PQC Method Statement
PQC Method Statement
Tentative start date is January, 2002. However this work will start stretch wise after at
least 1000 M continuos stretch of DLC is laid , cured & approved by the Engineer .
This Work Method Statement is for the entire contract stretch (i.e. Km 0+000 to
Km 53+410.) along the proposed alignment. The area involved will be within inner
edges of Gravel shoulders on either side of the proposed carriageways.
The work involve , the construction of unreinforced , Dowel jointed , Plain Cement
Concrete Pavement in accordance with the requirements of the MOST specification
clause 602 and in the conformity with the lines , grades & cross fall as per the
contract drawing .
One team with Wirtgen SP 500M Paver will be deployed for complete job.
Effective paving rate per hour = 70 M 3/Hr.
Considering effective paving hour = 10 Hr.
There fore per day paving quantity = 70X10 = 700 M 3
Hence total working days required =290489/700 = 415 Days
Considering 25 days paving/month,Total days required=498 days
Add for monsoon =180 days
Total duration of paving =678 days say 23months.
POSSIBLE PROBLEMS:
1. The road side slope of embankment of carriageway to be paved first will encroach
upon the existing road by 4 to 5 mts as shown in the enclosed Annexure-I.In view
of the above encrochment,the available pavement width will be insufficient to
accommodate the existing traffic. For uninterrupted traffic ,an additional pavement
of width of atleast 4.0M has to be constructed on the other side with sufficient
crust thickness to withstand the axle loads under clause 51.1(e) of GCC.
2. Adverse climatic condition such as high ambient temperature, high velocity of
wind, unexpected/ intermittent rain may hamper the paving work.
2
CONCLUDED/PARALLEL/PRECEEDING ACTIVITIES:-
b) Activities that can continue parallel to the concrete paving work are
1. Construction of gravel shoulder by the side of previously laid pavement.
2.Paving of DLC over approved GSB layer at other locations.
3.Initial joint cutting of pavement laid on the previous day.
4.Preparation for next days paving work.
RESOURCES:
KEY PERSONNELS
Other personnel like Paving supervisors, grade & level checker , QC helpers and
operators will be available at site on shift basis as per actual requirement.
MAJOR EQUIPMENTS :
1. Crushing plant with primary & secondary Crushers - Capacity 200 TPH
2. Automatic Concrete Batching Plant of 90cum - 2Nos
3. Wirtgen SP 500M Concrete Slip Form Paver - 01 No.
4. Wirtgen SP 850 Texturing & Curing Machine - 01No.
5. Excavator - 01No.
6. Concrete cutting Saw (Target 65 HP 4 Stroke M/C) - 02 Nos.
7. Water tankers with side sprinkling bar - 03 Nos
8. Tipper Trucks (TATRA 25 MT capacity ) - 09 to 14 Nos
(As per lead from
3
MATERIALS :
QUALITY CONTROL:
Quality Control tests for Concrete Pavement construction will be done as per MOST
specification clause 903.5.2 and will be followed by routine tests . Frequency of the
quality control tests will be as per the table No. 900.6 of MOST specification.
In addition to that , temperature of water before mixing at batching plant will be
ensured to bring concrete temperature within 30 0C at site . If required necessary
quantity of Chilled water / Ice will be added .
Before starting the paving work , wind velocity will be measured with the help of
Anemometer and will be ensured to be within the specified limit.
QUALITY ASSURANCE :
QA team will be responsible for documentation of all tests, QC records, Jointly with the
Engineer. QA team will ensure that QC tests are being conducted at site as per the
MOST norms and Engineers requirements.
In addition to the above , a paving register will be maintained at paving site in which
following details will be recorded for each dump truck / TATRA jointly with the
Engineer
1. Dump truck / TATRA No.
2. Quantity in M3
3. Time of despatch from Batching Plant .
4
Level Pads will be given at 5M interval at the both sides of paving lane at 1.5M or
suitable distance from the paving edge. Levels of these level pads will be jointly
checked by the Engineer before commencement of the days paving work. During
paving , level dips will be checked with the help of a measuring tape & string behind
the paver at every level stack (ie. @ 5M interval ).
QUANTITY SURVEY :
For the assessment of Quantity , a joint record of paved locations during the month
with lane details & levels/thickness details will be maintained at site and will be
produced before raising the monthly invoice.
SAFETY CONTROLS :
1. One safety plan will be prepared before commencement of Paving work activities.
2. Paving area will be marked/ barricated.
3. Necessary sign-boards and precautionary boards will be placed near working
locations.
4. Flag man and signal man will ensure regulation of traffic and dump trucks/TATRA at
paving site.
5. Dump trucks/TATRA will travel with minimum speed limit and will be provided with
reverse horns or signal man near unloading / paving area .
6. Safety stewards will conduct daily checking to ensure the working areas as safe.
7. Workmen and operators will be provided with necessary safety appliances.
8. Pep-talks will be given to all workmen at site to provide awareness and follow safe
working practice at site.
ENVIORNMENTAL CONTROL :
1. Dust pollution at Batching Plant area & paving area will be kept under control by
sprinkling of water from water tankers on earthen road / service road.
2. Sound pollution due to heavy machineries will be ensured to be minimum by way
of proper maintenance and tuning of engines.
3. Smoke pollution from all machines like Paver unit , Poclain , DG sets, Dump trucks/
TATRAs , Water tankers etc. will be ensured to be minimum by proper maintenance
and tuning of engines .
4. Cement leakage from Silos at Batching Plant will be ensured to be minimum by
proper maintenance and by introduction of cement filter unit so that the wastage
and escape of cement particles to the atmosphere will be controlled . In addition
5
to that proper care will be taken at the time of cement loading in Silos by using
proper pipe connection.
The Cement Concrete Pavement will be laid over Dry Lean Concrete, which will
be laid by sensor Paver to the required level , grade and compaction. PQC will be
laid over DLC after a curing period of seven days.Slipform Paving operation will be
in the following steps :-
18. Expansion joints will be provided at the end of the days work only to minimize
the number of joints for better riding quality.
19. At the expansion joint filler board will be provided as per the specification.
1. Texturing and Curing machine will follow the paver and the working platform.
2. The distance between paver and curing machine will be as per the climatic
condition , initial hardening of concrete and finally texturing grove depth and this
distance will be decided by the paving engineer at site.
3. The movement of the brush will be in the transverse direction and it will be
automatically controlled by the texturing machine .The depth of the Texturing will
be as per the specification.
4. Soon after the texturing , the approved quality of curing compound will be sprayed
on the paved surface by the texturing/curing machine. The process of texturing
and curing will go on simultaneously for complete paving operation.
5. Curing compound will be sprayed using pressure nozzles on top and on both sides
of the paved surface @ 4 to 5 sqm/lit.
V). Covering
1. After the application of curing compound the concrete will be covered by the
plastic sheet to prevent loss of moisture from concrete due to evaporation.
2. The concrete will be kept covered till curing compound is set.
1. The location of dowel bars marked on the side of concrete will be once again
confirmed by the cutting team and marked on both sides of paved surface. These
points on either side of paved surface will be joined and marked on concrete
surface with the help of a string & paint brush in the transverse direction.
2. The transverse joints cutting will be taken up after confirming the hardening and
setting of the concrete – to take the load of the sawing machine and no impression
formed on laid concrete.
3. This joint cutting will be done by using diamond edge saw blades of required
thickness (3mm) . The width and depth of cut will be maintained as per the
specification. After the initial cut ,the joints will be observed everyday. If any crack
does not develop at this location the cut is taken again to slightly more depth.
4. Soon after initial cut a compressible backup rod is inserted to avoid accumulation
of dirt in the joints.
VII). Curing
1. After the initial cut of transverse joints are completed, the paved surface will be
covered with wet hessian cloth.
2. Paved surface will be kept moist by sprinkling water with the help of water tankers
fitted with sprinkler arm for a period of 14 days after laying of concrete.
8
1. Joint sealing work will be carried out after the completion of curing period of
concrete (ie. After the 14 days of construction)
2. The transverse and longitudinal joints will be widened subsequently by sawing
before sealing. Depth/width gauges shall be used to control the dimension of the
groove.
3. The widened grooves will be cleaned to remove the loose dirt and dust particles by
using air compressor.
4. For joint sealing, an approved quality material will be used.
5. Joint sealing will be done by specialised applicators.
IX). Communication