Module-I-PREPARATION-FOR-CONSTRUCTION
Module-I-PREPARATION-FOR-CONSTRUCTION
Construction
BUILDING
Equipment
Major Parts of a Building
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
CONSTRUCTION
Retaining Structures
Pavements
l
PREPARATION FOR CONSTRUCTION
Preparation for
Construction 1.0
cdep
building, either partly or entirely
below grade.
Preparation for
Construction 1.0
cdep
Preparation for
Construction
Foundation Bed 1.6 building foundation which forms the FOUNDATION WALLS
Site Investigation
Soil mechanics
permanent retaining wall of the
Excavation & Earthworking structure below grade.
Site Drainage
Slope Protection and CONCRETE MASONRY
Retaining Structures Foundation piers/columns – FOUNDATION WALLS
Pavements piers/columns below grade, to
distinguish them from similar
construction above grade
cdep
FOUNDATION WALL
Preparation for
Construction 1.0
1.6.1 TYPES OF FOUNDATION BEDS
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring Foundation beds may be classified as follows:
Construction Tools &
Equipment
Major Parts of a Building
Foundation Bed 1.6
Site Investigation 1. Rock (solid rock, bedrock or ledge). Undisturbed rock masses forming an
Soil mechanics undisturbed part of the original rock-formation. Some examples of harder rocks
Excavation & Earthworking
Site Drainage are granite, slate, sandstone, and limestone which are all capable of carrying
Slope Protection and the load of any ordinary structure. Examples of softer rocks are shale, shaley
Retaining Structures slates and certain marley limestone and clay stones.
Pavements
2. Decayed rock (rotten rock). Sand, clays and other materials resulting from the
disintegration of rock masses, lacking the coherent qualities but occupying the
space formerly occupied by the original rock.
3. Loose rock. Rock masses detached from the ledge of which they originally
formed a part.
5. Boulders. Detached rock masses larger than gravel, generally rounded and
worn as a result of having been transported by water a considerable distance
from the ledges of which they originally formed a part.
cdep
Preparation for
Construction 1.0
10. Mud. Finely divided earthy material generally containing vegetable matter and deposited
from still or slowly moving water.
11. Mould. Earthy material containing a large proportion of humus or vegetable matter.
14. Filled Ground. All artificial fills and some natural fills are liable to a more or less uniform
but continuous settlement or shrinkage due to the gradual consolidation of the material of
which the fill is composed
cdep
Preparation for
Construction 1.0
cdep
Preparation for
Construction 1.0
cdep
Loading tests of the materials forming
the foundation bed are made to assist
in determining its safe bearing
capacity.
Preparation for
Construction 1.0
1.8 SOIL MECHANICS
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
1.8.1 CLASSES OF SOIL
Equipment
Major Parts of a Building There are two broad classes of soil:
Foundation Bed
Site Investigation
Soil mechanics 1.8
Excavation & Earthworking
Site Drainage A. Course-grained soil – consist
Slope Protection and
Retaining Structures of relatively large particles,
Pavements visible to the naked eyes.
B. Fine-grained soil –
consist of much smaller
particles, such as silt and clay.
cdep
Preparation for
Construction 1.0
cdep
OH Organic clay & silt Very poor Impervious
cdep
groundwater.
Preparation for
Construction 1.0
cdep
Preparation for
Construction 1.0
cdep
interfere with the excavation procedure.
Preparation for
Construction 1.0
cdep
Preparation for
Construction 1.0
cdep
building, esp. one of two supports
for a needle
Preparation for
Construction 1.0
WATER TABLE
AFTER PUMPING
cdep
Preparation for
Construction 1.0
A. SUB-SURFACE DRAINAGE –
consists of an underground network of piping for conveying groundwater
to a point of disposal, as a storm sewer system or a natural outfall at a
lower elevation on the site. Excess groundwater can reduce the load-
carrying capacity of a foundation soil and increase the hydrostatic
pressure on a building foundation. Waterproofing is required for basement
cdep
structures situated close to or below the water table of a site.
Preparation for
Construction 1.0 Components of the sub-surface drainage system are:
Staking-Out the Building
Laying the Batterboards Catch Basins
Formwork & Shoring receptacles for the runoff of SWALES
Construction Tools &
Equipment
surface water. They have a basin
Major Parts of a Building or sump that retains heavy
Foundation Bed
Site Investigation
sediment before it can pass into
Soil mechanics an underground drainpipe. AREA DRAIN
Excavation & Earthworking
Site Drainage 1.10
Slope Protection and Culverts
Retaining Structures are drains or channels passing under
Pavements
a road or walkway.
CATCH BASINS
Drainage tile
is a hollow tile, usually laid end to end
as piping (with open joints) in soil in
order to drain water saturated soil, or
CATCHMENTS
used to permit fluid in the hollow-tile
pipe to disperse into the ground (as in
cdep
an absorption field).
Preparation for
Construction 1.0
Swales
shallow depressions formed by the
intersection of two ground slopes,
designed to direct or divert the runoff
of surface water. Grass swales slope
1.5% to 2%; while paved swales, 4%
to 6%.
SWALES
cdep
Preparation for
Construction 1.0
cdep
surface water.
ABSORPTION TRENCH
Preparation for
Construction 1.0
cdep
Preparation for
Construction 1.0
3. Riprap is a layer of irregularly broken
Staking-Out the Building
Laying the Batterboards and random-sized stones placed on the
Formwork & Shoring slope of an embankment. RIPRAP
Construction Tools &
Equipment Depth of layer should be greater
Major Parts of a Building than the maximum size of stone
Foundation Bed
Site Investigation
Soil mechanics FILTER FABRIC or GRADED
Excavation & Earthworking SAND and GRAVEL for drainage
Site Drainage
Slope Protection and
Retaining Structures
1.11
Pavements
cdep
Preparation for
Construction 1.0
cdep 0.5 H
Preparation for
Construction 1.0
b) T-type Cantilevered Retaining Wall – limited to a height of
Staking-Out the Building
Laying the Batterboards 20’ (6 M); beyond this height a counterfort wall is employed.
Formwork & Shoring
Construction Tools &
8” (205)
Equipment Batter refers to backward
Major Parts of a Building sloping face of a wall as it
Foundation Bed
Site Investigation
rises to offset illusion of face
Soil mechanics leaning forward
Excavation & Earthworking
Site Drainage Temperature steel for walls
Slope Protection and
Retaining Structures
1.11 more than 10” (255) thick
Pavements
Drainage mat w/ filter fabric
0.6H or porous gravel backfill
(0.9H w/ surcharge)
2” (51 mm) o weepholes @
4’-6’ (1220-1830mm) o.c. or
perforated drainpipe sloped
to outlet away from wall
2” (51) min
3” (75) min
Structural Steel
reinforcement
cdep
2’ (610mm) below the
grade level,
whichever is higher
Preparation for
Construction 1.0
0.7H
(1.25 w/ surcharge)
0.6H
(1.0 w/ surcharge)
cdep
Preparation for
Construction 1.0
cdep
FLEXIBLE PAVEMENTS
Preparation for
Construction 1.0
cdep
Preparation for
Construction 1.0
cdep
Preparation for
Construction 1.0
cdep
Preparation for
Construction
BUILDING
Staking-Out the Building
Laying the Batterboards
CONSTRUCTION
Formwork & Shoring
Construction Tools &
1 Equipment
Major Parts of a Building
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
Pavements
END