tutorial-03-answers
tutorial-03-answers
Tutorial 03 (Answers)
Activity Optimistic Time Most Likely Time Pessimistic Time Expected Time
A 3 5 7 5.0
B 5 7 10 7.2
C 7 9 14 9.5
D 2 6 7 5.5
E 1 3 5 3.0
F 5 7 10 7.2
G 8 7 14 8.3
H 1 2 5 2.3
I 4 7 9 6.8
J 5 8 11 8.0
2. A project has been defined to contain the following list of activities along with their required
times for completion
Page 1
Notation TE TL
Activit ET calculate from 1st activity to calculate from last activity
y last activity to 1st activity
TE TL choose the largest choose the smallest
+ –
5 6 8 4
11 1 12+5=17 17-5=12 21 2
2 5
17-5=12 25-4=21
11+7=16 17+4=21
7 5
17 1
7 21+2=23 27-2=25
17+8=25 25-8=17
9 8 27-2=25 10 2
25 2 25+2=2 27 2
5 7
b. Calculate the earliest expected completion time.
27
1 2 4 7 9 10
d. What would happen if Activity 6 were revised to take six weeks instead of one week?
Page 2
3. List the five key activities done by a project manager during a project execution?
4. Explain the major differences between a network diagram and a Gantt chart.
5. Assume that you have a project with SEVEN activities labeled A-G. Derive the earliest
completion time (TE), latest completion time (TL) and the slack for each of the following
tasks (start at time = 0). Which tasks are on the critical path? Draw a network diagram for the
tasks shown. Highlight the critical path in the network diagram.
Notation
ET Slack
Activity
TE TL
Page 3
5 0 3 4 4 3
5+3=8 B 8+4=12 E
A
12-3=9 8 12 16-4=12 13 16
5 5
5+4=9 9+4=13 13+5=18
9-4=5 16-4=12 21-5=16
4 0 6 0 5 0
C 9+6=15 15+5=20
15-6=9 D G
9 9 21-5=16
15 15 21 21
16-1=15 15+1=16
16+5=21
21-5=16
1 0
F
16 16
Critical Path: A C D F G
6. What are the differences between problem identification and problem solving?
Problem identification is a way to find the gap or measurement between the current problem
and expectation.
Problem solving is the solution or alternative solution to reduce the gap or measurement.
7. Describe the activities performed by the project manager during project planning.
Page 4
8. Match the key terms to the following definition that best fits it.
Project Management
Critical Path
c) A systems analyst with a diverse set of skills: management, leadership, technical, conflict
management and customer relationship – who is responsible for initiating, planning,
executing and closing down a project.
Project Manager
Deliverable
e) The amount of time that an activity can be delayed without delaying the entire project.
Slack Time
f) The process of dividing the project into manageable tasks and logically ordering them to
ensure a smooth evolution between tasks.
g) A technique that uses optimistic, pessimistic and realistic time estimates to calculate the
expected completion time for a particular task.
Page 5
Project Workbook
i) A short document prepared for customer during project initiation that describes what the
project will deliver and outlines, generally at a high level, all work required to complete
the project.
Project Charter
j) A study that determines if the proposed information system makes sense for the
organization from an economic and operational standpoint.
Feasibility Study
Page 6