Topic 7 Monitoring and Controlling Bkel v2
Topic 7 Monitoring and Controlling Bkel v2
TOPIC 7:
PROGRESS AND PERFORMANCE
MEASUREMENT AND
EVALUATION
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 1
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 2
CONTENTS
1. Introduction
3. Assignments
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 3
INTRODUCTION
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
4
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
Control
The process of comparing actual performance
against plan to identify deviations, evaluate courses
of action, and take appropriate corrective action.
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 10
through Period 6
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 11
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 12
Common problems:
• Systems that measure only cost variances do not
identify resource and project cost problems associated
with falling behind or progressing ahead of schedule.
• If expenditures are lower than expected for a given period
it may be good or bad, depending on whether progress is
line with that amount of expenditure.
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 14
THE NEED OF
EARNED
VALUE
MANAGEMENT?
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 15
EARNED VALUE
COST/SCHEDULE SYSTEM
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 16
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 17
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 19
Variances
Cost variance (CV) = EV − AC
• Tells us if the work accomplished costs more or less than was
planned at any point over the life of the project.
Schedule variance (SV) = EV − PV
• Presents an overall assessment of all work packages in the
project scheduled to date.
• Contains no critical path information.
• Measures progress in dollars rather than time units.
Variance at completion (VAC) = BAC − EAC
• Suggests whether the costs at completion of the project will
differ from what was planned.
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
Cost/Schedule Graph
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 23
Glossary of Terms
EV (Earned Value) BCWP—budgeted cost of the work performed
The percent complete times its original budget. The percent of the
original budget that has been earned by actual work completed. The
older acronym for this value was BCWP—budgeted cost of the work
performed.
PV (Planned Value) (BCWS—budgeted cost of the work scheduled)
The time-phased baseline of the value of the work scheduled. An
approved cost estimate of the resources scheduled in a time-phased
cumulative baseline (BCWS—budgeted cost of the work scheduled).
AC (Actual Cost) ACWP—actual cost of the work performed
The actual cost of the work completed. The sum of the costs incurred in
accomplishing work. (ACWP—actual cost of the work performed).
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 24
Glossary of Terms
CV (Cost Variance)
Cost variance is the difference between the earned value and the
actual costs for the work completed to date where CV=EV-AC.
SV (Schedule Variance)
Schedule variance is the difference between the earned value
and the baseline line to date where SV=EV-PV.
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 25
Glossary of Terms
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 26
Glossary of Terms
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 27
Glossary of Terms
CPI
1,10
Integrating SPI and CPI
CPI (Cost Schedule problems On schedule
Performance Index) 1,05 Week 4 and on budget
(0.84,1.01) Week 1
Measures cost efficiency of (1.01, 1.01)
the work accomplished to 1,00
date
0,95
Budget
CPI = EV/AC Schedule and problems
SPI (Schedule 0,90 budget problems
Performance Index) 0,85
Measures scheduling Week 2
efficiency to date 0,80 (1.05, 0.85)
Week 3
SPI = EV/PV 0,75
(0.79,0.79)
0,75 0,80 0,85 0,90 0,95 1,00 1,05 1,10
SPI
28
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
Glossary of Terms
ETCe
EACe
0 SD n1 n2
PV ETCf BAC
VACf
EV EACf
AC
VACe
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 29
Glossary of Terms
VAC
Cost variance at completion (BAC-EACe), where EACe is derived by
estimators in the field.
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 30
Interpretation of Indexes
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
1. TABLE 13.3 3
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
3
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
3
1.
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
3
1.
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
3
Glossary of Terms
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 37
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 39
Key Terms
• Control chart
• Revised estimated cost at completion
• Cost performance index (CPI)
(EACre)
• Cost variance (CV)
• Schedule variance (SV)
• Earned value (EV)
• Scheduling performance index (SPI)
• Earned value management (EVM)
• Scope creep
• Forecasted total cost at completion
(EACf) • To complete performance index
• Management reserve index (MRI) (TCPI)
• Percent complete index actual • Tracking Gantt
costs (PCIC)
• Variance at completion (VAC)
• Percent complete index budgeted
costs (PCIB)
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 40
EXAMPLES
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 41
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 42
- Each cost account has only one work package, and each
cost account will be represented as an activity on the
network.
FIGURE 13.6
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 45
FIGURE 13.7
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 46
FIGURE 13.8
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 47
TABLE 13.2
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
48
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
49
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 50
FIGURE 13.9
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 51
FIGURE 13.10
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
52
FIGURE 13.11
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 53
FIGURE 13.12
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 54
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
1. EXHIBIT 13.1
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT 57
FIGURE 13.13
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
58
FIGURE 13.14
Instructor: Dr. Nguyen Thi Duc Nguyen, School of Industrial Management, HCMUT
59