PRINCE2_6th_edition___Risk_Management_Approach_template___long_example
PRINCE2_6th_edition___Risk_Management_Approach_template___long_example
This template provides explanations and guidance on the kinds of information necessary for the risk
management approach for PRINCE2 6th edition.
Contents
1 Introduction............................................................................................................................................4
2 Risk management process or procedure.................................................................................................4
3 Tools and techniques..............................................................................................................................5
4 Records...................................................................................................................................................5
5 Reporting................................................................................................................................................5
6 Timing of risk management activities....................................................................................................6
7 Roles and responsibilities.......................................................................................................................6
8 Scales......................................................................................................................................................7
9 Proximity................................................................................................................................................9
10 Risk categories....................................................................................................................................9
11 Risk response categories.....................................................................................................................9
12 Early warning indicators...................................................................................................................10
13 Risk tolerance...................................................................................................................................10
14 Risk budget.......................................................................................................................................10
1
PURPOSE
A risk management approach describes how risk will be managed on the project. This includes the
specific processes, procedures, techniques, standards, and responsibilities to be applied.
COMPOSITION
The risk management strategy includes the following:
Introduction This states the purpose, objectives and scope, and identifies who is
responsible for the approach.
Risk management process or procedure This describes (or refers to) the risk
management process or procedure to be used. Any variance from corporate, programme
management, or customer standards should be highlighted, together with a justification for
the variance. The process or procedure must describe how:
o risks are identified and assessed
o risk responses are planned and implemented
o risk management activities are communicated.
Tools and techniques This refers to any risk management systems or tools to be used, and
any preference for techniques which may be used for each step in the risk management
procedure.
Records This defines the composition and format of the risk register and any other risk
records to be used by the project.
Reporting This describes any risk management reports that are to be produced, including
their purpose, timing, and recipients.
Timing of risk management activities This states when formal risk management
activities are to be undertaken (e.g. at the end of management stages).
Roles and responsibilities This defines the roles and responsibilities for risk management
activities.
Scales This defines the scales for estimating probability and impact for the project to ensure
that the scales for cost and time (for instance) are relevant to the cost and timeframe of the
project. These may be shown in the form of probability impact grids giving the criteria for
each level within the scale (e.g. for ‘very high’, ‘high’, ‘medium’, ‘low’ and ‘very low’).
Proximity This provides guidance on how proximity for risk events is to be assessed.
Proximity reflects the fact that risks will occur at particular times and the severity of their
impact will vary according to when they occur. Typical proximity categories will be: imminent,
within the management stage, within the project, beyond the project.
Risk categories This defines the risk categories to be used (if at all). These may be derived
from a risk breakdown structure or prompt list. If no risks have been recorded against a
category, this may suggest that the risk identification has not been as thorough as it should
have been.
Risk response categories This defines the risk response categories to be used, which
themselves depend on whether a risk is a perceived threat or an opportunity.
Early warning indicators This defines any indicators to be used to track critical aspects of
the project so that if certain predefined levels are reached corrective action will be triggered.
They will be selected for their relevance to the project objectives.
2
Risk tolerance This defines the threshold levels of risk exposure which, when exceeded,
require the risk to be escalated to the next level of management. (For example, a project-
level risk tolerance could be set as any risk that, should it occur, would result in loss of
trading. Such risks would need to be escalated to corporate, programme management or the
customer.) The risk tolerance should define the risk expectations of corporate, programme
management or customer and the project board.
Risk budget This describes whether a risk budget is to be established and, if so, how it will
be used.
DERIVATION
The risk management approach is derived from the following:
project brief
business case
where relevant, any corporate, programme management or customer risk management
guides, strategies, or policies.
QUALITY CRITERIA
The following quality criteria apply to the risk management approach:
Responsibilities are clear and understood by both customer and supplier.
The risk management procedure is clearly documented and can be understood by all parties.
Scales, expected value, and proximity definitions are clear and unambiguous.
The chosen scales are appropriate for the level of control required.
Risk reporting requirements are fully defined.
3
1 Introduction
This document describes how risk management should be performed within a
project. The purpose of the document is to describe the use of risk management
processes, roles and responsibilities, the techniques and tools applied, and the
documentation kept for risk management. The risk management approach
described below is based on the PRINCE2® method and uses PRINCE2®
terminology. The degree of formalization of risk management established in this
document is determined on the basis of project size, its complexity, analysis of
the overall risk of the project, and strategic importance for the organization.
The executive holds accountability for this document and its appropriate
application within the project. Any change suggestions to the risk management
approach should be addressed to the project manager.
4
risks and risk responses.
Communicatin Ongoing communication related to project risk through reports, risk
g register reviews, meetings, and conversations. Continuous updating of
the probability and impact matrix (risk map) and ensuring access to it
by the project board.
Plan (risk Risk response planning (using risk response categories), response
responses) effectiveness analysis, decision trees
Implement Response effectiveness analysis, risk exposure trends
(risk
responses)
Communicatin Probability and impact matrix (risk map), reporting, risk register
g reviews
4 Records
A risk register is kept for the project in an Excel spreadsheet, available to the
entire project team in a dedicated project area(for example on Sharepoint), in
accordance with the risk register template.
5 Reporting
Risks should be reported in project progress reports. These reports should
include at least the following information:
5
report stage (responses to the most important risks)
summary of new risks identified during the stage
top 5 open risks, along with their assessment and planned
responses
risk responses planned to be implemented in the next stage.
End project summary of the most important risks and responses
report implemented
assessment of the effectiveness and efficiency of risk
management activities.
6
ongoing basis
collecting and maintaining the risk-related data and
administering risk-related documentation.
8 Scales
Risk probability will be determined using a five-point scale:
Descriptive
Very low Low Medium High Very high
scale
Definition (%) < 10% 10-30% 30-50% 50-70% 70-90%
Numerical scale 0,1 0,3 0,5 0,7 0,9
Descriptive
Insignificant Low Moderate High Critical
scale
Numerical
0,05 0,1 0,2 0,4 0,8
scale
Budget Insignificant Cost increase Cost increase Cost increase Cost
Impact
7
Duration Duration
Insignificant Duration Duration
increase by increase by
Schedule delay in increase from increase from
less than 5 more than
schedule 5 to 15 days 15 to 30 days
days 30 days
Must-have
requirements
affected.
Could-have Should-have The project
Insignificant Scope
Scope requirements requirements product is
scope impact reduction
affected affected useless
unacceptable
for the
on the project
customer
Must-have
requirements
affected.
Could-have Should-have The project
Insignificant Quality
Quality requirements requirements product is
scope impact reduction
affected affected useless
unacceptable
for the
customer
Loss of more
Loss of up to Loss of 15- than 30% of
Insignificant Loss of 5-15%
5% of 30% of benefits, the
Benefits reduction in of estimated
estimated estimated project loses
benefits benefits
benefits benefits business
justification
The probability and impact matrix (risk map) is a tool for compiling and
prioritizing risks and communicating all risks identified in the project. It will be
applied by mapping risks in accordance with the following table:
Very high
0,9 0,05 0,09 0,18 0,36 0,72
70-90%
High
0,7 0,04 0,07 0,14 0,28 0,56
50-70%
Probability
Medium
0,5 0,03 0,05 0,10 0,20 0,40
30-50%
Low
0,3 0,02 0,03 0,06 0,12 0,24
10-30%
Very low
0,1 0,01 0,01 0,02 0,04 0,08
> 10%
0,05 0,1 0,2 0,4 0,8
Insignific Moderat
Low High Critical
ant e
Impact
8
immediate escalation to the project board (exception
report) together with the proposed action.
9 Proximity
Risk proximity will be determined on a five-point scale, containing the following
categories of proximity:
• at any moment,
• in the current stage,
• in subsequent stages,
• at the end of the project,
• after the end of the project.
10 Risk categories
Risks will be assigned to the following categories:
• technological
• business
• contractual
• management
• social
• external.
Category Description
9
opportunity) basis.
Accept (threat or Taking the chance that the risk will occur, with its full impact if it
opportunity) did.
Prepare contingent
Preparing plans now, but not taking action now. The action will be
plans (threat or
taken should the risk occur.
opportunity)
13 Risk tolerance
The tolerance threshold for the total project's risk exposure calculated
using the expected monetary value method is £180,000.
Tolerance threshold for a single risk: according to the probability and
impact matrix (red box).
Exceeding the tolerance thresholds requires immediate notification of the
project board.
10
14 Risk budget
The costs of management activities related to risks are financed from the
project budget: Section 6. Project management.
The costs of risks responses are covered by the risk budget, set at 15% of
the project budget.
Funds from the risk budget are at the disposal of the project manager.
Expenditures on risk responses exceeding £10,000 must be approved by
the project board, along with approval of actions planned in response to
the risk.
11