The document outlines the construction program for a proposed 34-storey affordable housing block, detailing various tasks, their durations, and timelines from May 2016 to September 2018. Key tasks include mobilization, tower construction, typical floor completion, and various finishing works. The overall project is scheduled to be completed in 731 days, with specific milestones for each phase of construction.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
10 views4 pages
master program rev1a
The document outlines the construction program for a proposed 34-storey affordable housing block, detailing various tasks, their durations, and timelines from May 2016 to September 2018. Key tasks include mobilization, tower construction, typical floor completion, and various finishing works. The overall project is scheduled to be completed in 731 days, with specific milestones for each phase of construction.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4
MAIN BUILDING WORKS FOR THE PROPOSED 1 BLOCK 34 STOREY RUMAH MAMPU MILIK
Construction Programme (Revision 01a)
ID Task Name Duration Start Finish 2016 2017 2018
AprMayJun Jul AugSepOct NovDec JanFebMar AprMayJun Jul AugSepOct NovDec JanFebMar AprMayJun Jul AugSep Oct Nov 1 Overall Project Completion 731 days? Tue 3/5/16 Sat 1/9/18 2 Preliminaries 35 days Tue 3/5/16 Sat 11/6/16 3 Mobilisation 14 days Tue 3/5/16 Wed 18/5/16 4 Setting & Survey 7 days Tue 3/5/16 Tue 10/5/16 5 Site Facilities 21 days Wed 11/5/16 Fri 3/6/16 6 Fabrication Yard 21 days Thu 19/5/16 Sat 11/6/16 7 8 TOWER 712 days? Wed 11/5/16 Sat 18/8/18 9 tower crane 1 593 days? Mon 13/6/16 Fri 4/5/18 10 foundation 14 days Mon 13/6/16 Tue 28/6/16 11 erection 30 days Wed 29/6/16 Tue 2/8/16 12 dismantling 1 day? Fri 4/5/18 Fri 4/5/18 13 tower crane 2 522 days? Mon 13/6/16 Sat 10/2/18 14 foundation 14 days Mon 13/6/16 Tue 28/6/16 15 erection 30 days Wed 29/6/16 Tue 2/8/16 16 dismantling 1 day? Sat 10/2/18 Sat 10/2/18 17 Car Parks Below Tower 230 days Wed 11/5/16 Thu 2/2/17 18 Grd Flr (WBLFL) 60 days Wed 11/5/16 Tue 19/7/16 19 1st Flr 42 days Mon 13/6/16 Sat 30/7/16 20 2nd Flr 42 days Wed 29/6/16 Tue 16/8/16 21 3rd Flr 42 days Fri 15/7/16 Thu 1/9/16 22 4th Flr 42 days Mon 1/8/16 Sat 17/9/16 23 5th Flr 42 days Wed 17/8/16 Tue 4/10/16 24 6th Flr 42 days Fri 2/9/16 Thu 20/10/16 25 7th Flr 42 days Mon 19/9/16 Sat 5/11/16 26 8th Flr - Facilities 48 days Wed 5/10/16 Tue 29/11/16 27 Transfer Level 60 days Fri 28/10/16 Thu 5/1/17 28 9th Flr 45 days Tue 13/12/16 Thu 2/2/17 29 Typical Floors 336 days Sat 14/1/17 Fri 9/2/18 30 level 10 28 days Sat 14/1/17 Wed 15/2/17 31 level 11 16 days Fri 10/2/17 Tue 28/2/17 32 level 12 16 days Thu 23/2/17 Mon 13/3/17 33 level 13 16 days Wed 8/3/17 Sat 25/3/17 34 level 14 16 days Tue 21/3/17 Fri 7/4/17 35 level 15 16 days Mon 3/4/17 Thu 20/4/17 36 level 16 16 days Sat 15/4/17 Wed 3/5/17 37 level 17 16 days Fri 28/4/17 Tue 16/5/17 38 level 18 16 days Thu 11/5/17 Mon 29/5/17 39 level 19 16 days Wed 24/5/17 Sat 10/6/17 40 level 20 16 days Tue 6/6/17 Fri 23/6/17 41 level 21 16 days Mon 19/6/17 Thu 6/7/17 42 level 22 16 days Sat 1/7/17 Wed 19/7/17 43 level 23 16 days Fri 14/7/17 Tue 1/8/17 44 level 24 16 days Thu 27/7/17 Mon 14/8/17 45 level 25 16 days Wed 9/8/17 Sat 26/8/17 MAIN BUILDING WORKS FOR THE PROPOSED 1 BLOCK 34 STOREY RUMAH MAMPU MILIK Construction Programme (Revision 01a)
ID Task Name Duration Start Finish 2016 2017 2018
AprMayJun Jul AugSepOct NovDec JanFebMar AprMayJun Jul AugSepOct NovDec JanFebMar AprMayJun Jul AugSep Oct Nov 46 level 26 16 days Tue 22/8/17 Fri 8/9/17 47 level 27 16 days Mon 4/9/17 Thu 21/9/17 48 level 28 16 days Sat 16/9/17 Wed 4/10/17 49 level 29 16 days Fri 29/9/17 Tue 17/10/17 50 level 30 16 days Thu 12/10/17 Mon 30/10/17 51 level 31 16 days Wed 25/10/17 Sat 11/11/17 52 level 32 16 days Tue 7/11/17 Fri 24/11/17 53 level 33 16 days Mon 20/11/17 Thu 7/12/17 54 Water Tank Level 28 days Sat 2/12/17 Wed 3/1/18 55 LMR 21 days Fri 29/12/17 Mon 22/1/18 56 Upper Roof 21 days Wed 17/1/18 Fri 9/2/18 57 Staircase 450 days Fri 2/9/16 Thu 8/2/18 58 Staircase Podium 150 days Fri 2/9/16 Thu 23/2/17 59 Staircase Tower 300 days Fri 24/2/17 Thu 8/2/18 60 Mock Up Floor 132 days Tue 14/3/17 Mon 14/8/17 61 Remedial Works to RC Walls 14 days Tue 14/3/17 Wed 29/3/17 62 Brickworks 21 days Fri 24/3/17 Mon 17/4/17 63 Aluminium Frames and Door Frames 7 days Tue 18/4/17 Tue 25/4/17 64 Skim Coat 10 days Sat 22/4/17 Wed 3/5/17 65 M&E 1st Fix 7 days Tue 18/4/17 Tue 25/4/17 66 Backing Screed - Walls & Floors 10 days Wed 26/4/17 Sat 6/5/17 67 Setting Out Review 7 days Mon 8/5/17 Mon 15/5/17 68 Wall Finishes 10 days Tue 16/5/17 Fri 26/5/17 69 Ceiling 10 days Mon 22/5/17 Thu 1/6/17 70 Floor Finishes 14 days Fri 2/6/17 Sat 17/6/17 71 Door Leaves 3 days Mon 19/6/17 Wed 21/6/17 72 Painting - Sealer & First Coat 5 days Thu 22/6/17 Tue 27/6/17 73 Interior & Fit Out Works 28 days Wed 28/6/17 Sat 29/7/17 74 M&E 2nd Fix 5 days Mon 31/7/17 Fri 4/8/17 75 Painting - Final 3 days Sat 5/8/17 Tue 8/8/17 76 M&E Final Fix 5 days Wed 9/8/17 Mon 14/8/17 77 Architectural Finishes 412 days Wed 26/4/17 Sat 18/8/18 78 internal & external Walls 320 days Wed 26/4/17 Thu 3/5/18 79 Doors 320 days Wed 31/5/17 Thu 7/6/18 80 Windows 320 days Fri 16/6/17 Sat 23/6/18 81 Internal Finishes 320 days Mon 3/7/17 Tue 10/7/18 82 Floor Finishes 320 days Wed 19/7/17 Thu 26/7/18 83 Ceiling Finishes 320 days Fri 4/8/17 Sat 11/8/18 84 Painting & Decorations 320 days Mon 7/8/17 Tue 14/8/18 85 Sanitary Fittings 150 days Mon 26/2/18 Sat 18/8/18 86 External Wall Finishes 210 days Mon 27/11/17 Sat 28/7/18 87 Staircase Finishes 120 days Fri 9/2/18 Thu 28/6/18 88 Electrical works 455 days Sat 14/1/17 Thu 28/6/18 89 conduit / trunking 360 days Sat 14/1/17 Fri 9/3/18 90 sub circuit wiring 360 days Sat 18/2/17 Fri 13/4/18 91 sub main cable / busduct 350 days Sat 25/3/17 Mon 7/5/18 92 sub switch board / distribution board 75 days Tue 27/2/18 Thu 24/5/18 93 ELV cabling & wiring 360 days Sat 18/2/17 Fri 13/4/18 MAIN BUILDING WORKS FOR THE PROPOSED 1 BLOCK 34 STOREY RUMAH MAMPU MILIK Construction Programme (Revision 01a)
ID Task Name Duration Start Finish 2016 2017 2018
AprMayJun Jul AugSepOct NovDec JanFebMar AprMayJun Jul AugSepOct NovDec JanFebMar AprMayJun Jul AugSep Oct Nov 94 fittings 120 days Fri 9/2/18 Thu 28/6/18 95 Fire fighting works 538 days Fri 25/11/16 Tue 14/8/18 96 fire alarm system 470 days Fri 25/11/16 Sat 26/5/18 97 conduit / wiring 440 days Fri 25/11/16 Sat 21/4/18 98 fittings 60 days Thu 1/3/18 Wed 9/5/18 99 main fire alarm panel 60 days Mon 19/3/18 Sat 26/5/18 100 hose reel system 455 days Fri 25/11/16 Wed 9/5/18 101 piping 440 days Fri 25/11/16 Sat 21/4/18 102 fittings 60 days Thu 1/3/18 Wed 9/5/18 103 pump & panel 90 days Fri 3/11/17 Thu 15/2/18 104 wet riser system 455 days Mon 12/12/16 Fri 25/5/18 105 piping 440 days Mon 12/12/16 Tue 8/5/18 106 fittings 60 days Sat 17/3/18 Fri 25/5/18 107 pump & panel 60 days Fri 8/12/17 Thu 15/2/18 108 fireman intercom system 455 days Mon 12/12/16 Fri 25/5/18 109 conduit / wiring 440 days Mon 12/12/16 Tue 8/5/18 110 fittings 60 days Sat 17/3/18 Fri 25/5/18 111 fire extinguisher 30 days Wed 11/7/18 Tue 14/8/18 112 hydrant system 45 days Sat 17/3/18 Tue 8/5/18 113 T&C 60 days Sat 21/4/18 Fri 29/6/18 114 Plumbing works 529 days Fri 21/10/16 Fri 29/6/18 115 concealed pipes 360 days Sat 14/1/17 Fri 9/3/18 116 vertical stack 210 days Fri 21/10/16 Thu 22/6/17 117 fittings 240 days Wed 13/9/17 Tue 19/6/18 118 T&C 60 days Sat 21/4/18 Fri 29/6/18 119 CAR PARK & FACILITIES DECK 686 days Mon 13/6/16 Tue 21/8/18 120 Internal & External Walls 250 days Fri 21/10/16 Tue 8/8/17 121 Doors 250 days Mon 7/11/16 Thu 24/8/17 122 Windows 250 days Mon 12/12/16 Thu 28/9/17 123 Internal Finishes 250 days Mon 16/1/17 Thu 2/11/17 124 Floor Finishes 250 days Mon 20/2/17 Thu 7/12/17 125 Ceiling Finishes 250 days Mon 27/3/17 Thu 11/1/18 126 Painting & Decorations 250 days Fri 3/11/17 Tue 21/8/18 127 Sanitary Fittings 60 days Mon 11/6/18 Sat 18/8/18 128 External Wall Finishes 150 days Thu 27/4/17 Wed 18/10/17 129 Staircase Finishes 120 days Thu 19/10/17 Wed 7/3/18 130 Sundries 30 days Mon 16/7/18 Sat 18/8/18 131 Podium 150 days Mon 5/2/18 Sat 28/7/18 132 swimming pool 60 days Mon 5/2/18 Sat 14/4/18 133 finishes 60 days Mon 12/3/18 Sat 19/5/18 134 landscape 30 days Mon 21/5/18 Sat 23/6/18 135 hardscape 30 days Mon 25/6/18 Sat 28/7/18 136 TNB SSU 152 days Mon 7/11/16 Tue 2/5/17 137 architectural Finishes 90 days Mon 7/11/16 Sat 18/2/17 138 electrical works 30 days Mon 20/2/17 Sat 25/3/17 139 TNB underground ducting & manhole 32 days Mon 27/3/17 Tue 2/5/17 140 CO2 system 14 days Mon 27/3/17 Tue 11/4/17 141 FM200 system 14 days Mon 27/3/17 Tue 11/4/17 MAIN BUILDING WORKS FOR THE PROPOSED 1 BLOCK 34 STOREY RUMAH MAMPU MILIK Construction Programme (Revision 01a)
ID Task Name Duration Start Finish 2016 2017 2018
AprMayJun Jul AugSepOct NovDec JanFebMar AprMayJun Jul AugSepOct NovDec JanFebMar AprMayJun Jul AugSep Oct Nov 142 Electrical works 640 days Mon 13/6/16 Thu 28/6/18 143 conduit / trunking 340 days Mon 13/6/16 Thu 13/7/17 144 sub circuit wiring 300 days Mon 26/9/16 Sat 9/9/17 145 sub main cable / busduct 220 days Mon 9/1/17 Thu 21/9/17 146 sub switch board / distribution board 60 days Fri 22/9/17 Thu 30/11/17 147 ELV cabling & wiring 230 days Mon 31/10/16 Tue 25/7/17 148 fittings 120 days Fri 12/1/18 Thu 31/5/18 149 T&C 45 days Tue 8/5/18 Thu 28/6/18 150 151 M & E WORKS 437 days Fri 3/2/17 Wed 27/6/18 152 Electrical works 437 days Fri 3/2/17 Wed 27/6/18 153 infrastructure 88 days Sat 17/3/18 Wed 27/6/18 154 compound & street light 60 days Sat 17/3/18 Fri 25/5/18 155 telephone installation 60 days Tue 3/4/18 Mon 11/6/18 156 LV cable 60 days Thu 19/4/18 Wed 27/6/18 157 TNB SSU, 11kV consumer room, MSB & genset room 165 days Fri 3/2/17 Mon 14/8/17
158 HT installation 45 days Wed 3/5/17 Fri 23/6/17
159 LV installation 30 days Sat 24/6/17 Fri 28/7/17 160 TNB 11kV bulk meter 14 days Sat 29/7/17 Mon 14/8/17 161 Genset 110 days Fri 3/2/17 Sat 10/6/17 162 Plumbing works 134 days Fri 3/2/17 Sat 8/7/17 163 pump & panel 90 days Fri 3/2/17 Thu 18/5/17 164 incoming main pipe 30 days Mon 5/6/17 Sat 8/7/17 165 Lift services 119 days Tue 23/1/18 Sat 9/6/18 166 plumbing 7 days Tue 23/1/18 Tue 30/1/18 167 door jamb 21 days Wed 31/1/18 Fri 23/2/18 168 guide rail 21 days Sat 24/2/18 Tue 20/3/18 169 lift car 14 days Wed 21/3/18 Thu 5/4/18 170 electrical work 14 days Fri 6/4/18 Sat 21/4/18 171 motor 21 days Mon 23/4/18 Wed 16/5/18 172 T&C 21 days Thu 17/5/18 Sat 9/6/18 173 174 INFRASTRUCTURE WORKS 218 days Sat 2/12/17 Mon 13/8/18 175 On Site Detention Tank 28 days Fri 8/12/17 Tue 9/1/18 176 Sewerage Reticulation 120 days Sat 10/2/18 Fri 29/6/18 177 Water Reticulation 120 days Sat 10/2/18 Fri 29/6/18 178 Retaining Wall 120 days Sat 2/12/17 Fri 20/4/18 179 Surface Water Drainage 90 days Sat 10/2/18 Fri 25/5/18 180 Roads & Pavement 60 days Sat 26/5/18 Fri 3/8/18 181 Fencing & Gate 60 days Sat 26/5/18 Fri 3/8/18 182 Ancillary Buildings 75 days Sat 10/2/18 Tue 8/5/18 183 Hardscape 128 days Sat 17/3/18 Mon 13/8/18 184 Cleaning & Clearing 149 days Tue 13/3/18 Sat 1/9/18