RFP_STMC
RFP_STMC
For
on
August 2024
CONTENTS
Description
Deadline for submission of original documents and bid 12.09.2024 upto 3:00 PM at office of SE
PWD(NH) Circle Bikaner Opening of technical bids 12.09.2024 at 05:00 PM
5
NOTICE INVITING TENDER
1. The [Ministry of Road Transport and Highways through Rajasthan PWD represented
by SE PWD(NH) Circle Bikaner hereby invites Single Percentage Rate Bids through e-tendering
from experienced firms/organizations for maintenance works and activities for the following
sections of the National/State Highways/MDR/Rural roads
Average Annual Turn-over during last 3 Work of similar nature during last 5 years
years
Minimum Average Annual Turnover Single work of Rs 230.5 lac
Rs 461.00 lac (estimated cost of work) (minimum 50% of estimated cost of work)
or
Two similar works each of Rs 161.35 lac
(minimum 35% of estimated cost of work)
or
Three similar works each of Rs 115.25 lac
(minimum 25% of estimated cost of work)
6
3. The Scope of Work includes the routine maintenance of all the assets and facilities
existing within Right of Way (ROW) on the above mentioned section including maintenance of
carriageway, shoulders, median, bridges, culverts, drains, footpaths, road signage, plantation
etc., and carrying out other works as specified in the bid documents.
To participate in the bidding, it is mandatory for the Bidders to get registered their firm with e-
procurement portal http://eprocure.gov.in/eprocure/app to have user lD & password which has to
be obtained free of cost. Following may kindly be noted: (a) Registration with e-procurement portal
should be valid at least up to the date of submission of BlD. (b) BlDs can be submitted only during
the validity of registration. The Bidders shall update their project and other details on the portal on
a regular basis and apply to the tenders via the portal. The detailed bid documents can be viewed
on the website 23.08.2024 to 12.09.2024 upto 11:00 AM
5. The complete BID document can be viewed / downloaded from official portal of the CPPP
website (eprocure.gov.in/eprocure/app) from 23.08.2024 to 12.09.2024 upto 11:00 AM
. .The amendments/ clarifications to the Bid Document, if any, will be hosted on the
above website. The bidder is required to submit, along with its BlD, the cost of BID/RFP document,
i.e. Rs. (10000 Rupees only), to Employee/s account through Bharat Kosh
http://www.bharatkosh.gov.in , as mentioned below: The details for payment are as under:
5. The Bid should be submitted online in the prescribed format given on the website. No
other mode of submission is acceptable.
6. The authorized signatory holding Power of Attorney shall only be the Digital
Signatory. In case authorized signatory holding Power of Attorney and Digital Signatory
are not the same, the bid shall be considered non-responsive.
7. The last date for online submission of the Bid is 12.9.20244 upto 11:00 AM (as mentioned on
the e-portal only) ("Bid Due Date"). Bidder must submit its Financial Bid and Technical Bid on CPPP e-
procurement portal within the above deadline. The bids would be opened on 12.09.2024 at 05:00 PM at
Office of SE PWD(NH) Circle Bikaner, representatives of the bidders (maximum of two) who choose to
attend, may attend the online opening of the bids at 05.00PM on the date and time as mentioned above.
However, such representatives shall be allowed to attend the opening of the bids only if they produce
letter of authority on the letterhead of the bidder, at the time of opening of bids as mentioned above
(a) The amount of Bid Security is 9.22 lacs in the form of Original Bank
Guarantee in the format at Section-4 from a Scheduled Bank;
8. The period of validity of bid is 120 days from the deadline of submission of bid.
6
SECTION-2
TABLE OF CLAUSES
1. Scope of Bid
1.1 The Employer (as defined in the Appendix to ITB) invites Single Percentage Rate bids
through the process of e-tendering for works as described in these documents and referred to as
“the Works”. The name and identification number of the Works is as defined in the Appendix to
ITB.
1.2 The successful Bidder will be expected to complete the Works by the intended
Completion Date specified in the Contract Data.
1.3 Throughout these Bidding Documents, the terms “bid” and “tender” and their
derivatives (bidder/tenderer, bid/tender, bidding/tendering, etc.) are synonymous.
2. Source of Funds
2.1 The expenditure under this contract will be met by Ministry of Road Transport
&Highways.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all bidders meeting the qualification requirements
prescribed in Clause 4 of ITB.
3.2 Any entity which has been black listed or barred by the Central or any State Government
or any public sector undertaking, autonomous body or any authority under the Central or State
Government, from participating in any project, and the bar subsists as on the date of Application
shall not be eligible to submit the bid.
13
b) Each bidder must demonstrate for this work:
i) evidence of availability (either owned or leased or rented) of the key equipment
for this work as stated in the Appendix to ITB.
ii) availability of personnel with qualification and experience as stated in the
Appendix to ITB.
4.4 Bidders who meet the minimum qualification criteria will be qualified only if their
available bid capacity is more than the total bid value. The available bid capacity will be calculated
as under:
Available Bid capacity = (A* N* 2.5 - B)
Where.
A = Maximum value of civil engineering works executed in any one year during
the last three years (escalation factor as specified in this section shall be used
to bring the maximum value of civil engineering works to the level of current
financial year i.e.,2024-25) taking into account the completed as well as worksin
progress.
N = Number of years prescribed for completion of the works for which bid is invited.
B = Value (escalation factor as specified in this section shall be used to bring the value
to the level of current financial year i.e.,2024-25) of existing commitments and
on-going works to be completed during the next 12 months (period of
completionof the works for which bid is invited)
4.5 Even though the bidders meet the above qualifying criteria, they are subject to be
disqualified if they have:
i) made misleading or false representations in the forms, statements, affidavits
and attachments submitted in proof of the qualification requirements; and/or
ii) record of poor performance such as abandoning the works, not properly
completing the contract, inordinate delays in completion, litigation history, or
financial failures etc. or debarring from work etc.
6. Cost of Bidding
6.1 The Bidder shall bear all costs associated with the preparation and submission of his
Bid, and the Employer will, in no case, be responsible or liable for those costs.
7. Site Visit
7.1 The Bidder, at his own cost, responsibility and risk, is encouraged to visit, examine and
familiarise himself with the Site of Works and its surroundings including source of earth, water,
road aggregates, availability of labour etc. and obtain all information that may be necessary for
preparing the Bid and entering into a contract for undertaking the maintenance Works. The costs
14
of visiting the site shall be at the Bidder’s own expense. For this purpose, he may contact the
person whose contact details are given in the Appendix to ITB.
B. BIDDING DOCUMENTS
15
result of the pre-bid meeting or which are required in the opinion of the Employer shall be made
by the Employer exclusively through the issue of an Addendum pursuant to Clause 10 and not
through the minutes of the pre-bid meeting.
9.2.4 Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
C. PREPARATION OF BIDS
16
v) Affidavit duly notarized (as per the format provided in Section-3)
12.3 The following documents, which are not submitted with the bid, will be deemed to be
part of the bid.
i) Notice Inviting Tender
ii) Instructions to the Bidders and Appendix to ITB
iii) General Conditions of Contract and Contract Data
iv) Addendum to General Conditions of Contract
v) Road Maintenance Standards and Specifications for Road Maintenance Works,
Part-I and Part-II
vi) Drawings and Schedule of Drawings
16.1 Deleted
17
16.2 Any Bid not accompanied by an acceptable Earnest Money, shall be rejected by the
Employer as non-responsive.
16.3 The Earnest Money of unsuccessful bidders will be returned within 28 days of the end
of the Bid validity period specified in Sub-Clause 15.1.
16.4 The Earnest Money of the successful Bidder will be discharged when the Bidder has
signed the Agreement and furnished the required Performance Security.
16.5 The Bid Security/Earnest Money will be forfeited:
a) if the Bidder withdraws the Bid after its submission during the period of Bid validity;
b) in the case of a successful Bidder, if the Bidder fails within the specified time limit to
i) sign the Agreement; and/or
ii) furnish the required Performance Security.
16.6 In case of forfeiture of bid security, the bidder shall also be debarred from participation
in the works of MoRTH/PWD for a period as decided by Authority.
18
18. Format and Signing of Bid
18.1 The Bidder shall submit e-bid comprising the documents as described in Clause 12
of the ITB.
18.2 The documents to be submitted in the physical form along with the demand draft for
fees/security shall be typed or written in ink and shall be signed by a person duly authorized to
sign on behalf of the Bidder. All the pages of the documents as mentioned here shall be signed by
the person/persons signing the Bid. Documents as mentioned here shall contain no overwriting,
alterations or additions, except those to comply with instructions, issued by the Employer or as
necessary to correct errors made by the Bidder, in which case such corrections shall be made
by scoring out the cancelled portion, writing the correction and signing and dating it along with
the stamp by the person or persons signing the Bid
A. SUBMISSION OF BIDS
20.2 The Employer assumes no responsibility for inability of a bidder to submit bids through
the Employer’s e-tendering portal on account of delay in submission at bidder’s end. Bidders
shall ensure that they submit the bid well before the “Bid Due Date and Time of Bid-Submission”.
The Employer shall not be responsible if bidder is not able to submit the bid on account of failure
in network/internet connection or any other reason whatsoever.
19
20.3 The Employer may extend the deadline for submission of bids by issuing an amendment
in accordance with Clause 10, in which case all rights and obligations of the Employer and the
bidders previously subject to the original deadline will then be subject to the new deadline.
20
23.3 The Employer will prepare minutes of the Bid opening, including the information
disclosed to those present in accordance with this Clause 23.
23.4 The bids accompanied with valid bid security, bid document fee, Tender processing fee
will be taken up for evaluation with respect to the Qualification Information and other information
furnished in Part I of the bid pursuant to Clause 12.1.
As soon as possible, the Evaluation Committee will finalize the list of responsive bidders whose
financial bids are eligible for consideration. However, to assist in the examination, evaluation
of technical bids, the Employer may at his discretion, ask any bidder for clarification of his bid,
however, no additional documents in support of clarification will be entertained.
23.5 The Employer shall inform the bidders about the result of technical evaluation by
uploading on the web portal giving 3 days time for objections, if any, from the bidders. The
Employer shall finalise the evaluation of technical bids after due consideration of objections
received and intimate the bidders, whose Technical Bids are found responsive, of the date, time
and place of opening of the Financial Bids. The Bidders so informed, or their representative, may
attend the event of opening of Financial Bids.
23.6 At the time of the opening of the ‘Financial Bid’, the names of the bidders whose bids
were found responsive in accordance with Clause 23.5 will be announced. The financial bids
of only these bidders will be opened. The responsive bidders’ names, the Bid prices, the total
amount of each bid, pursuant to Clause 22 and such other details as the Employer may consider
appropriate will be announced by the Employer at the time of bid opening.
23.7 The Employer shall prepare the minutes of the opening of the Financial Bids.
21
27. Correction of Errors
27.1 Financial Bids determined to be substantially responsive will be checked by the
Employer for any arithmetic errors. Errors will be corrected by the Employer as follows:
a) Where there is a discrepancy between the rates in figures and words, the rates in
words will govern; and
27.2 The amount stated in the Financial Bid will be corrected as per Clause 27.1 and shall
be binding upon the Bidder. If the Bidder does not accept the corrected amount, the Bid shall be
rejected and the Bid Security shall be forfeited in accordance with Clause 16.6 (b).
C. AWARD OF CONTRACT
30. Employer’s Right to Accept any Bid and to Reject any or all Bids
30.1 Notwithstanding Clause 29, the Employer reserves the right to accept or reject any
Bid, and to cancel the bidding process and reject all bids, at any time prior to the award of
Contract, without thereby incurring any liability to the affected Bidder or bidders or any obligation
to inform the affected Bidder or bidders of the grounds for the Employer’s action.
22
31.3 The Agreement will incorporate all agreements between the Employer and the
successful Bidder. It will be signed by the Employer and the successful Bidder after the
performance security is furnished.
31.4 Upon furnishing of the Performance Security by the successful Bidder, the Employer
will promptly notify the other Bidders that their Bids have been unsuccessful.
32.2 The Performance Security shall be valid until 60 (sixty) days after the Defects Liability
Period.
32.3 For avoidance of any doubt, in case of failure of submission of Performance Security within
the stipulated time period, the award shall be deemed to be cancelled/ withdrawn. Thereupon all rights,
privileges, claims and entitlements of the Contractor under or arising out of the Award shall be deemed
to have been waived by, and to have ceased with the concurrence of the Contractor, and the Award
shall be deemed to have been withdrawn by the Employer.
32.4 The agreement will be executed within 10 days of receipt of Performance Security.
33. Advances
33.1 The Employer will provide Mobilization Advance as provided in Part I General
Conditions of Contract.
24
35. Labour Laws and Regulations
35.1 The Bidders shall be aware of the provisions of various Labour Laws, Regulations
and Welfare Measures applicable for Construction Workers in India, and other obligations stated
in the Conditions of Contract.
25
Appendix to ITB
2. Sensor Paver 1
3. Vibratory Roller (8/10 T) 1
4. Static Roller (8/10 T) 1
5. Small Roller/Compactor 1
6. Bitumen/emulsion sprayer 1
7. Mechanical Broom (1250 sqm per hour) 1
8. Air compressor 2
9. Grader/Backhoe loader 1
26
10. Water Tanker 2
11. Dewatering Pumps 2
12. Tipper/dumper Truck 2
13. Mini hot mix plant (6/10 T/Hr capacity) 1
with indirect heating arrangements
14. Hot Mix Plant 1
15. String line set 1
16. Flotter 1
17. Slip Form Paver 1
18. Skid Vibrator 1
19. Joint Cutting machine 1
.
Note: The bidder must upload scanned copy of the documentary evidence in support of his owning/
leased/rented of the above equipments. In case the bidder proposes to hire or take the above
equipment on lease, he should, along with the lease/rent agreement, attach the proof of ownership
of this equipment with the company/entity from whom the equipment are proposed to be hired on
lease/rent. Any conditional evidence of deployment of above equipment or inadequate proof as
required for any of the equipment shall make the bid non-responsive and financial bid shall not be
opened.
27
4.3 B (b) (ii) The Number of Technical Personnel, Qualifications and Experience will be
as follows:
28
SECTION -3
QUALIFICATION INFORMATION
SECTION -3
QUALIFICATION INFORMATION
The information to be filled in by the Bidder in this section and documents submitted in physical
form will be used for the purposes of post qualification as provided for in Clause 4 of the
Instructions to Bidders. This information will not be incorporated in the Contract.
31
QUALIFICATION INFORMATION
1.3 Total value of Civil Engineering construction and/or maintenance works performed in
the last three years (in Rs. Lakh).
(Upload scanned copies of certificate from Chartered Accountant and also supply original
certificate from Chartered Accountant)
2023-2024
2022-2023
2021-2022
32
1.4 (a) Work performed as prime contractor/JV partner provided further that all other
qualification criteria are satisfied (in the same name) of a similar nature during the last five years
as per ITB Clause 4.3A(b).
* Upload certificate(s) from the Employer (to be given by an officer not below the rank of Executive
Engineer or equivalent or higher and also supply original or certified copy in physical form
envelope)
Note: In case of sub-contractor–a certificate from the Executive Engineer or equivalent of the
Prime Employer should be obtained from whom an approval for subcontractor has been
obtained.
33
1.4 (b) Information on Bid Capacity (works for which bids have been submitted and accepted
and works which are yet to be completed) as on the date 7 days before the last date for bid
submission (as per Clause 4.4 of the ITB).
(i) Existing commitments and on-going works (B)
Description Place & Contract Name & Value of Stipulated Value of Escalation Anticipated Escalated value
of work State No. Address of Contract Period of works* factor date of of remaining work
Employer (Rs Cr) Completion remaining completion during completion
to be period of work for
completed which bids are
(Rs Cr) invited
1 2 3 4 5 6 7 8 9 10
* Upload certificate (s) from the Engineer(s)-in-Charge of the rank of Executive Engineer or
equivalent & also supply original or certified copy of certificate in physical form envelope.
(ii) Details of works for which bid submitted and accepted (i.e. where contract signing is
pending)
Description Place & State Name & Address Date of issue Value given in Stipulated period Value of work during
of works of Employer of Letter of LOA for completion completion period of
Acceptance work for which bids are
(LOA) * invited
1 2 3 4 5 6 7
(iii) Bid Capacity (Bidder shall calculate, mention his bid capacity and enclose the
supporting calculation)
A = Rs. .............. lakh (enclose the details)
N = ......................... years
B = Rs. .............. lakh (enclose the details)
available bid capacity = AxNx2.5 – B
= Rs. ............. lakhs
34
1.5 Availability of Key Equipment essential for carrying out the Works [Ref. Clause 4.3(B)
(b) (i)]. The Bidder should list all the information requested below.
Note: The bidder must upload the documentary evidence in support of his owning/leased/rented
of the above equipment. In case the bidder proposes to hire or take the above equipment
on lease, he should, along with the lease/rent agreement, attach the proof of ownership
of these equipments with the company/entity from whom the equipment are proposed to
be hired on lease/rent. Any conditional evidence of deployment of above equipment or
inadequate proof as required for any of the equipment shall make the bid non-responsive
and financial bid shall not be opened.
1.6 Qualification and Experience of Key Personnel required for administration and
execution of the Contract [Ref. Clause 4.3 (B) (b) (ii)]. Upload biographical data for technical
personnel (Refer also to Clause. 4.1 (e) of Instructions to Bidders).
(Refer also to Sub Clause 9.1 of the General Conditions of Contract).
Note : The signed CVs of the Technical Personnel must be uploaded along with the bid. Non-
compliance of the above or non-furnishing of the CV as above or conditional deployment
of any of the above personnel or proposal to employ lesser number of personnel than
above shall make the bid non-responsive and financial bid shall not be opened.
1.7 Information on litigation history in which the Bidder is involved.
35
AFFIDAVIT
1. I, the undersigned, do hereby certify that all the statements made in the enclosed
attachments are true and correct.
2. The undersigned also hereby certifies that neither our firm M/s
have abandoned any work in India nor any contract
awarded to us for such works have been rescinded, during last five years prior to the date of this
bid.
3. The undersigned hereby Authorise(s) and request(s) any bank, person, firm or
corporation to furnish pertinent information deemed necessary and requested by the Employer
to verify this statement or regarding our competence and general reputation.
4. The undersigned understands and agrees that further qualifying information may be
requested, and agrees to furnish any such information at the request of the Employer and within
the prescribed time.
Name of Firm
Date
To be notarized by Notary
36
UNDERTAKING
Name of Firm
Date
37
UNDERTAKING
Name of Firm
Date
38
SECTION-4
1. In consideration of you, ****, having its office at ****, (hereinafter referred to as the
“Authority”, which expression shall unless it be repugnant to the subject or context
thereof include its, successors and assigns) having agreed to receive the BID of
…………………… and having its registered office at ....................... (and acting on behalf
of its JV) (hereinafter referred to as the “Bidder” which expression shall unless it
be repugnant to the subject or context thereof include its/their executors, administrators,
successors and assigns), for the*** ** maintenance Project on PBMC basis (hereinafter
referred to as “the Project”) pursuant to the Bid Document dated
…………… issued in respect of the Project and other related documents
including without limitation the draft contract Agreement (hereinafter collectively
referred to as “Bidding Documents”), we (Name of the Bank) having our registered
office at ………………… and one of its branches at ……………………..
(hereinafter referred to as the “Bank”), at the request of the Bidder, do hereby in terms of
Clause 16 read with Clause 32.3 of the Bid Document, irrevocably, unconditionally and
without reservation guarantee the due and faithful fulfilment and compliance of the
terms and conditions of the Bidding Documents (including the Bid
Document) by the said Bidder and
unconditionally and irrevocably undertake to pay forthwith to the Authority an amount of
Rs. *** ** (Rupees *** ** only) (hereinafter referred to as the “Guarantee”) as our
primary obligation without any demur, reservation, recourse, contest or protest and
without reference to the Bidder if the Bidder shall fail to fulfil or comply with all or any
of the terms and conditions contained in thesaid Bidding Documents.
2. Any such written demand made by the Authority stating that the Bidder is in default
of the due and faithful fulfilment and compliance with the terms and conditions
contained in the Bidding Documents shall be final, conclusive and bindingon the Bank.
3. We, the Bank, do hereby unconditionally undertake to pay the amounts due and payable
under this Guarantee without any demur, reservation, recourse, contest or protest and
without any reference to the Bidder or any other person and irrespective of whether
the claim of the Authority is disputed by the Bidder or not, merely on the first demand
from the Authority stating that the amount claimed is due to the Authority by reason of
failure of the Bidder to fulfil and comply with the terms and conditions contained in the
Bidding Documents including failure of the said Bidder to keep its BID open during the
BID validity period as set forth in the said Bidding Documents for any reason whatsoever.
Any such demand made on the Bank shall be conclusive as regards amount due and
payable by the Bank under this Guarantee. However, our liability under this Guarantee
shall be restricted to an amount not exceeding Rs. *** **(Rupees *** ** only).
39
4. This Guarantee shall be irrevocable and remain in full force for a period of 150 (one
hundred and fifty) days from the BID Due Date inclusive of a claim period of 60 (sixty)
days or for such extended period as may be mutually agreed between the Authority and
the Bidder, and agreed to by the Bank, and shall continue to be enforceable till all
amounts under this Guarantee have been paid.
5. We, the Bank, further agree that the Authority shall be the sole judge to decide as to
whether the Bidder is in default of due and faithful fulfilment and compliance with
the terms and conditions contained in the Bidding Documents including, inter alia,
the failure of the Bidder to keep its BID open during the BID validity period set forth in
the said Bidding Documents, and the decision of the Authority that the Bidder is in
default as aforesaid shall be final and binding on us, notwithstanding any differences
between the Authority and the Bidder or any dispute pending before any Court,
Tribunal, Arbitrator or any other Authority.
6. The Guarantee shall not be affected by any change in the constitution or windingup
of the Bidder or the Bank or any absorption, merger or amalgamation of the Bidder or
the Bank with any other person.
7. In order to give full effect to this Guarantee, the Authority shall be entitled to treat theBank
as the principal debtor. The Authority shall have the fullest liberty without affecting in any
way the liability of the Bank under this Guarantee from time to time to vary any of the
terms and conditions contained in the said Bidding Documents or to extend time for
submission of the BIDs or the BID validity period or the period for conveying acceptance
of Letter of Acceptance by the Bidder or the period for fulfilment and compliance with all
or any of the terms and conditions contained in the said Bidding Documents by the said
Bidder or to postpone for any time and from time to time any of the powers
exercisable by it against the said Bidder and eitherto enforce or forbear from enforcing
any of the terms and conditions contained in the said Bidding Documents or the
securities available to the Authority, and the Bank shall not be released from its liability
under these presents by any exercise by the Authority of the liberty with reference to the
matters aforesaid or by reason of time being given to the said Bidder or any other
forbearance, act or omission on the part of the Authority or any indulgence by the
Authority to the said Bidder or by any change in the constitution of the Authority or its
absorption, merger or amalgamation with any other person or any other matter or thing
whatsoever which under the law relating to sureties would but for this provision have the
effect of releasing the Bank from its such liability.
10. It shall not be necessary for the Authority to proceed against the said Bidder before
proceeding against the Bank and the guarantee herein contained shall be enforceable
against the Bank, notwithstanding any other security which the Authority may have
obtained from the said Bidder or any other person and which shall, at the time when
proceedings are taken against the Bank hereunder, be outstanding or unrealised.
11. We, the Bank, further undertake not to revoke this Guarantee during its currency
40
except with the previous express consent of the Authority in writing.
12. The Bank declares that it has power to issue this Guarantee and discharge
the obligations contemplated herein, the undersigned is duly authorised and
has fullpower to execute this Guarantee for and on behalf of the Bank.
13. For the avoidance of doubt, the Bank’s liability under this Guarantee
shall be restricted to Rs. *** crore (Rupees *** ** crore only). The Bank
shall be liable to pay the said amount or any part thereof only if the
Authority serves a written claim on the Bank in accordance with paragraph
9 hereof, on or before [*** (indicate date falling 210 days after the BID Due
Date)].
(Signature of the
Authorised Signatory)
(Official-Seal)
FORM OF BANK GUARANTEE FOR PERFORMANCE SECURITY
To
[Address of Employer]
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall
furnish you with a Bank Guarantee for the sum specified therein as security for compliance with
his obligations in accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee:
NOW THEREOF we hereby affirm that we are the guarantor and responsible to you on
behalf of the Contractor, up to a total amount of Rs……………… (amount of guarantee)
(Rupees… .....................................................(in words) and we undertake to pay you, upon your first
written demand and without cavil or argument, any sum or sums within the limits of ………………..
(amount of guarantee) as aforesaid without your needing to prove or to show grounds or reasons
for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before
presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of the Contract
or of the works to be performed there under or of any of the contract documents which may be
made between you and the Contractor shall in any way release us from any liability under this
guarantee, and we hereby waive notice of any such change, addition or modification.
This guarantee shall be valid until 60 days from the date of expiry of the Defects Liability Period.
Notwithstanding anything contained herein before, our liability under this guarantee is restricted
to Rs. (Rs. in words) and the guarantee shall remain valid till
. Unless a claim or a demand in writing is served upon us on or before
all our liability under this guarantee shall cease.
Signature and seal of the Guarantor with Name, Designation, Employee Code Number and
Telephone Number………………………………………………………
42
The guarantor/bank hereby confirms that it is on the SFMS (Structural
Finance Messaging System) platform & shall invariably send an advice of this
Bank Guarantee to the designated bank of RAJASTHAN PWD, details of
which is as under:
Bank/Branch------------------- Branch/Bank------------------------------
Date………………………….
1…………………………………………………………………………………………
2…………………………………………………………………………………………
An amount shall be inserted by the Guarantor, representing the percentage of the Contract Price
specified in the Contract and denominated in Indian Rupees.
43
FORM OF LETTER OF APPLICATION
To,
[Address of Employer]
Dear Sir,
Having examined the Bid Document, Instructions to Bidders, Qualification Information, Scope of
works, etc. for the subject work we hereby submit our bid for the subject work.
It is certified that the information furnished in this document is true and correct. The proposal is
unconditional and unqualified. We undersigned accept that the Employer reserves the right to
reject any or all applications without assigning any reason.
Thanking you,
Yours faithfully,
(Authorized Signatory)
For and on behalf of M/s
44
FORM OF LETTER OF ACCEPTANCE
To
M/s………………………….
Sir,
Based on your bid submitted on................... in compliance of bidding document of [the Employer]
for execution of the works of.......................................................................... , it is hereby notified that
your bid for a Contract Price of Rs…………… (Rupees in words… ...... ) has been accepted for
and on behalf of [the Employer]
You are hereby requested to furnish Performance Security plus additional security in the
form detailed in Clause 32.2 of ITB for an amount equivalent to Rs…………… (Rupees in
words… ) within 10 days as per provisions of Clause 32.1 of ITB of the bid document and
sign the contract agreement failing which the actions as stipulated in Clause-32.3 of ITB shall
be taken.
Thanking you,
Yours faithfully,
(………………..)
Employer
45
FORM OF AGREEMENT
AGREEMENT
46
3. The foregoing documents shall be construed as complementary and mutually
explanatory one with another. Should any ambiguity or discrepancy be noted, then
the order of precedence of these documents shall be subject to the order as listed
above and interpreted in the above order of priority.
4. In consideration of the payments to be made by the Employer to the Contractor as
hereinafter mentioned, the Contractor hereby covenants with the Employer to execute
and complete the works and remedy any defects therein in conformity in all respects
with the provisions of the contract.
5. The Employer hereby covenants to pay the Contractor in consideration of the execution
and completion of the works and remedying of defects therein, the Contract Price or
such other sum as may become payable under the provisions of the contract at the
times and in the manner prescribed by the contract.
IN WITNESS WHEREOF the parties here to have caused this agreement to be executed the
day and year above written. Signed, sealed and delivered by the said Employer through his
Authorized Representative and the said Contractor through his Power of Attorney holder.
2. Name : 2. Name:
Address: Address:
47
SECTION -5
48
SECTION 5
GENERAL CONDITIONS OF CONTRACT (GCC)
TABLE OF CLAUSES
51
A. GENERAL
1. Definitions
1.1 Terms which are defined in the Contract Data but not defined in the Conditions of
Contract keep their defined meanings. Capital initials are used to identify defined terms.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the
Contractor’s Bid.
Certificate of Completion is the Certificate issued by the Engineer upon completion of works or
parts thereof as applicable in accordance with Clause 47.
Compensation Events are those defined in Clause 40.
Contract is the Contract between the Employer and the Contractor to maintain the road assets
and to execute, complete, and maintain the Works. It consists of the documents listed in
Clause 2.3.
Contract Data defines the documents and other information, which comprise the Contract.
Contractor is a person or corporate body whose Bid to carry out the Road Maintenance Works
and Activities has been accepted by the Employer.
Contractor’s Bid is the completed Bidding Document submitted by the Contractor to the
Employer.
Contract Price is the price stated in the Letter of Acceptance and thereafter as adjusted in
accordance with the provisions of the Contract.
Days are calendar days; months are calendar months.
Defect is any part of the Maintenance Works and Activities not completed in accordance with
the Contract Specifications.
Defects Liability Certificate is the certificate issued by the Engineer, after the Defects Liability
Period has ended and upon correction of Defects by the Contractor.
Defects Liability Period means the period so stipulated in the Contract Data, calculated from
the Completion Date, during which the Contractor remains responsible for the rectification of any
defect in the Works he has undertaken.
Employer is the party as defined in the Contract Data, who employs the Contractor to carry out
the Works. The Employer may delegate any or all functions to a person or body nominated by
him for specified functions.
Engineer is the person named in the Contract Data (or any other competent person appointed
by the Employer and notified to the Contractor, to act in replacement of the Engineer) who is
responsible for supervising the execution of the Works and administering the Contract on behalf
of the Employer.
Equipment is the Contractor’s machinery and vehicles brought temporarily to the Site to execute
the Maintenance Works and Activities.
52
Intended Completion Date is the date, as given in contract data, on which it is intended that the
Contractor shall complete the Works as per scope under the contract. The intended Completion
Date may be revised only by the Engineer by issuing an Extension of Time after approval from
the Employer.
Letter of Acceptance means the formal acceptance of the Bid by the Employer.
Materials are all supplies, including consumables, used by the Contractor for incorporation in
the Maintenance Works and Activities.
Maximum Response Time means the maximum permissible time within which remedial action
must be completed prior to a defect exceeding the permissible tolerance. Maximum Response
Time commences from the time of earliest detection of the defect by (i) observation of the defect
by the Contractor, or (ii) notification of the defect by the Engineer, or (iii) intimation of the defect
by a road user.
Notice to Proceed means the notice issued by the Employer to the Contractor to proceed with
the work after signing of the contract pursuant to Clause 32.1 of ITB.
Permissible Tolerance means the maximum permissible amount or quantity of a defect in
road-asset condition that will not be exceeded at any time. If any defect exceeds the permissible
tolerance, it shall be treated as “non-compliance” and the Contractor shall be paid in accordance
with the relevant provisions in this contract.
Project Manager is a person appointed by the Contractor who is in charge of managing all
activities of the Contractor under the Contract. He is also the Contractor’s Representative for the
purpose of this Contract.
Road means the Road or package of roads in network or scattered for which the Maintenance
Works and Activities are to be carried out under the Contract.
“Road Assets” include the following:
i) Main carriageway with shoulders (paved and/or earthen), medians, slip roads,
service roads;
ii) Road embankment including slopes, protection works, kerbs and chute drains;
iii) Roadway in cutting including slopes protection works, drains;
iv) Culverts, Bridges, Over/Underpasses, retaining walls, Guide bunds, Floor
protection works;
v) Road signs, road markings, road delineators, guard rails, safety barriers, railings,
fencings, parapets, kilometre stones, 200 m stones, road boundary stones;
vi) All types of drains, trees, plantations and erosion control measures;
vii) Road land;
viii) Any other project facility or asset forming integral part of the road(s).
Road Maintenance Standards is the collective term for parameters which define the condition
in which the road assets are required to be maintained and other requirements regarding safety
and quality of works to be complied with by the Contractor.
53
Road Maintenance Works and Activities to be carried out by Contractor shall include:
Maintenance of the road specified in the BOQ and executing other items of road maintenance
works as ordered by the Engineer.[Amended as per MoRTH circular RW/G-23012/01/2019-
W&A (Pt III) dated 15.1.2021]
Rectification Standard
The Contractor shall maintain the specific parts of the road aspects as specified in BOQ or as
ordered by Engineer in charge and ensure road users safety and comfort. The maintenance
activities shall be so planned that the defects are repaired well before they reach maximum
condition as per the permissible tolerance.[ Amended as per MoRTH circular RW/G-
23012/01/2019-W&A (Pt III) dated 15.1.2021]
Site is the area defined as such in the Contract Data, where maintenance works are to be
executed.
Specifications means the Specifications of the Maintenance Works including the Road
Maintenance Standards as per the Contract.
Start Date is given in the Contract Data. It is the date when the Contractor shall commence
execution of the Works.
Service Level means the defined condition in which the road assets are to be maintained by the
Contractor.
Sub-Contractor is a person or corporate body who has a Contract with the Contractor to carry
out a work under the Contract, which includes part of the agreed scope of works at the Site.
Temporary Works are works designed, constructed, installed and removed by the Contractor
that are needed for Works and Activities.
Time for Completion means the duration for completing the execution of maintenance works
and passing the tests on completion of the Works or any Section or part thereof as stated in the
Contract Data or as extended by the Engineer by issuing an Extension of Time after the approval
from the Employer.
Variation is an instruction given by the Engineer in writing which varies the scope of Maintenance
Works.
Work Order is an order issued by the Engineer to the Contractor for execution of certain works,
specifying the time limits which may be in variance with the approved programme or in variation
to the scope of work depending upon the site requirement.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also
means female or neuter and the other way around. Headings have no significance. Words
have their normal meaning under the language of the Contract Unless specifically defined. The
Engineer will provide instructions clarifying queries about these Conditions of Contract.
2.2 If part completion is specified in the Contract Data, references in the Conditions of
Contract to the Works, the Completion Date and the Intended Completion Date apply to any part
of the Works (other than references to the Completion Date and Intended Completion Date for
54
the whole of Works).
2.3 The following documents shall be deemed to form and be read and construed as
part of the Contract. In case any ambiguity or discrepancy is noted, then the Contract shall be
interpreted in the following order of priority:
i) Agreement;
ii) Notice to Proceed with the Work;
iii) Letter of Acceptance;
iv) Contractor’s Bid;
v) Contract Data;
vi) General Conditions of Contract;
vii) Road Maintenance Standards and Specifications for Road Maintenance Works,
Part I and Part Il;
viii) Priced Bill of Quantities; and
ix) Any other documents listed in the Contract Data.
4. Engineer’s Decisions
4.1 The Employer shall designate and notify to the Contractor in writing the name of the
Engineer.
4.2 Except where otherwise specifically stated, the Engineer will decide contractual
matters between the Employer and the Contractor in the role representing the Employer. The
Engineer shall have no authority to relieve the Contractor of any of his obligations under the
Contract.
5. Delegation
5.1 The Engineer, duly informing the Employer, may delegate any of his duties and
responsibilities to other people, after notifying the Contractor and may cancel any delegation
under intimation to the Contractor.
6. Communications
6.1 Communications between parties that are referred to in the Conditions shall be
effective only when in writing. A notice shall be effective only when it is delivered as per Indian
Law.
7. Subcontracting
7.1 The Contractor may subcontract any portion of work, up to a limit specified in Contract
Data, with the approval of the Engineer but may not assign the Contract without the approval
of the Employer in writing. Subcontracting shall neither alter the Contractor’s obligations, nor
relieve the Contractor from any liability or obligation under the Contract.
55
7.2 The Contractor shall not be required to obtain any consent from the Employer for:
a) the sub-contracting of any part of the Works for which the Sub-Contractor is
named in the Contract;
b) the provision for labour, or labour component;
c) the purchase of Materials which are in accordance with the standards specified
in the Contract.
7.3 Beyond what has been stated in Clauses 7.1 and 7.2, if the Contractor proposes
sub-contracting of any part of work during execution of the Works, because of some unforeseen
circumstances to enable him to complete the Works as per terms of the Contract, the Employer
will consider the following before according approval:
a) The Contractor shall not sub-contract the whole of Works.
b) The Contractor shall not sub-contract any part of the Work without prior consent
of the Employer. Any such consent shall not relieve the Contractor from any
liability or obligation under the Contract and he shall be fully responsible for the
acts, defaults and neglects of any of his sub-Contractor, his agents or workmen
as if they were the acts, defaults or neglects of the Contractor, his agents and
workmen.
7.4 The Engineer should satisfy himself before recommending to the Employer whether
a) the circumstances warrant such sub-contracting; and
b) the sub-Contractor so proposed for the Work possess the experience,
qualifications and equipment necessary for the job proposed to be entrusted to
him in proportion to the quantum of Works to be sub-contracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other Contractors, public
authorities, utilities, and the Employer between the dates given in the Schedule of Other
Contractors, as referred to in the Contract Data. The Contractor shall also provide facilities and
services for them as described in the Schedule. The Employer may modify the Schedule of
Other Contractors and shall notify the Contractor of any such modification. The Contractor shall
cooperate in such situations as well.
8.2 The Contractor should take up the works in convenient reaches as decided by the
Engineer to ensure that there is least hindrance to the smooth flow of traffic including movement
of vehicles and equipment of other Contractors till the completion of Works.
56
9.2 The Contractor shall use the equipment identified in the bid along with competent
operators and adequate stock of spares for smooth operations.
9.3 If the Engineer asks the Contractor to remove a person who is a member of the
Contractor’s staff or work force, stating the reasons, the Contractor shall ensure that the person
leaves the Site within seven days and has no further connection with the Works under the
Contract.
9.4 The Contractor shall establish, within his own organizational structure, a planning
unit, staffed with suitably qualified personnel. The team will be headed by a Project Manager
who will be assisted by his representatives, i.e. Site Manager and Manager, Planning. The task
of this unit will be:
9.4.1 To plan, and to verify continuously the degree of compliance by the Contractor with
the specified Road Maintenance Standards and report the same to the Engineer in the format
acceptable to the Engineer.
9.4.2 To maintain and update the road condition inventory regularly.
9.4.3 To assist the Engineer in verification of the compliance.
9.5 The Contractor’s planning unit mentioned under Sub-clause 9.4 shall report the
level of compliance with the required Service Levels in the standard formats acceptable to the
Engineer.
13. Insurance
13.1 The Contractor at his cost shall provide, in the joint names of the Employer and the
Contractor, insurance cover from the Start Date to the completion of defect liability period, in that
amounts and deductibles stated in the Contract Data for the following events which are due to
the Contractor’s risks:
57
a) Loss of or damage to the Works and Materials
b) Loss of or damage to Equipment
c) Loss of or damage to property (except the Works Materials and Equipment) in
connection with the Contract
d) Third Party Liability Insurance
e) Automobile Liability Insurance
f) Workers’ Compensation
g) Employer’s Liability
h) Other Insurances
13.2 Insurance policies and certificates for insurance shall be delivered by the Contractor to
the Engineer for the Engineer’s approval before the Start Date. All such insurance shall provide
for compensation to be payable in Indian Rupees to rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates required, the
Employer may affect the insurance which the Contractor should have provided and recover
the premiums the Employer had paid from payments otherwise due to the Contractor or, if no
payment is due, the payment of the premiums shall be a debt due from the Contractor.
13.4 Alterations to the terms of insurance shall not be made without the approval of the
Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies. The Contractor
shall ensure that wherever applicable, its Sub-Contractor(s) shall take out and maintain in effect
adequate insurance policies for their personnel and vehicles and for works executed by them
under the Contract unless such Sub-Contractor(s) is/are covered by the policies taken out by the
Contractor.
58
17. The Works to be completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Maintenance Works and Activities
on the Start Date and shall carry out the Works in accordance with the Programme submitted
by the Contractor, as updated with the approval of the Engineer, and complete them by the
Intended Completion Date.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly discovered
on the Site is the property of the Employer. The Contractor shall notify the Engineer of such
discoveries and carry out the Engineer’s instructions for dealing with them.
59
person/persons/agency authorized by:
a) The Engineer
b) The Employer
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining to the
maintenance works which comply with the applicable laws where the Site is located.
23.2 The Contractor shall permit the Engineer/Employer to inspect the Contractor’s
contemporary records in respect of invoice of bitumen, cement, aggregates and steel, if so
desired by the Engineer.
24.1 Arbitration
The procedure for arbitration will be as follows:
i) In case of Dispute or difference arising between the Employer and the Contractor
relating to any matter arising out of or connected with this contract, such disputes
or differences shall be settled in accordance with the Arbitration and Conciliation
Act, 1996 as amended vide Act of 2015. The Arbitral Tribunal shall consist of sole
Arbitrator from the panel of three Arbitrators proposed by the Employer and choice
of selecting one given to the Contractor. Contractor shall select one out of the three
names of Arbitrators given to him within 30 days failing which the Employer shall
nominate the Arbitrator out of the panel of three Arbitrators. In case the Contractor
objects to the Arbitrator selected by the Employer, the Employer shall refer selection
of Arbitrator to the Indian Roads Congress for nominating the Arbitrator for the dispute
and both parties agree that the Arbitrator so selected by IRC shall decide the dispute.
Indian Roads Congress shall try to appoint Arbitrator preferably from the state where
the project is located or otherwise from adjoining States.
ii) Arbitration proceedings shall be held at [Name of Place], India, and the language of
the arbitration proceedings and that of all documents and communications between
the parties shall be English.
iii) The decision of the Arbitrator shall be final and binding upon both parties. The cost and
expenses of Arbitration proceedings will be paid as determined by the Arbitral Tribunal
However, the expenses incurred by each party in connection with the preparation,
presentation, etc. of its proceedings shall be borne by each party itself. The fees and
expenses of the Arbitrator shall be shared equally by both the parties.
iv) Performance under the contract shall continue during the Arbitration proceedings and
payments due to the Contractor by the Employer shall not be withheld, unless they
are the subject matter of arbitration proceedings.
60
B. TIME CONTROL
25. Programme
25.1 The Contractor shall submit to the Engineer for approval a programme within period
specified in the contract data showing the general methods, arrangements, order, and timing for
all the maintenance works and activities.
25.2 The Engineer may issue the work order in stages specifying the time limit for the
same as and when required except the performance-based maintenance items.
25.3 An update of the Programme shall be a programme showing the actual progress
achieved on each activity and the effect of progress achieved on the timing of the remaining
Works, including any changes to the sequence of activities.
25.4 The Contractor shall submit to the Engineer for approval an updated Programme
at intervals. If the Contractor does not submit an updated Programme within this period, the
Engineer may withhold the amount stated in the Contract Data from the next payment certificate
and continue to withhold this amount until the next payment after the date on which the overdue
Programme has been submitted.
25.5 The Engineer’s approval of the Programme shall not alter the Contractor’s obligations.
The Contractor may revise the Programme and submit it to the Engineer again at any time. A
revised Programme shall show the effect of Variations and Compensation Events.
61
28.2 The Engineer shall record the business of management meetings and provide copies
of the record to those attending the meeting. The responsibility of the parties for actions to be
taken shall be decided by the Engineer either during the management meeting or after the
management meeting and to be intimated in writing to all those who attended the meeting.
C. QUALITY CONTROL
30. Tests
30.1 The Contractor shall set up a field laboratory within period stated in contract data and
be solely responsible for:
a) Carrying out the mandatory tests prescribed in Technical Specifications and
b) For the correctness of test/procedures, whether preformed in his laboratory or
elsewhere.
30.2 If the Engineer instructs the Contractor to carry out a test not specified in the
Specifications to check whether any work has a Defect and the test shows that it does, the
Contractor shall pay for the testing charges and for any number of samples. Otherwise, the
Employer shall pay for the testing charges.
31.5 If during the Defects Liability Period any defect is found in the design, engineering,
materials and workmanship of the Works and Services executed by the Contractor, then the
Contractor shall promptly, in consultation and agreement with the Engineer, appropriately remedy
62
such defects at its cost, or repair, replace or otherwise make good (as the Contractor shall, at its
discretion, determine) such defects as well as any damage to the Road caused by such defects.
31.6 The Contractor’s obligations under this Clause 31 shall not apply to:
a) any material that is supplied by the Employer, and normally consumed in maintenance,
or have a normal life shorter than the Defects Liability Period stated herein;
b) any design, Specification or other data, supplied or specified by or on behalf of the
Employer or any matter for which the Contractor has disclaimed responsibility herein;
31.7 The Employer shall offer the Contractor all reasonable opportunity to inspect the
defect(s) Noticed, as well as provide all necessary access to the Facilities and the Site to enable
him to perform his obligations under this Clause 31.
The Contractor may remove from the Site any Plant and Equipment or any part of the Facilities
that are defective, if the nature of the defect, and/or any damage to the Facilities caused by the
defect, is such that repairs cannot be expeditiously carried out at the Site.
D. COST CONTROL
63
not exceeding the quoted lump sum amount shall be made to the Contractor subject to meeting
the specified maintenance requirements by the Contractor in accordance with the Agreement. It
is agreed, beyond doubt, by the Contractor that no claims shall be entertained by the Engineer/
Employer on account of reduction to any extent, due to budgetary constraints, in quantities of
measurable items.
35. Variations
35.1 The Engineer may order Variations, with the prior approval of the Employer, he
considers necessary or advisable during the progress of the Works. Such Variations shall form
part of the Contract and the Contractor shall execute the varied works. Oral orders of the Engineer
for Variations, unless followed by written confirmation, shall not be taken into account.
39. Payments
39.1 Payments shall be adjusted for deductions for advance payments, security deposit,
other recoveries in terms of the Contract and taxes at source, as applicable under the law. The
Employer shall pay the Contractor the amounts the Engineer had certified, within 28 days of the
date of each certificate.
39.2 The authorized representative of the Employer shall make the payment certified by
the Engineer.
39.3 Items of the Works for which no rate or price has been entered in the Bill of Quantities,
will not be paid for by the Employer and shall be deemed to be covered by other rates and prices
in the Contract.
65
41.2 All payments shall be made in Indian Rupees.
66
demonstrate that the advance payment has been used in this way by supplying copies of invoices
or other documents to the Engineer.
44.3 The advance payment shall be repaid with interest @ SBI PLR applicable on the date
of release of mobilisation advance, by deducting from payments otherwise due to the Contractor.
The mobilisation advance will be recovered from third running bill upto 8th running bill in six equal
instalments and the interest will be recovered from 9th bill. In any case, the mobilisation advance
with interest must be recovered within ten months from the date of agreement. No account
shall be taken of the advance payment or its repayment in assessing valuations of work done,
Variations, Compensation Events, or Liquidated Damages.
47. Completion
47.1 The Contractor shall request the Engineer to issue a certificate of Completion of the
Works, and the Engineer will do so upon deciding that the Works are completed.
67
50. Operation and Maintenance Manual
50.1 If “as built” Drawings and/or operation and maintenance manuals are required relating
to construction work carried out, the Contractor shall supply them within 28 days from the date of
issue of certificate of completion.
50.2 If the Contractor does not supply the Drawings and/or manuals by the stipulated date
or they do not receive the Engineer approval, the Engineer shall withhold the amount equal to
Rs. 5 lakh from payments due to the Contractor.
51. Termination
51.1 The Employer or the Contractor may terminate the Contract if the other party causes
a fundamental breach of the Contract.
51.2 Fundamental breaches of Contract include, but shall not be limited to, the following:
A) Fundamental Breaches by the Contractor
a) the Contractor stops work or grossly neglects Routine Maintenance Works
and Services for 28 days when no stoppage of work is shown on the current
programme and the stoppage has not been authorized by the Engineer;
b) the Contractor is declared as bankrupt or goes into liquidation other than for
approved reconstruction or amalgamation;
c) the Engineer/Employer gives Notice that failure to correct a particular Defect is
a fundamental breach of Contract and the Contractor fails to remedy the defect
and correct it within the period of time determined by the Engineer;
d) the Contractor does not maintain a Security Deposit as per clause;
e) the Contractor has delayed the completion of Works by the number of days for
which the maximum amount of liquidated damages can be paid, as defined in
Clause 43;
f) the aggregate liability of the Contractor to the Employer, exceeds the total
amount specified in the Contract Data, provided that this limitation shall not
apply to the cost of repairing or replacing defective works and equipment;
g) the Contractor fails to provide insurance cover as required under Clause 13;
h) if the Contractor, in the judgement of the Employer, has engaged in the corrupt
or fraudulent practices as defined in Clause 34 of the Instructions to Bidders in
competing for or in executing the Contract;
i) if the Contractor fails to set up a field laboratory with the prescribed equipment,
within the period specified in the Contract Data;
j) if the Contractor does not deploy any of the personnel stated in Contract Data
within 45 days of issue of notice to proceed;
k) The Contractor violates the provisions of Child Labour (Prohibition & Regulation)
Act, 1986;
l) Any other fundamental breaches as specified in the contract data.
68
51.3 Without prejudice to any other right or remedies which the Employer may have under
this contract upon occurrence of a Contractor’s fundamental breach of contract, the Employer
shall be entitled to terminate this contract by issuing a Termination Notice to the Contractor
provided that before issuing the Termination Notice, the Employer shall by a Notice inform the
Contractor of its intention to issue such Termination Notice and grant 15 days to the Contractor
to make a representation and may after the expiry of such 15 days, whether or not it is in receipt
of such representation issue the Termination Notice.
51.4 Notwithstanding the above, the Employer may terminate the Contract for convenience.
51.5 If the Contract is terminated, the Contractor shall stop work immediately, make the
Site safe and secure, and leave the Site as soon as reasonably possible.
53. Property
53.1 All Materials on Site, Plant, Equipment, Temporary Works and Works shall be
deemed to be the property of the Employer for use for completing balance work if the Contract
is terminated because of the Contractor’s default.
69
F. OTHER CONDITIONS OF CONTRACT
55. Labour
55.1 The Contractor shall, unless otherwise provided in the Contract, make his own
arrangements for the engagement of all staff and labour, local or other, and for their payment,
housing, feeding and transport; and for compliance of various labour laws/regulations.
55.2 The Contractor shall, if required by the Engineer, deliver to the Engineer a return in
detail, in such form and at such intervals as the Engineer may prescribe, showing the staff and
the numbers of the several classes of labour from time to time employed by the Contractor on
Site and such other information as the Engineer may require.
55.3 The Contractor’s personnel including equipment operators shall be appropriately
qualified, skilled and experienced in their respective trades or occupations. The Engineer may
require the Contractor to remove or cause to be removed any person employed on the site or
the works, including the Contractor’s representative, if applicable, who
a) Persists in any misconduct or lack of care;
b) Carries out duties incompetently or negligently;
c) Falls to conform with any provision of the contract;
d) Persists in any conduct which is prejudicial to safety, health or protection of the
environment.
If appropriate, the contractor shall then appoint or cause to be appointed a suitable replacement
person
70
57. Drawings and Photographs of the Works
57.1 The Contractor shall do photography/video photography of the site firstly before the
start of work, secondly mid-way in the execution of different stages of work and lastly after the
completion of each item of work. No separate payment will be made to the contractor for this.
57.2 The Contractor shall not disclose details of Drawings furnished to him and works
on which he is engaged without the prior approval of the Engineer in writing. No photograph of
the works or any part thereof or plant employed thereon, except those permitted under Clause
57.1, shall be taken or permitted by the Contractor to be taken by any of his employees or
any employees of his sub-Contractors without the prior approval of the Engineer in writing. No
photographs/video photography shall be published or otherwise circulated without the approval
of the Engineer in writing.
71
CONTRACT DATA
1.1
1. The Employer is [Cl.1.1 of ITB]
Chief Engineer (NH), PWD, Rajasthan
Jaipur
Name of authorized
Representative:[SUPERINTENDING
ENGINEER PWD NH CIRCLE BIKANER ]
7. (a) The law which applies to the Contract is the law of Union of India. [CI.3.1 of GCC]
(b)The language of the Contract documents is English [Cl.3.1 of GCC]
8. The limit of subcontracting is NIL of initial contract price [CI.7.1 of GCC]
9. Schedule of other Contractor- NIL [Cl.8.1 of GCC]
10. The Technical Personnel are [Cl. 9.1 of GCC]
72
S. No. Personnel Qualification Particular Experience No. of
(minimum requirement) Persons
1. Project Manager Degree in Civil 5 years as Project 1
Engineering Manager on Highway,
Bridge construction/
Maintenance works
2. Site Engineer-cum- Degree in Civil 4 years on Highway 1
Surveyor Engineer- Engineering Construction/
cum- Material Engineer Maintenance works
3. Incident cum Road Graduate from 3 years on Highway 1
Property Manager a recognized Property Management
-cum-Route Operation University and Maintenance
Manager
73
b. Maximum limit of liquidated damages 10 per cent of the Initial Contract Price
for delay in completion of work. rounded off to the nearest thousand
[Clause.43 of GCC]
18. The standard form of Performance Security acceptable to the Employer shall be an
unconditional Bank Guarantee of the type as specified in the Bidding Documents.
[Cl. 45.1 of GCC]
19. The percentage to apply to the value of work not completed representing the Employer’s
additional cost for completing the work shall be 20 percent. The Performance Security
shall also be forfeited if the Contract is terminated because of a fundamental breach
of Contract by the Contractor. [Cl.52.1 of GCC]
20. The reasonable cost of removal of equipment and repatriation of the Contractor’s
personnel employed solely on the works in the event of termination of the contract at
the Employer’s convenience or because of a fundamental breach of contract by the
Employer is to be treated as [----Nil-------] lac. [Cl. 52.2 of GCC]
74
SECTION 6
78
prescribed manner. The Act does not apply to certain establishments. The newly set-
up establishments are exempted for five years in certain circumstances. States may
have different number of employment size.
j) Industrial Disputes Act, 1947: The Act lays down the machinery and procedure for
resolution of industrial disputes, in what situations a strike or lock-out becomes illegal
and what are the requirements for laying off or retrenching the employees or closing
down the establishment.
k) Industrial Employment (Standing Orders) Act, 1946: It is applicable to all
establishments employing minimum prescribed number of persons (say, 100, or 50).
The Act provides for laying down rules governing the conditions of employment by
the Employer on matters provided in the Act and get these certified by the designated
Authority.
l) Trade Unions Act, 1926: The Act lays down the procedure for registration of trade
unions of workmen and employees. The Trade Unions registered under the Act have
been given certain immunities from civil and criminal liabilities.
m) Child Labour (Prohibition & Regulation) Act, 1986: The Act prohibits employment
of children below 14 years of age in certain occupations and processes and provides
for regulations of employment of children in all other occupations and processes.
Employment of child labour is prohibited in building and construction industry.
n) Inter-State Migrant Workmen’s (Regulation of Employment & Conditions
of Service) Act, 1979: The Act is applicable to an establishment which employs
minimum prescribed number of labour (say, five or more) inter-state migrant workmen
through an intermediary (who has recruited workmen in one state for employment
in an establishment situated in another state). The Inter-State migrant workmen, in
an establishment to which this Act becomes applicable, are required to be provided
certain facilities such as Housing, Medical-Aid, Travelling expenses from home up to
the establishment and back etc.
o) The Building and Other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 and the Cess Act of 1996: All the establishments
who carry on any building or other construction work and employ the minimum
prescribed (say, 10 or more) number of workers are covered under this Act. All such
establishments are required to pay cess at the rate not exceeding 2 percent of the cost
of construction as may be notified by the Government. As per current notification, one
percent of the cost of construction is payable by the Employer of the establishment.
The Employer of the establishment is required to provide safety measures at the
building or construction work and other welfare measures, such as canteens, first-aid
facilities, ambulance, housing accommodations for workers near to the work place
etc. The Employer to whom the Act applies has to obtain a registration certificate from
the Registering Officer appointed by the Government.
p) Factories Act, 1948: The Act lays down the procedure for approval of plans before
setting up a factory, health and safety provisions, welfare provisions, working hours,
annual earned leave and rendering information regarding accidents or dangerous
occurrences to designated authorities. It is applicable to premises employing the
minimum prescribed number of persons (say, 10 persons or more) with aid of power
or another minimum prescribed number of persons (say, 20 or more persons) without
the aid of power engaged in manufacturing process.
77
SECTION -7
78
SECTION-7
ROAD MAINTENANCE STANDARDS AND SPECIFICATIONS FOR
ROAD MAINTENANCE WORKS, PART-I AND PART-II
PREAMBLE
The Road Maintenance Standards and Specifications shall be read in conjunction with all
other documents constituting the Contract viz. Notice Inviting Tender, Instructions to Bidders;
Conditions of Contract, Bill of Quantities and other related documents mentioned in the Bid
Documents.
General
The Standards and Specifications for the Road Maintenance Works and Activities as described
hereinafter shall comprise of the following:
PART-I : Road Maintenance Standards
PART-II : Specifications for Road Maintenance Works
Carbon foot prints shall be evaluated during the execution of project. If approved by the Employer,
the environment friendly machinery like Infrared Recycling Road Maintenance as approved by
CRRI/IRC/MoRTH shall be got deployed.
81
PART-I
1 Inspections
1.1 The Contractor shall carry out weekly Inspection of project road and submit report to
the Engineer on the maintenance works carried out during the week and also identify other items
of works with location requiring attention for maintenance.
1.2 Any maintenance which involves works of emergent nature and/or replacement shall
be immediately reported to the Engineer for joint assessment and issue of the work order. Such
repairs shall be carried out on authorization by the Engineer except in emergency situations
where it needs to be attended to urgently for safety reasons. In such situations, temporary
arrangements shall be made immediately and further directions sought from the Engineer.
1.3 The Engineer will monitor road condition and shall carry out at least fortnightly
Inspection of the project road to verify that the Contractor is maintaining maintenance standards
as per Contract and to make note of non-compliances of Performance based items of BOQ, other
items of work and work orders issued for other works. Non-compliance/delayed compliance of
maintenance work shall be dealt with as per provisions of GCC Clause 32.1 and maintenance
standards hereinbelow.
82
2.2 [AS PER MoRTH circular no. RW,/G-23012/01/2019-W&A(Pt III)dated 15.1.2021)
3.1 Maintenance standards for cleaning, clearing and repairing roadside open/
unlined/lined/covered drains and cross drainage works
i) The work shall consist of cleaning, clearing, deepening and reshaping of roadside
drains and making shallow lateral drains on shoulders to drain out the rain water/
surface water effectively from bituminous surface as well as from roadside berms.
ii) Disposal of sediments, extraneous debris or vegetation growth, blocking flow.
iii) Safety devices and signs shall be placed as per MoRTH Specifications for Road and
Bridge Works (5th Revision) Clause No. 112.
iv) The excavated material shall be disposed off as directed by Engineer-in-charge with
all leads and lifts.
v) The drain slopes and sides shall be dressed up to original flow line and cross section.
3.4 Maintenance standards for routine maintenance of road signs and delineators
i) The work shall consist of washing of signs, delineators, removal of posters etc. and
repair to supporting structures with repainting.
ii) The road signs and delineators should be thoroughly washed using a detergent
solution followed by a lean rinse and whole face of the sign shall be dried.
iii) Defects in supporting structures like bullet holes, surface marks or bent posts shall be
repaired with appropriate tools.
iv) Damaged area shall be cleaned and loose/flaking paint shall be removed. Bullet holes
shall be filled with filler and supporting structures shall be painted with first quality
enamel paint in two or more coats.
84
PART-II
1. General
1.1 All materials, works and construction operations shall conform to the requirements
laid down in the “Specifications for Road and Bridge Works” (5th Revision), Ministry of Road
Transport and Highways, Published by Indian Roads Congress (IRC), New Delhi; IRC:82 “Code
of Practice for Maintenance of Bituminous Surfaces on Highways” and IRC:SP:83 Guidelines for
Maintenance, Repairs and Rehabilitation of Cement Concrete Pavements” wherever applicable.
Where the Specification for a work is not given, sound engineering practice shall be adopted to
the satisfaction of the Engineer.
“Specifications for Road and Bridge Works, Ministry of Road Transport and Highways” (5th
Revision) is hereinafter referred to as MoRTH Specifications.
3 Quality Control
3.1 Quality control on materials and workmanship is the primary responsibility of the
Contractor. Quality control shall be exercised in accordance with the Quality Plan approved by
the Engineer. The Engineer may, during and after construction test the quality of materials and
work in order to verify conformance with the prescribed Specifications.
3.2 An attempt shall be made to attend to defects like potholes, undulations, rutting,
bleeding, linear and alligator cracks and eroded edges etc. at an initial stage itself. Thermal
bonded patches of regular rectangular shapes without bump or sump shall preferably be adopted.
85
4 Specifications for Routine Maintenance
Before any work is started, signs, barriers, etc. shall be placed and necessary arrangements
made for ensuring safety of traffic and workers in the work zone, as described in Clause 2 of
this Section
Preparation of the surface prior to application of any treatment, shall be carried out in accordance
with the relevant Clauses of MoRTH Specifications.
After completion of the work, the site shall be left cleaned and tidy. No stockpiles of material shall
be left on the road.
86
SECTION 8
91
SECTION–8
All the drawings as and when required by the authority is to be furnished by the
contractor and get it duly approved before execution of the work.
Maintenance Programme
b. Finalization of maintenance programme: This activity shall begin with the stipulated date of
commencement. The various steps proposed to be taken under this are as under:
i. To carry out present state inspection of entire stretch of High way by Contractor &
Engineer.
ii. To identify defects as per various available engineering characteristics of road. The
extent of defects shall be recorded in forms finalized in consultation with authority for paved road,
unpaved road and structure/furniture. All Defects with its extent shall be assessed in terms of
length & area of the subsection, mentioning chainage (locations) in order to have exact estimate
of work.
iii. A comprehensive documentation shall be prepared by Contractor in consultation with
engineer mentioning their assessment of various types of defects in each km of road.
Iv Management meetings shall be called within 15days of inspection to finalize and then to
quantity the defects, This shall be followed by identification of particular maintenance work
proposed to be carried out at site to make good the defects noted above, out of various
alternatives available in BOQ.
92
Work Scheduling
The maintenance and rehabilitation work of road is of unpredictable nature so quantities shown
against each item or work are only representative. It is expected that they would be consumed
during the entire base period of works but employer would not be responsible to pay any
compensation etc. in case there is variation to any extent in quantity of actual execution of
particular item of work with respect to representative quantity shown in BOQ for that particular
work.
Work Control & Quality Assurance
The Engineer shall adopt random sampling procedures to ensure quality control. Engineer shall
carry out in-process inspections and end product inspections to collect sample and shall carry out
testing in order to determine the degree of adherence to the maintenance standards of delivered
or constructed material. Any testing / checking of works by Engineer shall not absolve the
contractor from his responsibility to execute works strictly in accordance of MoRTH / IRC /IS
specifications or laid down standards in bid document. A quality control laboratory equipped with
all instruments required to perform tests as indicated in MoRTH/ IRC/ IS specifications at
frequency mentioned therein shall have to be provided by the contractor. Contractor shall ensure
that testing of all material delivered or constructed is regularly carried out by his filed staff as per
standard norms and results of these tests are recorded in specified manner and made available
to Engineer whenever required by him. The contractor shall provide the QC laboratory, as
incidental to work and no separate payment shall be made for this item. The QC lab shall also be
made available to Engineer for conducting tests of his own. In-process inspections shall be
carried out by the Engineer to witness and/or to verify the quality/quantity of work, when activity is
in process with aim to judge justification of payment. Engineer shall carry out end product
inspections after completion of the activity to provide satisfactory evidence about acceptability of
the contractors work. The results of in process inspections, end product inspections and quality
control tests shall form basis of acceptance of completed works and issuance of Non
Conformance Report (NCR).Items of Works or unit of material or the end product do not meet the
specifications/ standards shall be identified by “Non-Conformance-Report” and can become basis
of rejection of work on establishing the authorized disposition. Non Conformance Report:
Defective or uncompleted work shall not be paid. Such work shall also be notified to the
Contractor within 10 days of submission of bill through non- conformance report (NCR). The NCR
shall clearly identify the item of work that is non–conforming either to specification or to a specific
requirement in the contract document. Once NCR is identified, it shall be evaluated and of the
dispositions would be established. a. “Do” Identifies the work which has not been done at all at
site within specified time limit. An NCR issued with “Do” disposition for the work should
immediately be undertaken by contractor. b. “Re-Do” Identified the work that is non-conforming of
all quality aspects. Such works be totally removed & redone. c. “Re-work” Requires part of
particular item identified in this category be reworked to bring it to the quality required. d. “Use-as-
is” Applied where Engineer accepts work “as-is” notwithstanding the fact that it does not exactly
conform to the contract requirements. This work shall be accepted only for agreed reduced rates
with respect to unit rates quoted in financial bid by the contractor otherwise shall be re-classified
under disposition “Do” or “Re-Do”.
Payment Procedures
The contractor shall submit to the Engineer after the end of each month bill in two copies, each
signed by authorized contractor’s representative in standard format, showing the amounts to
which the contractor considered himself to be entitled upto the end of the month. These bills
should be prepared each indent wise. • The Engineer after scrutiny of the bills shall certify and
recommend the payments for completed accepted works within 14 days of presentation of bill to
him to the employer subject to deductions as per bid documents. • The employer shall pay the
amount due to the Contractor under certificate and recommendations by the Engineer with in 28
days after it has been delivered to the Employer.
95
DESCRIPTION OF WORKS:
FINANCIAL BID
96
BILL OF QUANTITIES
1. Preamble
i) The Bill of Quantities (BOQ) shall be read in conjunction with the Instructions to
Bidders, Conditions of Contract, Road Maintenance Standards and Specifications for
Road Maintenance Works.
ii) The quantities given in the Bill of Quantities are estimated quantities. The basis of
payment will be actual quantities of items of work carried out and valued at the rates
tendered in the BOQ alongwith accepted/awarded tender premium. The accepted/
awarded tender premium above/below the grand total of the project cost shall be
applicable for individual items of work to determine payable amount to Contractor for
work done subject to other contractual provisions. Any variation shall be dealt with as
per contract provisions.
iii) The rates and prices tendered in the BOQ shall include all equipment, tools, spares,
labour, supervision, overheads, consumables, materials, erection, maintenance,
testing of input material delivered, profit, taxes and duties together with general risks,
liabilities and obligations set out and implied in the contract and other incidentals to
comply with the requirements of Standards and Specifications.
iv) Payment for treatment and repair of pot holes/ruts as given in Table below:
Brief Description Weightage for Remarks
performance rating
Providing treatment and To be assessed km Performance measurement
repair to pot holes/ruts wise during bi-monthly to be assessed based on
inspection as per road road maintained as per
Maintenance Standards standards as a proportion of
indicated in Clause 2.1 total project length
97
IRC:SP:124-2019
v) The Contractor shall submit at least once in two months video recording of condition
of the Project Highway with special emphasis on performance based items.
vi) A rate or price shall be entered as a single rate as Tender Premium % above/below
on the rate/amount in the BOQ.
98
BILL OF QUANTITIES
99