7.IdwalPrePurchaseReport Container Sample
7.IdwalPrePurchaseReport Container Sample
Example Individual
Organisation:
Example Organisation
Example Containership
INSPECTED IN AUSTRALIA
1st OCTOBER 2022
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
This report is intended for the sole use of Example Individual and is designed to o er a condition evaluation of the subject
vessel, as found on the day of the survey and in the opinion of the surveyor concerned. The report is subject to any access
restrictions as described herein, and subject always to the level of cooperation a orded to the surveyor during the inspection
itself. All details are given in good faith, and without guarantee.
This report has been prepared and issued by Idwal Marine Services Ltd to its Customer, Example Individual of Example
Organisation, in accordance with, and subject to, the General Terms and Conditions of Idwal Marine Services Ltd, a copy of
which can be obtained at www.idwalmarine.com/terms-conditions. Attention is particularly drawn to restrictions on
reproduction and disclosure of, and limits on reliance on, this Report as more fully set out therein.
To access all documents related to this report, and verify the authenticity of its contents,
please view the full version available here:
customer.idwalmarine.com/0-0000
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 1
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
CONTENTS
INSPECTION
. . . . . . . . . . . . . . . . . . . .SUMMARY
....................................................................................................................................................
3
COMPARE
. . . . . . . . . . . . . . . . YOUR
. . . . . . . . . .IDWAL
. . . . . . . . . . .GRADE
5
...................................................................................................................................
KEY
. . . . . . .NOTABLE
. . . . . . . . . . . . . . .ITEMS
..................................................................................................................................................
6
DECARBONISATION
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .SUMMARY
8
.........................................................................................................................................
GRADING
. . . . . . . . . . . . . . . DATA
.........................................................................................................................................................
9
DESIGN
. . . . . . . . . . . . .AND
. . . . . . . CONSTRUCTION
10
..............................................................................................................................................
HULL
..................................................................................................................................................................
11
MOORING
. . . . . . . . . . . . . . . . .DECKS
12
.................................................................................................................................................
WEATHER
. . . . . . . . . . . . . . . .DECKS
. . . . . . . . . . .AND
. . . . . . .FITTINGS
13
................................................................................................................................
BALLAST
. . . . . . . . . . . . . . TANKS
. . . . . . . . . . .AND
. . . . . . . SYSTEMS
15
..................................................................................................................................
ACCOMMODATION
..................................................................................................................................................................
16
BRIDGE
. . . . . . . . . . . . AND
. . . . . . . .NAVIGATION
. . . . . . . . . . . . . . . . . . . . EQUIPMENT
17
..........................................................................................................................
ENGINE
. . . . . . . . . . . . .ROOM
. . . . . . . . . . .AND
. . . . . . . MACHINERY
...................................................................................................................................
18
FIRE
. . . . . . . .FIGHTING
. . . . . . . . . . . . . . . .EQUIPMENT
. . . . . . . . . . . . . . . . . . .AND
. . . . . . . SYSTEMS
21
................................................................................................................
LIFESAVING
. . . . . . . . . . . . . . . . . . .APPLIANCES
...............................................................................................................................................
22
SAFE
. . . . . . . . WORKING
. . . . . . . . . . . . . . . . ENVIRONMENT
23
..........................................................................................................................................
POLLUTION
. . . . . . . . . . . . . . . . . . . CONTROL
24
...............................................................................................................................................
ONBOARD
. . . . . . . . . . . . . . . . .MANAGEMENT
26
.................................................................................................................................................
VESSEL
. . . . . . . . . . . .CAPABILITIES
. . . . . . . . . . . . . . . . . . . . .AND
. . . . . . . CARGO
. . . . . . . . . . . .SYSTEMS
27
..............................................................................................................
ADDITIONAL DOCUMENTS
Vessel documents
Vessel photos
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 2
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
INSPECTION SUMMARY
74 GRADE
VESSEL PA R TI C ULA R S
01/01/2014
Delivery Date
ExampleMT
Example 1 Oct 2022 Status: 6 Hours Limited Dead Weight
ExampleMT
Australia Loading Aboard documents
Gross Tonnage
provided Example MT
Net Tonnage
Example m
The Example Vessel is an example DWT, example Gross Tonnage, Length Overall
Example flagged, gearless Containership vessel built to a good standard Example m
by Example Shipbuilding, in China under Example Class supervision and Breadth
Examplem
was delivered on the 1st January 2014. The vessel remains Classed with Depth
Example m
Example Class.
Summer Draught
Example
A Pre-purchase Inspection of the vessel was conducted on the 1st TEU
Example MT
October 2022 in Sydney by Idwal under instruction from Example Owner. Lightweight
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 3
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
The vessel was found to be in good overall condition with an Idwal Grade
above the average for vessels of a similar age, type and size but with a few
notable items found during the inspection. These are reported specifically in
the notable items section of this report.
The onboard management was found to be good with the Safety
Management system found to be well implemented and the vessel generally
found to provide a safe working environment. The Port State Control (PSC)
history was found to be good with 7 deficiencies and 0 detentions in the 5
inspections conducted in the past three years.
The vessel's Attained EEXI was calculated to be between 18.37 and 19.51,
which is above the required EEXI of 17.08, and therefore the vessel will
require the installation of technologies to reduce the EEXI score.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 4
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
This section of the report allows you to compare your ship's grade with similar ships.
Your Idwal Grade vs other Feeder Container vessels This graph shows the distribution of
Idwal Grades against your ship's
Vessel Grade: 74 sector.
8
Percentage of Total Ships
Average Grade: 73
0
50 55 60 65 70 75 80 85 90
Idwal Grade
Your Idwal Grade vs other Feeder Container vessels, age 5-10 years This graph shows your ship’s Idwal
Grade compared against other ships
inspected in the same sector, within a
90 similar age range, and how it
compares against the average Idwal
Grade for the sector.
80
Idwal Grade
70
60
50
0 5 10 15 20 25 30
Ship Age
The ship’s grade may appear different when compared with the average of the two graphs. This is as a result of the second graph
comparing a smaller and more focused sample of ships.
For a more in-depth analysis of where your vessel compares amongst its peers, please contact your Idwal sales rep.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 5
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
The vessel does not use Environmentally Various upgrades and modifications $20000 - $50000
Acceptable Lubricants (EALs) in the stern may be required if the vessel wishes
tube or has an airseal and is therefore not to trade in the USA.
VGP compliant in this regard.
The vessel has one Condition of Authority The Condition should be thoroughly $1000 - $5000
as follows: The BWMS has not been addressed to Class satisfaction by the
commissioned at D-2 due date. due date.
Contingency measures according to IMO
Circular BWM.2/Circ.62 will be used for
managing non-compliant ballast water
discharges, until the installation and
commissioning is completed. Agreement
on contingency measures must be
obtained from the Coastal State of
destination before exercised and arrival of
coastal area. Due Date: 06 Dec 2022.
High running hours were noted on To be further investigated and any $20000 - $50000
auxiliary engines 2, 3 and 4 since the last required overhauls carried out as
overhaul. However, no set overhaul soon as practical.
intervals were provided.
Cargo hatch covers were seen to have Remedial cosmetic maintenance to <$1000
moderate scattered spot corrosion to the be carried out as soon as practical.
tops.
Gauges for LT fresh water cooling pump To be further investigated and <$1000
and fresh water heater unit were found to rectified as soon as practical.
be damaged.
ER air vent blower outlet cover, in way of To be further investigated and <$1000
auxiliary engine number 4, was found to rectified as soon as practical.
be missing.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 6
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
Windlass band brakes had only minimal Band brake linings to be renewed <$1000
thicknesses remaining. when possible.
Main and auxiliary engine performance Ensure all future engine performance <$1000
reports were seen to all have been carried tests are carried out at a minimum
out at a low loads. load of 70% as per good marine
practice.
Please note, all costs are estimations only, based on industry averages, and may vary depending on locations and scopes of
work. These costs are provided to assist the reader to consider the potential Capex or Opex impact of the related Notable Item
and should not be used for budgeting purposes without further internal assessment of their accuracy.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 7
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
DECARBONISATION SUMMARY
The vessel was delivered to the market before the EEDI requirements, and therefore has no EEDI score assigned. Based
on information provided by the vessel during the inspection, the Attained EEXI score was calculated to be between 18.37
and 19.51. This Attained EEXI score is above the required EEXI of 17.08, and therefore the vessel will require the
installation of technologies to reduce the EEXI score. For more information about technologies to reduce a vessel's EEXI,
the creation of the EEXI technical file or operational measures to reduce a vessel's Attained CII, please contact your Idwal
sales representative.
EEXI
Vessel does not meet the EEDI/EEXI requirement and requires additional retrofitting of technologies
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 8
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
74
GRADING DATA
GRADE
The Idwal Grade® is an industry recognised measure of asset integrity. Using proprietary algorithms, the Idwal Grade is
programmatically calculated from over 500 individual data points, captured during a rigorous and standardised inspection
process. Our data-driven methodology ensures that our reports are consistent, accurate and free from bias.
SUB GRADES
The methodology used to calculate the Idwal Grade® is also applied to the grading of the different vessel areas and categories.
Two key areas are the overall vessel condition and vessel management:
Condition 74 Management 73
The following are grades representing individual areas of interest of the vessel:
PSC Performance 80
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 9
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
80
The construction and design was found to be hold a Class notation for In Water Surveys. No Cargo Lifting
good overall, with the vessel built to IACS Appliances are fitted. Apart from the equipment required by
standards and Rules in China by Example international rules and regulations, the bridge is also fitted
Shipbuilding with the keel laid in January 2013. The vessel is with integrated bridge system, machinery space control
a Containership, with 5 holds, driven by a xed pitch, direct system repeater panel and differential-GPS and the engine
drive propeller. The Main Engine is a NOx Tier 2, Hyundai room and machinery are fitted with incinerator sludge
Heavy Industries and the vessel has 4 Auxiliary Engines, burning system, UMS capabilities, 2-stroke engine
and no shaft generator. It is not on the Enhanced Survey mechanical lubricator and dual air handling unit
Program or Extended Dry Docking schedule but does refrigeration compressors.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 10
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
HULL
70
The hull was seen to be in a fair to good overall foulings. Areas of abrasions from fenders and tugs were also
condition, primarily due to the levels of corrosion noted. Hull markings were partly obscured, with several
noted, with the hull able to be inspected from the draft markings found to be covered with corrosion, with
port side only. The vessel was found to be free of both minor marine fouling observed. The vessel's last out of
major and minor structural defects and had only minor water bottom survey was carried out on 09-Sept-19, with the
localised spot corrosion, up to approximately 5% of the vessel’s next out of water bottom survey due by 21-Oct-24.
surface area, mainly located to midships boot top and anti-
NOTABLE ITEMS
Description Estimated
Cost [USD]
Issue: Several draft markings found to be covered with corrosion.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 11
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
MOORING DECKS
80
The Mooring decks were seen to be in a good replacement. Clutching and gearing arrangements were
condition overall with the decks found to be free sufficiently greased. Anchor chains and mooring ropes were
of structural defects and had only minor scattered in a good overall condition. Mooring practices were seen to
spot corrosion, up to approximately 2% of the mooring deck be good and snap-back zone warnings were seen to be
plating total surface area, mainly located to deck plating. posted at the entrances to mooring areas as per industry
Deck fittings were found to be in a good condition with best practice. The Bosun's store was in a fair overall
fairleads and mooring rollers free to turn when tested. All condition with it noted that the housekeeping could be
Electric windlasses and winches were reported to be fully improved upon. The bitter end release arrangements were
operational. Mooring machinery was in good condition seen to be clear and unobstructed and the emergency
however, band brake thicknesses were minimal, and require towing booklet seen to be available near to the Foc'sle.
NOTABLE ITEMS
Description Estimated
Cost [USD]
Issue: Windlass band brakes had only minimal thicknesses remaining.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 12
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
70
The Weather Decks and Fittings were seen to be in and cross deck areas. Deck fittings were found to be in a
fair to good condition overall, primarily due to the good condition with pipework and fittings free of leakages.
levels of corrosion noted. The were decks found The accommodation ladders and gangways were in a good
to be free of structural defects and had only minor scattered overall condition, with no notable defects found, as were
spot corrosion, up to approximately 5% of the main deck provisions lifting appliances.
plating total surface area, mainly located to deck walkways
NOTABLE ITEMS
Description Estimated
Cost [USD]
Issue: Scattered areas of corrosion noted to deck plating under cross deck lashing walkways.
Corrective Action: Remedial cosmetic maintenance to be carried out as soon as practical. <$1000
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 13
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
Description Estimated
Cost [USD]
Issue: Scattered areas of corrosion were noted to the main deck walkways and cross deck areas.
Corrective Action: Remedial cosmetic maintenance to be carried out as soon as practical. <$1000
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 14
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
80
Ballast tanks and systems were deemed to be in a spot corrosion, up to approximately 2% of the ballast tanks
good overall condition. No tanks could be entered total surface area, mainly located to edges of supports.
due to however, a very small number of Ballast tank fittings such as ladders and pipework were seen
photographs of previous tank entries in 22-Sept-22 were to be in a good overall condition with Anodes seen to be
provided for review. Due to the small number of previous depleted up to 5%. Tanks were seen to have a minimal
inspection photos provided for review the condition of the amount of mud/sediment accumulation but were free of
tanks is primarily based upon vessels of a similar age, type any signs of staining from sewage or marine fouling. Ballast
and size. From the photographs provided, it was seen that control systems such as valves and gauges were reported to
the ballast tanks were found to be generally free of be fully operational and all ballast pumps were in good
significant structural defects and had only minor localised working order and in good visual condition.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 15
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
ACCOMMODATION
80
The accommodation areas were seen to be in a the galley hoods also found to be kept clean. The vessel's
good condition overall with floor and wall walk-in cold rooms were found to be clean and hygienic
coverings found to be in good condition and with temperatures at the required levels. Provision room
upholstery and furniture found to be free from components were seen to be generally free of frosting and
deterioration and defects. The levels of housekeeping and deterioration. The external superstructure was found to be
cleanliness was found to be good with levels of hygiene also free of structural defects and had only minor localised spot
seen to be good in the sanitary facilities. The hospital was corrosion, up to approximately 2% of the surface area,
seen to be well equipped and ready for use with drugs and mainly located to the edges of port holes and around weld
controlled substances locked away. The associated drugs log seams. The external superstructure fittings were seen to be
was kept up to date. The accommodation was found to be in a good overall condition with all external accommodation
outfitted to an average quality. The Air Handling Unit (AHU) doors in good working order and properly closing. The Crew
was found to be maintaining a comfortable temperature Welfare was found to be in good overall with it noted that
and was seen to be in good condition with no defects. The the vessel is fitted with a paid to access yet unlimited Wi-Fi
galley equipment was deemed to be in a good overall system and crew were reported to have access to a well-
condition with all equipment reportedly in good working stocked bond store.
order. The galley was found to be in a clean condition with
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 16
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
90
The Bridge and navigation equipment were found generally up-to-date. The vessel is licensed to cover GMDSS
to be in a good to very good condition overall sea areas A1, A2, and A3 and had a valid shore-servicing
with housekeeping found to be good and with all agreement in place. The radio batteries were seen to be well
bridge equipment reported to be fully operational. The maintained and in good condition and the EPIRB, SART and
vessel's was found to be free from any unanticipated alarms VHF handheld batteries were all in date as required. Berth to
with collection instructions posted nearby and with the berth passage plans were seen on-board and were signed by
Bridge Navigation Watch Alarm System (BNWAS) reported to all navigating officers with nautical publications provided in
be fully operational. The vessel's primary means of Electronic format. Master's standing and night orders were
navigation, as listed on form E of the safety equipment found to be signed by all navigating officers with the bridge
certificate is a dual ECDIS system which were found to be up log book correctly filled in and the GMDSS logbook also up
to date. RADAR blind sectors were seen to be posted near to date and correctly filled in. The Monkey island was found
the RADARs with the compass deviation card up-to-date and to be in a good overall condition with the mast, aerials and
available near to the helm. The compass deviation log was antennas seen to be satisfactory and free of defects.
found to be satisfactory, with no major deviations and
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 17
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
60
The Engine room and machinery were found to be including the Bow thruster were in good working order with
in a fair overall condition, primarily due to the no defects reported or sighted. The 4 Auxiliary Engines were
high running hours since last overhaul for reported to be fully operational and were seen to be in
auxiliary engines 2, 3, and 4. with no significant defects good condition, with no major visible defects. A review of
reported or observed and with the engine room generally the latest Auxiliary engines performance report provided
found to be clean. During the inspection the Auxiliary showed some areas of concern as follows: seen to have
Engines, purifiers, pumps, air compressors and sewage been carried out at a low loads, 60%. Auxiliary engines
treatment plant were seen running. Bilges and tank tops running hour data was provided post inspection with high
were generally free of oil or water. Pipework was seen to be running hours noted on engines 2, 3 and 4 since the last
in good overall condition, free of leaks, temporary repairs overhaul. However, no set overhaul intervals were provided.
and significant corrosion with pipework lagging seen to be The vessel's steam boiler was found to be fully operational
all clean and intact. Housekeeping was seen to be to a good but in fair condition with the circulation pump pressure
overall standard with the vessel found to be equipped with gauge found to be damaged. The boiler safety valves were
adequate critical spares as recommended by the ship seen to be satisfactory and free of tampering. All Auxiliary
manager Safety Management System (SMS) which were seen equipment was found to be fully operational and in good
to be neatly stowed and secured. A review of the latest lube condition barring pumps and fresh water generator, which
oil analysis reports provided showed no areas of concern. were in fair condition with gauges for LT fresh water cooling
The Main Engine was reported to be fully operational and pump and fresh water heater unit were found to be
was seen to be in good condition, with no major visible damaged. The steering gear was seen in good working order,
defects. A review of the latest Main Engine performance free of leakage with emergency steering instructions seen to
report provided showed some areas of concern as follows: be posted nearby. The machinery spaces are operated in
seen to have been carried out at a low load, 45%. A review Unmanned mode and the alarm and control system was
of the latest engine running hours showed that the Bearings seen to be free of any serious alarms. Electrical distribution
and Cylinder Liners overhaul schedules are subject to systems including the main switchboard were in good
Condition Based Monitoring (CBM) and therefore no working order and switchboard insulation readings were
dedicated overhaul intervals are provided. Cylinder heads adequate. However an ER air vent blower outlet cover, in
and Pistons running hour data was not provided for review. way of auxiliary engine number 4, was found to be missing.
Propulsion systems, such as shafts, gearing and bearings
NOTABLE ITEMS
Estimated
Description Cost
[USD]
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 18
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
Issue: High running hours were noted on auxiliary engines 2, 3 and 4 since the last overhaul. However,
no set overhaul intervals were provided.
$20000 -
Corrective Action: To be further investigated and any required overhauls carried out as soon as $50000
practical.
Description Estimated
Cost [USD]
Issue: The boiler circulation pump pressure gauge was found to be damaged.
Description Estimated
Cost [USD]
Issue: Gauges for LT fresh water cooling pump and fresh water heater unit were found to be
damaged.
<$1000
Corrective Action: To be further investigated and rectified as soon as practical.
Description Estimated
Cost [USD]
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 19
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
Issue: ER air vent blower outlet cover, in way of auxiliary engine number 4, was found to be missing.
Estimated
Description Cost
[USD]
Issue: Main and auxiliary engine performance reports were seen to all have been carried out at a low
loads.
Corrective Action: Ensure all future engine performance tests are carried out at a minimum load of <$1000
70% as per good marine practice.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 20
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
80
Fire Fighting Equipment and Systems were found fire main and ancillaries such as hydrants and valves were in
to be in a good condition overall and generally good overall condition, free of defects. Fire extinguishers
free of fire hazards with all firefighting equipment were all in good condition and all portable equipment were
seen to be regularly serviced and inspected. The fire positioned in accordance with the fire plan. Firefighting
detection and alarm system was found to be fully outfits and associated equipment were all in good condition
operational and was free of signs of tampering and alarms. with BA equipment found fully charged and ready for use.
The vessel is fitted with CO2 and Water Spray fixed The emergency generator was tested during the inspection
firefighting in the engine room, CO2 and Water Spray for the and found to be in good working order and in a good
cargo areas and no fittings in the accommodation. Fixed overall condition. Remote shutdown emergency devices
firefighting systems were all reported to be in good working such as quick closing valves, machinery stops and
condition with operating instructions clearly posted. The ventilation dampers were deemed to be in a good overall
main and emergency fire pumps were reportedly fully condition with no defective shut down equipment. The fire
operational and both were found to be in a good condition, doors were found to be in good condition, closing
free of leakages. A fire pump was tested during the effectively and free from any unauthorised 'hold-open'
inspection and was found to deliver adequate pressure. The arrangements.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 21
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
LIFESAVING APPLIANCES
80
Lifesaving appliances were seen to be in a good arrangements were found to be in good condition overall
overall condition with all equipment regularly with evidence of regular maintenance, servicing and
serviced and inspected as required. The vessel is inspection sighted and evident. Ancillary lifesaving
fitted with 1 free-fall lifeboat, which was seen to be in good equipment such as lifejackets, immersion suits and EEBD's
overall condition externally and internally. The lifeboat etc. were found to be in good condition and ready for
engine was tested during the inspection and found to be in immediate use with man overboard smoke and light signals
good working order. The vessel's rescue boat was found to seen to be in date. Embarkation ladders were found to be in
be in a good overall condition and ready for immediate use. a good, well maintained condition and the pyrotechnics and
The vessel is equipped with 5 life rafts, which were found to line throwing apparatus were seen to be appropriately
be in good condition with Hydrostatic Release Units (HRUs) stored and within their expiry dates.
in date and correctly rigged. Davits and lowering
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 22
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
80
Safe working was deemed to be good overall with were seen to be up to date and satisfactory with enclosed
no unsafe practices observed during the space entry procedures followed and an effective Permit To
inspection and the vessel presenting a generally Work (PTW) system in place. Main and emergency exits were
safe working environment. Hazards were seen to be clearly clearly identified and unobstructed with all IMO signage
marked and external walkways adequately coated with non- seen to be satisfactory. Pilot ladders and boarding
slip paint and free of trip hazards. Adequate PPE was seen arrangements were seen to be in a good safe condition with
to be worn by crew at all times and portable gas detection clear pilot boarding instructions posted. Regular drills were
meters were provided and calibrated. Hazardous substances conducted on board with the last drill conducted on the 15-
were seen to be generally safely managed with appropriate Sept-22, which was a Boat and Fire drill.
Material Safety Data Sheets provided. Risk Assessments (RA)
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 23
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
POLLUTION CONTROL
60
Pollution control was deemed to be fair overall, in good condition as observed. The vessel's ballast record
primarily due to the open Condition of Authority. book was seen to be up to date and correctly filled in. The
Pollution control was generally found to be well vessel was not found to be Vessel General Permit (VGP)
implemented on board with the vessel free of pollution compliant, as the vessel had no valid oil-to-water interface
hazards. The vessel holds a Class-approved Inventory of controls such as Environmentally Acceptable Lubricants
Hazardous Materials, which is required for entry into EU (EALs) or an Airseal, with no documentation provided to
ports. The vessel's Oily Water Separator (OWS) was found to verify otherwise. The vessel's sewage treatment plant was
be fully operational and in good overall condition, with no found to be fully operational and in good overall condition,
obvious defects. The OWS was simulation tested during the with no obvious defects. Garbage segregation was found to
inspection and the 15ppm Oil Content Meter (OCM) was be good, with adequate, labelled containers and garbage
seen to be calibrated. The bilge overboard was seen to be seen to be well sorted and containers seen to be made of
sealed and locked against unauthorised opening and the approved non-combustible materials. The Garbage Record
oily water treatment system as a whole was seen to be free Book (GRB) was seen to be well-maintained and up-to-date,
from signs of tampering or unauthorised modification. The with the last entry on the 28-Sept-22. The Emission Control
SOPEP locker was found to be well stocked with SOPEP Area (ECA) change-over logbook was reviewed and found to
equipment in good condition and an accurate list of be satisfactory with the date of last entry on undefined. The
equipment posted nearby. The Oil Record Book (ORB) was vessel's incinerator was found to be fully operational and in
seen to be well-maintained and up-to-date, with the last good overall condition, with no obvious defects. The vessel
entry on the 26-Sept-22. An IMO approved Ballast Water complies with IMO 2020 regulations by employing the use of
Treatment System (BWTS) is fitted but was found not to be Very Low Sulphur Fuels Oils (VLSFO) with a sulphur content
fully operational as the system was yet to be commissioned of less than 0.5%.
for use as per relevant Condition of Authority, though was
NOTABLE ITEMS
Estimated
Description Cost
[USD]
Issue: The vessel does not use Environmentally Acceptable Lubricants (EALs) in the stern tube or has an
airseal and is therefore not VGP compliant in this regard.
$20000 -
Corrective Action: Various upgrades and modifications may be required if the vessel wishes to trade $50000
in the USA.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 24
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
Estimated
Description Cost
[USD]
Issue: The vessel has one Condition of Authority as follows: The BWMS has not been commissioned at
D-2 due date. Contingency measures according to IMO Circular BWM.2/Circ.62 will be used for
managing non-compliant ballast water discharges, until the installation and commissioning is
completed. Agreement on contingency measures must be obtained from the Coastal State of $1000 -
destination before exercised and arrival of coastal area. Due Date: 06 Dec 2022.
$5000
Corrective Action: The Condition should be thoroughly addressed to Class satisfaction by the due
date.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 25
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
ONBOARD MANAGEMENT
70
Onboard management was found to be fair to up to date with no critical overdue work orders. The Class-
good overall, primarily due to the issues noted approved system-based Planned Maintenance System (PMS)
with the auxiliary engine running hours. The was fully integrated with the SMS for ordering of spares and
computer-based Safety Management System (SMS) was general vessel management. The Port State Control (PSC)
deemed to be functioning and well implemented in general, history was found to be good with 7 deficiencies and 0
with Permits to Work (PTW), risk assessments and detentions in the 5 inspections conducted in the past three
procedures understood and followed. Onboard years. The vessel's flag is not targeted by any Memorandum
management was found to deal with accidents, near misses of Understanding (MoU) or the USCG. Security access
and deficiencies in an effective manner and regular safety controls were deemed to be satisfactory with the vessel
committee meetings were carried out on board. The vessel's conforming to International Ship and Port Security (ISPS)
MLC certificate was valid with records of hours of rest (ILO) standards. The Master and crew were prepared for the
correct and up to date and maximum work hours not inspection and provided good cooperation but with limited
regularly exceeded. The PMS system was found to be kept documents provided.
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 26
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
70
Vessel capabilities and cargo systems were corrosion, up to approximately 15% of the surface area,
deemed to be in a fair to good overall condition, mainly located to tops and edges. Hatch coamings were
primarily due to the level of corrosion noted on found to be free of structural defects and had only minor
the hatch covers. No cargo holds could be entered due to localised spot corrosion, up to approximately 5% of the
operational limitations and no photographs of previous surface area, mainly located to edges. Compression
hold entries were provided for review. Inspection reports bars/strips were not applicable due to . Hatch coaming drain
were provided for review. In the absence of photographic channels were free of corrosion, scaling and debris and the
support the condition of the holds is primarily based upon coaming non-return valves were clear and operational.
vessels of a similar age, type and size. The inspected cargo Cargo securing fittings such as container sockets, pad-eyes
hold structural members were reported to be free of damage and D-rings etc. were in good condition. Cargo securing
and had only minor scattered spot corrosion, up to equipment was plentiful with inspection records maintained
approximately 10% of the surface area, mainly located to and securing equipment in good condition as observed.
tanks tops and bulkheads, as well as to cell guides. Cell Stability calculations were seen to be carried out and the
guides were reported to be free of damage and vessel holds a Document of Compliance (DOC) for the
deformation. Cargo hold fittings such as ladders, handrail, carriage of Dangerous Goods (DG). The vessel is equipped to
ventilation ducts, light fixtures and pipe guards etc. were carry 536 Reefer containers whose temperatures were
reported to be generally free of damage and all cargo effectively monitored. Reefer sockets were seen in good
monitoring systems were fully operational. The cargo holds condition with switchboards free of low insulation or earth
were reported to be free of signs of water ingress both from faults. The vessel uses it's own power for all Reefer
internal and external sources. Mechanical ventilation containers, without the need for an additional auxiliary
systems were in good working order. The vessel is fitted power unit. The vessel was reported to have 2,546 TEU
with pontoon hatch covers. Hatch covers were found to be capacity, however limited documentation was provided to
free of structural defects but had moderate scattered spot verify a full breakdown.
NOTABLE ITEMS
Description Estimated
Cost [USD]
Issue: Cargo hatch covers were seen to have moderate scattered spot corrosion to the tops.
Corrective Action: Remedial cosmetic maintenance to be carried out as soon as practical. <$1000
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 27
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref: Issued On:
Example Vessel 0/0000 October 1 2022
Description Estimated
Cost [USD]
Issue: Scattered areas of corrosion noted to deck plating under cross deck lashing walkways.
Corrective Action: Remedial cosmetic maintenance to be carried out as soon as practical. <$1000
Report commissioned by and for the sole use of Example Individual of Example Organisation. PDF
generated for [email protected] at 00:00 (UTC) on 1st October 2022 Page: 28
REPORT SECURITY I.D. ca9e10ac-b575-3afd-841e-2ff7c46d33ea
Vessel: Ref:
Example Vessel 0/0000
OPERATIONAL DATA
Total Very and Ultra Low Sulphur Fuel Oil (VLSFO and
2,677.5 m3
ULSFO) capacity:
Total Marine Gas Oil (MGO) and Diesel Oil (DO) capacity: 147.6 m3
What fuel type does the vessel run on for the majority
Heavy Fuel Oil (HFO)
of the time?
Page: 1
Vessel: Ref:
Example Vessel 0/0000
Engines Table
Main
Main Engine Aux Engine Aux Engine Aux Engine Aux Engine
Engine
1 1 2 3 4
2
Hyundai
Designer Heavy N/A Daihatsu Daihatsu Daihatsu Daihatsu
Industries
Number of Cylinders 7 6 6 6 6
Stroke (mm) 2 4 4 4 4
Nox Tier 2 2 2 2 2
Page: 2
Vessel: Ref:
Example Vessel 0/0000
Loaded Eco 15 38
Loaded Service 16 42
Ballast Eco 14 34
Ballast Service 17 42
Bearings Yes
1 2 3 4 5 6 7 8 9 10 11 12
Class Surveys
Were all Class and Statutory certificates valid? Yes
Page: 3
Vessel: Ref:
Example Vessel 0/0000
What was the location of the last out-of-water docking? Example Location
Provide details of works done in last dry dock not provided for review
Has the vessel remained with the same Class since Yes
build?
Page: 4
Vessel: Ref:
Example Vessel 0/0000
The cost for the next out of water bottom survey or dry
docking based on a far eastern shipyard and includes all
800,000
survey and normal maintenance costs is approximately
estimated at:
Page: 5
Vessel: Ref:
Example Vessel 0/0000
HULL
Hull Condition
Page: 6
Vessel: Ref:
Example Vessel 0/0000
Page: 7
Vessel: Ref:
Example Vessel 0/0000
MOORING DECKS
Please provide further details Windlass band brakes had only minimal thicknesses remaining
Page: 8
Vessel: Ref:
Example Vessel 0/0000
What was the condition of the bosun's store structure? Structurally sound with no visible damage
What was the condition of the bosun's store coatings? Coatings fully intact with no corrosion
Was the condition of the bosun's store housekeeping? Fairly neat with some scattered equipment
Page: 9
Vessel: Ref:
Example Vessel 0/0000
Page: 10
Vessel: Ref:
Example Vessel 0/0000
Anode depletion: 5%
Page: 11
Vessel: Ref:
Example Vessel 0/0000
Page: 12
Vessel: Ref:
Example Vessel 0/0000
ACCOMODATION
Was the Hospital well equipped and ready for use? Yes
Page: 13
Vessel: Ref:
Example Vessel 0/0000
Galley Condition
Page: 14
Vessel: Ref:
Example Vessel 0/0000
Crew Welfare
Officers: 4 Months
Crew: 6 Months
What Public Recreation equipment did the crew have Free Weights Fixed weight machine
access to?
Treadmill Cycling Machine
Page: 15
Vessel: Ref:
Example Vessel 0/0000
Sofa Desk
Ample storage
Does the crew have access to a bonded store? Yes, well stocked
Page: 16
Vessel: Ref:
Example Vessel 0/0000
General Condition
Was all the bridge equipment reported to be fully Yes
operational?
Was the view from the bridge clear and unobstructed? Yes
Navigation Condition
Primary Secondary
Page: 17
Vessel: Ref:
Example Vessel 0/0000
Communication Condition
What GMDSS sea areas was the vessel licensed to A1 A2 A3 A4
cover?
Documentation Condition
Page: 18
Vessel: Ref:
Example Vessel 0/0000
Was the bridge log book up to date and correctly filled Yes
in?
External Condition
Was the Monkey Island found to be in good, well Yes
maintained condition?
Page: 19
Vessel: Ref:
Example Vessel 0/0000
General Condition
What equipment was seen running? Auxiliary Engines Purifiers
Were bilges and tank tops free of oil and water? Yes
Page: 20
Vessel: Ref:
Example Vessel 0/0000
Were the performance reports satisfactory? No seen to have been carried out at a low
load, 45%
Propulsion
What type of propulsion does the vessel have? Fixed Pitch Propeller (FPP)
What type of thruster systems does the vessel have? Bow Thruster
Power Generation
Page: 21
Vessel: Ref:
Example Vessel 0/0000
Were the performance reports satisfactory? No seen to have been carried out at a low
loads, 60%
Auxiliary Machinery
Does the vessel have an Auxiliary Boiler? Yes
Please provide further details circulation pump pressure gauge found to be damaged
Page: 22
Vessel: Ref:
Example Vessel 0/0000
gauges for LT fresh water cooling pump and fresh water heater unit
Why was 'No', 'Fair' or 'Poor' selected above?
were found to be damaged
Page: 23
Vessel: Ref:
Example Vessel 0/0000
Was the Engine Control and Alarm system free of any Yes
serious alarms?
Page: 24
Vessel: Ref:
Example Vessel 0/0000
LIFESAVING APPLIANCES
Page: 25
Vessel: Ref:
Example Vessel 0/0000
What Date is the next Davit wire due for change? 13-Jun-23
What was the date of the last abandon ship drill? 15-Sept-22
Page: 26
Vessel: Ref:
Example Vessel 0/0000
Page: 27
Vessel: Ref:
Example Vessel 0/0000
Are all IMO signs correctly placed, and compliant with Yes
IMO requirements?
Page: 28
Vessel: Ref:
Example Vessel 0/0000
POLLUTION CONTROL
General Condition
Was Pollution Control well implemented within the on Yes
board Safety Management System (SMS)?
Does the vessel have a Class approved Inventory of Yes The vessel holds a Class approved
Hazardous Materials (IHM)? Inventory of Hazardous Material (IHM)
Locked
Page: 29
Vessel: Ref:
Example Vessel 0/0000
Type: UV
Page: 30
Vessel: Ref:
Example Vessel 0/0000
Is the Vessel General Permit (VGP) compliant? No The vessel does not use Environmentally
Acceptable Lubricants (EALs) in the stern
tube or has an airseal and is therefore
not VGP compliant in this regard
Page: 31
Vessel: Ref:
Example Vessel 0/0000
How does the vessel comply with IMO 2,020 Use of Very Low Sulphur Fuel Oils (VLSFO), MGO, DO
regulations? etc.
EEXI
Does the vessel have an EEDI score assigned at build? No
What fuel type does the vessel run on for the majority
Heavy Fuel Oil (HFO)
of the time?
Page: 32
Vessel: Ref:
Example Vessel 0/0000
Main Engine(s)
Auxiliary Engines
Page: 33
Vessel: Ref:
Example Vessel 0/0000
ONBOARD MANAGEMENT
Page: 34
Vessel: Ref:
Example Vessel 0/0000
Was the PMS a fully integrated type system? (i.e. has Yes
integration with the SMS, spares ordering and is
accessible by shore side management)
Page: 35
Vessel: Ref:
Example Vessel 0/0000
Page: 36
Vessel: Ref:
Example Vessel 0/0000
Cargo hold Capacity in hold (TEU) Capacity on deck (TEU) Total (TEU)
Page: 37
Vessel: Ref:
Example Vessel 0/0000
Were the cell guides free from any significant damage Yes
or significant deformation?
Page: 38
Vessel: Ref:
Example Vessel 0/0000
Hatch Covers
Page: 39
Vessel: Ref:
Example Vessel 0/0000
Hatch Coamings
Were the hatch coamings found to be free from Yes
structural damage?
Cargo Securing
Page: 40
Vessel: Ref:
Example Vessel 0/0000
Did the vessel use a Class-approved computer based Yes CARGO ASSITANT / II
loading/stability software?
Reefer Containers
Is the vessel equipped to carry Reefer containers? Yes
Reefer Capacity
On deck 348
In Holds 188
Total 536
Was the vessel's own electrical supply sufficient for all Yes
reefer containers, without the use of an additional
Power Unit (package generator) ?
Page: 41
Vessel: Ref:
Example Vessel 0/0000
Is there an effective system for monitoring reefer Yes Automatic remote monitoring
container temperatures?
Page: 42
Vessel: Ref:
Example Vessel 0/0000
Page: 43