approve the of payment requests by contractors
to enable the Project Implementation Units of TANESCO to authorize the payment requests.
The supervision works shall include the inspection of the commissioning of substations,
transmission lines and Rural Electrification (Distribution) projects, control and protection systems,
communication systems as carried out by the contractors.
11
ToR for Consultancy Service Benaco-Kyaka TL
The Resident Project Manager of the Consultant and his staffs shall undertake close follow up to
ensure that all works are constructed, erected and completed in accordance with approved
drawings and specifications and international technical standards.
Transmission Line
The Consultant shall provide Electrical Transmission Line engineer for the following works for
TANESCO: -
- Supervise contractor's construction procedures,
- Monitor the transmission lines construction schedules.
- Advise on the interpretation of contractual matters.
- Supervise the delivery of equipment and materials to site.
- Supervise construction progress, test and commissioning procedures
- Witness and approve contractors on site tests and commissioning
Substations
The Consultant shall provide Electrical Engineers, Civil Engineers and Protection and control etc.,
engineers or the following works for Employer (TANESCO): -
- Supervision contractor's electromechanical construction procedures,
- Supervision contractor's civil works construction procedures
- Monitoring the electromechanical and civil works construction schedules.
- Advising on the interpretation of contractual matter.
- Supervision of the delivery of equipment and materials to site.
- Supervision of construction progress, test and commissioning procedures
- Witnessing and approving contractors on site test and commissioning
The Consultant must ensure that all the environmental and social impact mitigation and monitoring
measures as stipulated in Project’s Environmental and Social Impact Assessment (ESIA) and the
Environmental and Social Management Plan (ESMP) are appropriately executed by TANESCO
and contractors to National and International standards.
The Consultant shall perform environmental monitoring once every 6 months after commencement
of the construction and during all stages of the Project. The Consultant shall perform, among
others, the following activities during the construction phase of the Project.
12
ToR for Consultancy Service Benaco-Kyaka TL
and safety management plan (ESHS-MP) in their bid proposal, based on the ESMP for
the Project,
e) Ensure that all construction contractors prepare an acceptable, detailed ESHS-MP and
an HIV/AIDS Awareness and Prevention Plan prior to commencement of site
preparation and construction activities and
f) Ensure that all construction contractors implement the detailed HSES-MP and
HIV/AIDS Awareness and Prevention Plan and otherwise adhere to sound construction
management guidelines.
g) Submit a detail Environmental and social quarterly Progress report
The Consultant shall carry out the necessary environmental monitoring activities together
with environmental monitoring unit of TANESCO.
The equipment to be supplied under this project should be inspected and tested in the
manufacturers testing stations. The Consultant shall be responsible for quality assurance of all
equipment and material to be supplied under all contracts. The Consultant together with
TANESCO personnel shall inspect and witness all factory tests for major equipment in order to
ensure strict follow up of the testing process. It is not required to assign permanently an inspector
in the manufacturer country. Inspection of factory manufacturing shall be organized periodically.
The costs for factory inspection shall be covered by contractors. This will include all Consultant
personnel expenses, travel, and hotel and allowance expense (For minimum of 40 trips of
accommodation of minimum 7 days per travel). Written report shall be provided by the consultant
on each test witnessed by him or together with TANESCO.
The procedure for testing should be prepared by the manufacturer/contractor in coordination with
the consultant and should be reviewed and submitted to the client six (6) weeks prior to the test
date.
The Resident Project Manager and the Consultant staff shall hold site meetings regularly as
required with the contractors' site representatives and TANESCO’s. Staff.
13
ToR for Consultancy Service Benaco-Kyaka TL
Minutes of the meeting shall be prepared and signed by the participating parties. Copies of the
minutes shall be given to the participants and to the TANESCO's Project Implementation Units.
Other members of the Resident Engineer's field staff shall also attend the meeting.
The Resident Project Manager shall chair the liaison meetings with the respective TANESCO
Project Coordinator with the contractors of each lot respectively. The consultant shall be
responsible to chair the meetings and handling of the minutes. The main objectives of the meetings
are to review the project progress reports, and to evaluate the actual site progress.
16. Reports
16.1 General
The Executing/ Implementing Agency and financiers of the Project consider of
atmost importance the timely submission of project reports during the course of the
project implementation. All reports shall be submitted in 5 copies to the
Executing/implementing agency with all required information for all sections of the
line and substations. Format of the report should be discussed and agreed upon with
the Employer. The Quarterly Progress Reports (QPRs) including implementation of
the Environmental and Social Management Plan (ESMP) shall cover all aspects of
Project implementation, including the status of progress against agreed
implementation and disbursement schedules for all lots of the project. The QPRs will
provide updated information in relation to the baseline data in line with the Project
Appraisal Report.
The Resident Project Manager of the Consultant shall compile, summarize and
14
ToR for Consultancy Service Benaco-Kyaka TL
submit monthly and quarterly progress report to the Project Coordinator as per the
agreed formats of the meeting between TANESCO and Consultant.
The quarterly progress reports shall be prepared in accordance with the Banks
guidelines which shall be agreed by financers of this project. The reports by contracts
shall at least include.
16.5.2 The Resident Engineers of the Consultant shall compare the statement with
their own records and solve issues of differences with the contractor's
representative. The updated master copies of progress charts shall be
submitted to TANESCO Project Office along with the monthly statement, the
progress charts, the duplicate sheet, the works diary, the monthly site financial
15
ToR for Consultancy Service Benaco-Kyaka TL
statement, etc.
16.5.3 The Consultant Project Manager or the Deputy Project Manager shall prepare
and sign payment certificates with the Project Coordinator of TANESCO for
works executed. The disbursements shall be indicated in the progress report.
16.5.4 TANESCO shall check the monthly statement(s) endorsed by the respective
Resident Project Manager of the Consultant and authorize the payment
17. Training
On Job Training
17.2 The Consultant shall monitor the training courses provided by Contractors
in the framework of their contracts, the training should be arranged for
senior experienced engineers for each field.
16
ToR for Consultancy Service Benaco-Kyaka TL
18. Transportation
The consultant shall purchase a maximum of six latest double cabin (D4D Toyota Hilux) vehicles
to be used by the consultant staff during the whole project duration and vehicles will be handed
over to TANESCO after the completion of the project. Vehicles will be inspected by TANESCO
before handing over and TANESCO will accept only vehicles which are in good condition.
The consultant shall cover all the related costs for maintaining those vehicles (insurance,
maintenance, fuel, drivers, etc.) during the entire project duration.
Engine: -
- Drive Line: 4-wheel drive;
- Engine: 3.0L & above, DOHC, DUAL VVT-I (2TR-FE);
- Transmission: 6-speed Manual, TURBO;
- Fuel type: Diesel; -Fuel tank capacity: 80L & above;
- Maximum torque: 42.9/4000 KG-M/RPM.
Safety Features:
- Anti-Lock Brake System (ABS) + Brake Assist (BA);
- Electronic Brake Force Distribution (Ebd);
- Tire Inflation Pressure Warning;
- Vehicle Stability Control (Vsc);
- Rear View Camera; - Power window automatic.
The cost for provision of the above vehicles shall be deemed to be included in the schedules of
prices.
Upon completion of the project construction activities, the Consultant shall prepare a Project
Completion Report (PCR) in accordance with OPEC Fund and ADFD requirements. The PCR will
form a comprehensive record of the design, construction and erection works accomplished
including: -
17
ToR for Consultancy Service Benaco-Kyaka TL
Except as the Client may otherwise agree, no changes shall be made in the Key Personnel. If, for
any reason beyond the reasonable control of the Consultant, such as retirement, death, medical
incapacity, among others, it becomes necessary to replace any of the Key Personnel, the Consultant
shall provide as a replacement a person of equivalent or better qualifications”, the Consultant
should be assured that the proposed key personnel for this consultancy service agreement should
be available for the duration of the contract. Therefore, after contract award, the consultant cannot
issue a request for replacement of any key personnel, unless it is beyond the Consultant’s
reasonable control such as retirement, death, and medical incapacity which shall be proved to have
happened. The Consultant, when nominating the key personnel on his technical proposal, should
carefully check the medical fitness and the age of the key personnel to avoid unnecessary dispute
with the Clients for replacement of the key personnel after contract award. This issue has become
of prime importance from recent experience and has become intolerable any more for the clients.
The Consultant’s Project Coordination Office, Site Organization and Home Office shall comprise
of the following key personnel but not limited to: -
18
ToR for Consultancy Service Benaco-Kyaka TL
The Consultant must provide a schedule with breakdown for the various activities called
for in the TOR’s, including the home office and field activities. The consultant should
clearly indicate the man-months to be spent on activities in Project Site in Tanzania,
and Home Office. Separate Staff shall be assigned for the work in Tanzania. The man-
months activities shall be indicated clearly. The consultant will be evaluated with the
total man-month proposed. The estimated man-months by the clients are as indicated
in the table below.
The minimum proposed man-months by the Consultant shall not be less than the
estimated man-months by the clients for each key personnel and activity involved.
Person-Month Estimate: The total minimum estimate of person-months by the clients
is 224 person-months spread over a period of 48 calendar months. However, the
consultant, based on the complexity of each activity and understanding of the required
services to be rendered, shall propose their own quantities of person-months for any of
key personnel and the total person-months shouldn’t be less that the total minimum
estimated by the client (s).
19
ToR for Consultancy Service Benaco-Kyaka TL
Total Man-months
No. Number of Key Staff No. Home In
Total
office Tanzania
Project Office and Site Office in
Tanzania
Home office Staff
1 Project Director 1 1.5 2 3.5
2 Transmission Line Design Engineer 1 3 2.5 5.5
3 Civil Works design engineer 1 3 2.5 5.5
4 Substation Equipment Design Engineer 1 1.5 5 6.5
Protection and Control systems design
5 1 1 2 3
engineers
Communication and SCADA Design
6 1 1 2 3
Engineer
7 Distribution engineer 1 1 2 3
Sub Total 12 18 30
Project Office and Site Office Staff
1 Resident Project Manager Kagera 1 0 24 24
Substation Electromechanical
2 2 0 33 33
Supervision Engineer
Substation Civil Work Supervision
3 1 0 12 12
Engineer
Communication and SCADA
4 1 0 5 5
Commissioning Engineer
Protection and Control
5 1 0 3 3
/Commissioning Engineer
Transmission Line Supervision
6 2 0 33 33
Engineers.
7 Social and Environmental Specialist 2 0 10 10
8 Distribution Supervision Engineer 1 0 18 18
Local Engineers assistants 2 TL and 1
9 3 0 42 42
Distribution
10 Other Support Staff 3 0 8 8
Sub Total 0 198 198
Total Minimum Man-month 12 216 224
21.5 Qualifications
The Consultant must be highly qualified and should have sufficient reference in design,
20
ToR for Consultancy Service Benaco-Kyaka TL
The Consultant Project Director, Resident Project Manager, Project Site Manager and
other experts should have an extensive experience in Project management of
transmission line, substations and Distribution line Projects.
The Project Director should have a minimum of Master’s degree in engineering with a
minimum of 15 years of experience in project management role, the Resident Project
Manager and Project site Manager should have a minimum of Bachelor degree in
engineering with not less than 12 years of experience in project management role.
The Transmission Line Design Engineer, Civil Works design engineer, Substation
Equipment Design Engineer, Protection and Control systems design engineers,
Communication and SCADA design engineers and Distribution Engineers should have
at least Bachelor degree with 10 years of experience in transmission line, substations
and Distribution line projects.
The Social and Environmentalist Specialist should have at least Bachelor degree with 8
years of experience in Social and environmental issues.
All supervision staff should have adequate experience outside of their country similar
to the project area. In addition, it is required that all field personnel of the Consultant be
proficient in international communication skills, especially in English language.
The Consultant should prepare and submit a description of the organization planned to
be set up for the project and the list of his key personnel with their Curriculum Vitae
(CV) to be assigned to work in Tanzania for effective supervision and project
management of the project.
21
ToR for Consultancy Service Benaco-Kyaka TL
The Financial Proposal shall be clear and formal as possible with breakdowns of each subtotal into
remuneration, reimbursable, miscellaneous and grand total. The evaluation will take care of
consideration for all items on the same basis and on equal ground for comparison. All items in the
Technical Proposal incurring expense must be supported with a corresponding financial proposal
It is required that the Consultant costs includes the cost for establishment of Local Project Offices
located in Karagwe to make it easy for project staff to access information as well as making
execution of the consulting activities as defined in the scope of works run smoothly.
The offices shall have enough space and furnishing to accommodate staff of consultant and
counterpart personnel, and TANESCO Project Implementation Team (PIT) offices.
Communications facilities including internet shall be provided to PIT offices as well.
Project Implementation Team meetings will be held at the consultant’s offices in Karagwe. The
offices shall therefore have enough space, furnishing and equipment for this purpose.
The Consultant shall provide for the entire duration of the Contract for the sole use of the Clients’
and the consultant’s personnel fully furnished, air conditioned, sound and weatherproof offices
complete with all electrical fittings, plumbing and sanitary systems clean and provided with
windows to give a sufficient supply of natural light. The client’s office shall be equipped with
Heavy Duty Photocopy and printer machines
The construction contractors under all lots shall provide on a 24-hour basis, the vehicles,
computers and photocopying equipment as specified in the Price Schedules for the use of the
consultant and the clients’ project staff. Details of the vehicles, facilities, services, repair and
maintenance including drivers and other persons such as mechanic(s) etc., shall be included in the
construction bidding documents.
The Employer(s) shall also avail staff who shall work closely with the Consultant and represent
the Client(s) and assist in provision of existing project information and data when required,
participate in the review and approval of detailed designs and any submissions by the EPC
contractor(s) that require approval, follow-up on the site works, monitoring environmental
implementation plans, participate in installation, commissioning and witnessing tests including
22
ToR for Consultancy Service Benaco-Kyaka TL
factory acceptance tests. These staff shall, however, be under the control of and be paid by the
Employer. They shall not be held responsible for any failure on the consultant to deliver the project
with the desired quality.
23
ToR for Consultancy Service Benaco-Kyaka TL
TANESCO MANAGING
DIRECTOR
DEPUTY MANAGING
DIRECTOR -PRI
PROJECT MANAGER
/COORDINATOR
24