STE Micro Project
STE Micro Project
Prof.
In partial fulfillment of requirement for the award of
Diploma in Computer Engineering
MSBTE, Mumbai.
CERTIFICATE
This is to certify that the micro project report entitled
of semester V institute, Sau. Sundarabai Manik Adsul Polytechnic, Chas, Ahmednagar (code:
1464) has completed the micro project satisfactorily in course (22518) for the Academic year
2024-25as prescribed in the MSBTE curriculum.
Place: Ahmednagar
Date: / /2024.
I take this opportunity to acknowledge the constant encouragement and continuous help given to
me by my guide I convey my sincere thanks to his valuable timely suggestion. I would also like
to thanks principal Prof. Gadakh R.S. and Head of Computer Department Prof. Hole.P.P I would
also like to thank teaching staff of Computer Department for helping us to achieve this goal.
I am also thankful to those who directly or indirectly helped me for completing this micro
project. I would like to thank my parents without whose supports; the completion of the micro
project would not have been possible.
Sr. No Name of Topic Page No
collect information
2 from the internet
and textbook
collect information
from the STE
3 Software testing
22518 reference
book
arrange all
4 information in ms
word
Prepare a report on
5
it using MS word
Sr.
Name of resource material Specifications Quantity
no.
1
3 textbook/manual STE Software testing 22518
Annexure-II
Micro-Project Report
A MICRO PROJECT ON "ONLINE FEEDBACK SYSTEM "
Faculty Module:
Here faculty will first log in to this section. The faculty will enter their user name and
password if the faculties do not have an account they have to sign up in order to
make an account. As the details are filled the faculty dashboard appears in which
they can fill self-appraisal and peer appraisal. The faculty should first fill the self-
appraisal in which they have to rate themselves on some criteria. The peer faculty
has to click on the peer appraisal in order to fill the form as they click on peer
appraisal.
Principal/H.O.D’s Module:
HOD user cannot sign up for the feedback system since she is the only one to
access the feature the login is pre-defined in the code itself. Once the HOD logins
into her portal she can perform various tasks like Giving authority appraisals also
reviewing forms no one is duly filled by faculty after verifying that only then the HOD
can further proceed with the summary form. In summary, the total of all marks will be
calculated and according to it, the percentage is calculated also the grades are
calculated on this percentage basis also she can take a printout of the summary list
and keep a backup of it.
TEST PLAN
Prepare Test Plan for Online Feedback System
1 Introduction
The Test Plan is prepared to define the scope, approach, resources, and schedule of
all testing activities of the project Online Feedback System. The plan identified the
items to be tested, the features to be tested, the kinds of testing to be performed, the
personnel responsible for testing, the resources and schedule needed to complete
testing, and the risks associated with the plan
1.1 Scope
1.1.1 In Scope
All the features of the Online Feedback System which were defined in software
necessity specs are
require to bested
Applicable
odule Name Description
Roles
2 Test Methodology
2.1 Test Levels
In the project Online Feedback System, there're 3 types of testing that should be
conducted.
Integration Testing (Individual software modules are combined and tested as a
group)
System Testing: Conducted on a complete, integrated system to evaluate the
system's
compliance with its specified requirements
API testing: Test all the APIs create for the software under tested
2.2 Suspension Criteria and Resumption Requirements
If the team members report that there are 40% of test cases failed, suspend testing
until the
development team fixes all the failed cases.
2.3 Test Completeness
Specifies the criteria that denote successful completion of a test phase
The run rate is mandatory to be 100% unless a clear reason is given.
The pass rate is 80%, and achieving the pass rate is mandatory
2.4 Project task and estimation and schedule
Task Members Estimate effort
Total 28 man-hour
3) Test Deliverables
Test deliverables are provided below
Before testing phase
Test plans document.
Test cases documents
Test Design specifications.
4) Test Environment
It mentions the minimum hardware requirements that will be used to test the
Application. Following software's required in addition to client-specific software.
Windows 8 and above
Office 2013 and above
5) Terms/Acronyms
Make a mention of any terms or acronyms used in the project
TERM/ACRONYM DEFINITION
In a database system, you may also be able to see past test results and who
generated the results, and the system configuration used to generate those results.
These past results would usually be stored in a separate table.
DEFECT REPORT
Application Test Scenario
Sr.
Name of resource
no Specifications Quantity
material
.
4 GB RAM, Windows
1 Computer System 1
8.1 OS
Methodologies: