allocations_map
allocations_map
Units
1 Project Management 135 days 137 days 05/12/24 23/06/25
2 Initiating 5 days 5 days 05/12/24 11/12/24
3 Develop project charter 5 days 5 days 05/12/24 11/12/24
Project Manager 5 days 05/12/24 11/12/24 100%
4 Approved project charter 0 days 0 days 11/12/24 11/12/24
Project sponsor 0 days 11/12/24 11/12/24 100%
5 Planning - Project Plan 18 days 108 days 12/12/24 09/01/25
6 Develop Work Breakdown Structure 5 days 30 days 12/12/24 18/12/24
Project Manager 5 days 12/12/24 18/12/24 100%
PSO 2 5 days 12/12/24 18/12/24 100%
PSO 1 5 days 12/12/24 18/12/24 100%
SS Coordinator 5 days 12/12/24 18/12/24 100%
Technical coordinator 5 days 12/12/24 18/12/24 100%
Project sponsor 5 days 12/12/24 18/12/24 100%
7 Develop Gantt Chart 4 days 24 days 19/12/24 26/12/24
Project Manager 4 days 19/12/24 26/12/24 100%
PSO 2 4 days 19/12/24 26/12/24 100%
PSO 1 4 days 19/12/24 26/12/24 100%
SS Coordinator 4 days 19/12/24 26/12/24 100%
Technical coordinator 4 days 19/12/24 26/12/24 100%
Project sponsor 4 days 19/12/24 26/12/24 100%
8 Estimate Costs 3 days 18 days 26/12/24 31/12/24
Project Manager 3 days 26/12/24 31/12/24 100%
PSO 2 3 days 26/12/24 31/12/24 100%
PSO 1 3 days 26/12/24 31/12/24 100%
SS Coordinator 3 days 26/12/24 31/12/24 100%
Technical coordinator 3 days 26/12/24 31/12/24 100%
Project sponsor 3 days 26/12/24 31/12/24 100%
9 Identify possible risks 3 days 18 days 02/01/25 06/01/25
Project Manager 3 days 02/01/25 06/01/25 100%
PSO 2 3 days 02/01/25 06/01/25 100%
PSO 1 3 days 02/01/25 06/01/25 100%
SS Coordinator 3 days 02/01/25 06/01/25 100%
Technical coordinator 3 days 02/01/25 06/01/25 100%
Project sponsor 3 days 02/01/25 06/01/25 100%
10 Analyse and create a risk response plan 2 days 12 days 07/01/25 08/01/25
Project Manager 2 days 07/01/25 08/01/25 100%
PSO 2 2 days 07/01/25 08/01/25 100%
PSO 1 2 days 07/01/25 08/01/25 100%
SS Coordinator 2 days 07/01/25 08/01/25 100%
Technical coordinator 2 days 07/01/25 08/01/25 100%
Project sponsor 2 days 07/01/25 08/01/25 100%
11 Review the project plan 1 day 6 days 09/01/25 09/01/25
Project Manager 1 day 09/01/25 09/01/25 100%
PSO 2 1 day 09/01/25 09/01/25 100%
PSO 1 1 day 09/01/25 09/01/25 100%
SS Coordinator 1 day 09/01/25 09/01/25 100%
Technical coordinator 1 day 09/01/25 09/01/25 100%
Project sponsor 1 day 09/01/25 09/01/25 100%
12 Approved project plan 0 days 0 days 09/01/25 09/01/25
FITS CONTRACT 0 days 09/01/25 09/01/25 20%
13 Monitoring & Controlling 113 days 24 days 09/01/25 23/06/25
38 Closure 3 days 0 days 17/06/25 19/06/25
39 Verify the project outcomes 1 day 0 days 17/06/25 17/06/25
40 Lessons Learned 1 day 0 days 18/06/25 18/06/25
41 Archive Documents 1 day 0 days 19/06/25 19/06/25
42 Project Closed 0 days 0 days 19/06/25 19/06/25
43 Definition 13 days 29 days 10/01/25 28/01/25
44 Current system (As Is) 4 days 8 days 10/01/25 15/01/25
45 Project management processes 1 day 2 days 10/01/25 10/01/25
PSO 2 1 day 10/01/25 10/01/25 100%
PSO 1 1 day 10/01/25 10/01/25 100%
46 Project management methods 2 days 4 days 13/01/25 14/01/25
PSO 2 2 days 13/01/25 14/01/25 100%