The document outlines a Job Hazard Analysis (JHA) for the demolition and installation of a new reinforced concrete apron slab by Renowaras SDN BHD. It details the work activities, potential hazards, and control measures for each step of the installation process, emphasizing safety protocols and responsible personnel. The analysis serves as a guide for workers to follow safety practices and reassess conditions as needed during the task.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
47 views3 pages

5-JHA INSTALLATION FORMWORK AND CONCRETE

The document outlines a Job Hazard Analysis (JHA) for the demolition and installation of a new reinforced concrete apron slab by Renowaras SDN BHD. It details the work activities, potential hazards, and control measures for each step of the installation process, emphasizing safety protocols and responsible personnel. The analysis serves as a guide for workers to follow safety practices and reassess conditions as needed during the task.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

RENOWARAS SDN BHD

JOB HAZARD
DEMOLISH AND INSTALLATION NEW RC APRON SLAB
ANALYSIS REF NO: JSA/1/2024

Task Name: Team Composition: REVISION:


INSTALLATION OF FORMWORK AND 5 WORKERS No of Pages:
CONCRETE

HOW TO USE THIS FORM : WORK ACTIVITY


1) Crew performing task reviews ALL generic JHA/JSA considerations. Installation/Facility Installation Formwork and Concrete
:
2) Review previous JHA/JSA update(s) for useful information which Location Collins Aerospace, Subang Jaya
will help this task. :
3) Create new JHA update with generic form and ALL considerations Associated Work Permit
for this task. Type :
4) Carry out task as per plan. If any conditions change ---STOP & RE- Associated Work Permit
ASSESS. Number:
5) File JHA update for future reference. JHA Cross-Reference
Number :

A. SAFETY, OCCUPATIONAL AND ENVIRONMENTAL HAZARD


JOB
DESCRIPTION OF JOB POTENTIAL HAZARD/S CONTROL / RECOVERY MEASURES PERSON
STEP
RESPONSIBLE
1 Setup site to formwork and pour
concrete Setup site to formwork and pour concrete Inspect all cordsets on tools and equipment for Site supervisor, Site
damage. Engineer, Operator
Concrete Mixer, Safety
Supervisor,

Sprains/Strains Team lift any material, tools or equipment as Site supervisor, Site
needed. Engineer, Operator
Concrete Mixer, Safety
Supervisor,

Struck-by/Crushed by Site supervisor, Site


Setup safe access and barricade for concrete trucks Engineer, Operator
Concrete Mixer, Safety
Supervisor,

2 Install Formwork, and BRC


Sprains/Strains Use legs to lift, do not bend at the waist, team lift if Site supervisor, Site
needed Engineer, Operator
Concrete Mixer, Safety
Supervisor,
1
RENOWARAS SDN BHD
JOB HAZARD
DEMOLISH AND INSTALLATION NEW RC APRON SLAB
ANALYSIS REF NO: JSA/1/2024

Pinch points Use proper hand placement on rebar to avoid Site supervisor, Site
pinching when installing BRC Engineer, Operator
Concrete Mixer, Safety
Supervisor,

Cuts/Lacerations Use leather gloves when handling BRC and tie- Site supervisor, Site
wire Engineer, Operator
Concrete Mixer, Safety
Supervisor,

3 Cast in place concrete


Chemical/ Concrete Burns Use gloves, safety glasses/face shields and wash off Site supervisor, Site
splattered concrete asap with fresh water or Engineer, Operator
neutralizing solution. Concrete Mixer,
Safety Supervisor,

Strains/Sprains Use power screed whenever possible to eliminate Site supervisor, Site
constant bending & pulling motion required by hand Engineer, Operator
screed. Concrete Mixer,
Safety Supervisor,

Struck by/ Crushed by Use chute man to swing concrete chute back & Site supervisor, Site
forth & signal concrete truck driver. Chute man Engineer, Operator
needs to commute with rest of crew when moving Concrete Mixer,
chutes or repositioning truck. Safety Supervisor,
Use a spotter for concrete trucks and all vehicles
in tight or congested areas.

Slips, trips and falls Inspect work area, move material that may cause Site supervisor, Site
trips prior to performing work. Engineer, Operator
Use mesh over rebar to cover holes produced by Concrete Mixer,
BRC. Exposed mesh will be trip hazards until Safety Supervisor,
concrete placed. Keep mesh ends tied down.

Chemical Burns Secure a fresh water souce (a hose) or use Site supervisor, Site
neutralizing solution Engineer, Operator
Concrete Mixer,
Safety Supervisor,

4 Clean up
Slips, trips and falls Inspect work area, move material that may cause Site supervisor, Site
trips prior to performing work. Engineer, Operator
Concrete Mixer,

2
RENOWARAS SDN BHD
JOB HAZARD
DEMOLISH AND INSTALLATION NEW RC APRON SLAB
ANALYSIS REF NO: JSA/1/2024

Safety Supervisor,

5 Secure tools. Slips, trips and falls


Inspect work/staging area. Site supervisor, Site
Engineer, Operator
Concrete Mixer,
Safety Supervisor,