Consumers_-_Standards_101_Version_1.1
Consumers_-_Standards_101_Version_1.1
VERSION: 1.1
www.seanz.org.nz
© Sustainable Electricity Association New Zealand 2009 Standards 101 Version 1.0.odt
DISCLAIMER
This document is written act only as a guide to the relevant standards that should be
consulted in the design and installation of small scale renewable energy systems. Namely
grid-connected and stand-alone power systems utilizing photovoltaic, micro wind and micro
hydro technologies. Information is provided to help identify the relevant clauses in relevant
standards in New Zealand. This guide does not attempt to provide reference to all relevant
clauses and all considerations as this is the purpose of the standards in their totality. This
guide does not in any way replace the standards or relevant training in the design and
installation of these systems. From time to time the standards will be revised and references
made in this guide to relevant clauses in the standards may cease to point to the correct
clause. Additional clauses may be added that are relevant and clauses deleted.
All those designing, installing and working with the relevant systems should have access to
the associated standards and familiarise themselves with the requirements in detail.
SEANZ, the Authors and Reviewers shall not be liable in any way for damages resulting from
the use of this guide.
ACKNOWLEDGEMENTS
Author:
Shay Brazier - SEANZ Board & Southern Perspectives Limited
Contribution:
Glen Morris – SolarQuip, CEC
Brendan Winitana – SEANZ Chair & Eqinox Group
Jeroen Brand – SEANZ Board & Alphatron Pacific
Reviewers:
Shane Robinson – Powersmart NZ Ltd
Michael Lawley – Ecoinnovation
Hamish Littin – SEANZ Board & Elemental Energy
Geoffrey Webb – Standards Australia
Graeme Duder – Southern Alternative Power
Rod Krempansky- Able Solar
CONTENTS
1.0 INTRODUCTION............................................................................................................6
2.0 NZ REGULATIONS........................................................................................................6
3.0 THE RELEVANT STANDARDS.....................................................................................7
3.1 What are standards and how do they work..........................................................9
4.0 STAND-ALONE POWER SYSTEMS...........................................................................11
4.1 Relevant standards............................................................................................11
4.2 System sizing and configuration........................................................................12
4.3 Assessment of demand.....................................................................................12
4.4 Resource assessment.......................................................................................12
4.5 System configuration.........................................................................................13
4.6 Component sizing and selection........................................................................13
4.7 Sizing the renewable energy generator.............................................................14
4.8 Batteries.............................................................................................................15
4.9 Charge regulators & a.c. coupled inverters........................................................19
4.10 Battery inverters.................................................................................................20
4.11 Battery chargers.................................................................................................20
4.12 Generating sets (Genset)...................................................................................20
4.13 Metering and control..........................................................................................22
4.14 Electronic equipment location requirements......................................................22
4.15 Wiring, electrical protection and isolation...........................................................23
4.16 Connection of SPS to load.................................................................................25
4.17 Lighting protection..............................................................................................25
4.18 Documentation...................................................................................................25
4.19 Signs and labelling.............................................................................................25
4.20 Testing and commissioning...............................................................................25
4.21 Maintenance......................................................................................................26
4.22 Software.............................................................................................................26
5.0 GRID-CONNECT INVERTER SYSTEMS.....................................................................27
5.1 Relevant standards............................................................................................27
5.2 Inverter installation.............................................................................................28
5.3 Basic sizing/design guidelines ..........................................................................29
5.4 Connection to grid and metering........................................................................31
5.5 Required documentation....................................................................................31
5.6 Software packages............................................................................................31
6.0 PHOTOVOLTAIC ARRAYS.........................................................................................33
6.1 Relevant standards............................................................................................33
6.2 Sizing and energy yield estimations...................................................................33
6.3 Array wiring and protection................................................................................34
6.4 Lightning protection............................................................................................37
6.5 Signs and labelling.............................................................................................37
6.6 Documentation...................................................................................................37
6.7 Product and component standards....................................................................38
6.8 Structural...........................................................................................................38
6.9 Maintenance......................................................................................................39
6.10 Commissioning tests..........................................................................................39
7.0 WIND TURBINE GENERATORS.................................................................................40
7.1 Relevant standards summary............................................................................40
7.2 Siting and energy yield estimation.....................................................................40
7.3 Regulation and control.......................................................................................41
7.4 Wiring, protection and isolation..........................................................................41
7.5 Lightning............................................................................................................42
7.6 Structural...........................................................................................................42
7.7 Product standards..............................................................................................43
8.0 HYDRO.........................................................................................................................45
8.1 Siting..................................................................................................................45
8.2 Regulation and control.......................................................................................45
8.3 Estimating energy yield......................................................................................45
8.4 Structural...........................................................................................................46
8.5 Product standards..............................................................................................46
1.0 INTRODUCTION
This document has been written primarily for practitioners in the small scale renewable
energy industry who are installing stand-alone and grid-connected power systems utilizing
photovoltaics, small wind turbine generators and micro hydro.
This document is written to act as a guide to the relevant standards that should be consulted
in the design and installation of these systems. Information is provided to help identify the
relevant clauses in the standards. This document does not in any way replace the standards
and relevant training in the design and installation of these systems.
All electrical installations should comply with New Zealand regulation. AS/NZS 3000 – The
Wiring Rules is the key standard for electrical installations. All systems whether they are extra
low voltage (ELV) or low voltage (LV) should comply with AS/NZS 3000. This guide discusses
the specific standards relating to renewable energy systems.
Working knowledge of the Standards is considered necessary for good practice. All installers
should have access to the Standards and refer to these for clarification and requirements.
The document is structured to help you find the information that you require quickly and
easily. Where relevant requirements and recommendations are listed, the standard name and
clause number will be given in the margin as shown
below. Please note that as standards are revised the AS 4509 2.1
clause number listed in this document may change in
the standard.
Standard Clause
The document does not distinguish between requirements (SHALLS) and best
practice (SHOULDS) in the Standards as requirements are often conditional and best
covered by the standard itself.
The Standards should always be referred to when clarifying requirements.
2.0 NZ REGULATIONS
All electrical installations must comply with the New Zealand electrical regulations. The
regulation states:
“Works, electrical installations, fittings, electrical appliances, and
associated equipment must be designed, constructed, maintained,
installed, and used so that they are electrically safe”
One way of complying with the regulations is to ensure that the installation complies with AS/
NZS 3000 - The Australian and New Zealand Wiring Rules (The Wiring Rules). This includes
all standards that have a nominative reference from The Wiring Rules, see section 3.0. There
are restrictions of the work that you can carry out if you are not a registered electrical worker
“Any person, other than a homeowner, who carries out
prescribed electrical work, is required to be registered by
the Electrical Workers Registration Board (EWRB). All
AS 3008
IEC 61215
AS 3011.1 EN 61215
AS 3011.2
IEC 61730.2
EN 61730.1
AS/NZS 3010 EN 61730.2
AS 4509.1
AS 4086.2
AS 4509.2
AS 2676.1
AS 4509.3 AS 2676.2
AS 4777 AS 1940
AS 4777.1
AS 1319
AS 4777.2
AS 4777.3
Figure 1: Renewable energy standards map
Standards are living documents and are frequently revised and updated as experience is
gained with renewable energy systems.
Most of the standards referenced in this document were developed by the EL-042 committee,
which is joint between New Zealand and Australia. A list of current Member organisations can
be obtained from Standards Australia. SEANZ is a member of this committee and can
represent SEANZ members concerns at regular meetings. Anyone can make a submission on
a standard directly to Standards New Zealand.
Are standards law?
Standards are often referenced in regulations as a means of complying with the law. The
Wiring Rules (AS/NZS 3000) is a means of complying with the electrical regulations. Where
The Wiring Rules reference other standards as “nominative references” these standards also
become part of the requirement to meet the regulation.
Within each section of this standard and the above diagram (Figure 1) demonstrate the
linkages between standards.
How do I use standards?
Standards contain requirements and best practice advise. To “comply” with a standard you
must meet the requirements, but you may chose to comply with the best practice advise.
Where the standard says that you shall do some thing this is a requirement.
Where the standard says that you should do something this is best practice and is advisable
but optional.
Why should I use standards?
Where standards are referenced as a means of complying with law this is usually the simplest
way to ensure that your installation meets the requirements.
Should there be a dispute in the future or damage or injury as a result of your installation
designing and installing a system to comply with the standards will provide some protection. If
you are asked to defend why you did something a certain way it is easy to show that you have
completed your work to the requirements and best practice agreed by experts and the
industry as a whole.
Working to the standards gives your customers confidence in the installation and your work.
Where do I buy standards?
Standards can be purchased from:
SIA Global – www.sai-global.com
Standards New Zealand – www.standards.co.nz (NZS standards only)
It should be noted that the continued support and development of standards is made possible
through their sale. Standards are protected by copy right and should not be reproduced
without permission.
The document does not distinguish between requirements (SHALLS) and best
practice (SHOULDS) in the Standards as requirements are often conditional and best
covered by the standard itself.
The Standards should always be referred to when clarifying requirements.
AS 3008
IEC 61215
AS 3011.1 EN 61215
AS 3011.2
IEC 61730.2
EN 61730.1
AS/NZS 3010 EN 61730.2
AS 4509.1
AS 4086.2
AS 4509.2
AS 2676.1
AS 4509.3 AS 2676.2
AS 1940
AS 1319
Figure 2: Stand-alone power systems standards map
Note part 1 and 3 will be combined into a new AS/NZS 4509.1 later in the year which will
become a joint Australian, New Zealand standard.
AS 4509 references various other standards for particular parts of the system.
AS 4086.2: Secondary batteries for use with stand-alone power systems – Installation and
maintenance
AS/NZ 3010: Electrical installations – Generating Sets
Various other standards are references for particular aspects of the installations and these will
be noted at the relevant points in the document.
Wind resource is very site specific. The most robust means of determining specific site wind
conditions is to carry out measurements at the site for a period of 12 months or more.
However when considering small wind turbine generators the cost of this will often be
significant relative to the cost of the turbine making this uneconomic in many cases. Short
term site measurements can be taken and should be correlated against long-term data from
nearby sources.
If on site measurements are not taken then the w w w .bcse.org.au/default.asp?id=96
effective average wind speed and effect of local
topography and obstructions should be carefully considered and recorded for future
reference.
To assess the hydro resource potential for a particular site information about the volume of
flow in the stream and the static head available between the water intake and proposed
turbine location are required.
Estimates of static head can be made from topographical maps but on site measurements
should be used for any design work.
Hydro turbine manufacturers should be consulted on practical methods for on site
measurement of flow and head.
standard is that it provides an agreed and defendable way for a system designer to size
components should the system design be questioned in the future.
Appendix A of AS4509.2 provides a worked example of how to apply the
Appendix A
information in the standard.
An area not generally covered by standards is the reliability of equipment. Often it is a case of
you get what you pay for, however, consumers should be informed of the relative merits of
different equipment options, warranties and likely replacement periods.
Information on sizing and selection of system components, including design and installation
considerations are provided in the following sections.
The sizing of a PV array should consider the available solar radiation, required energy (as
discussed in the above section) and the chosen PV module characteristics. In particular the
following:
• Module tilt should be chosen to maximise the available energy,
3.4.3.3
typically in the month with the lowest available solar radiation.
3.4.3.3
The array should be oriented as close as possible to north
• Solar radiation used to calculate the energy yield should be
3.4.3.5
determined for the plane of the PV modules. Irradiation data is
3.2.2
also discussed in section 4.4.1
• Shading of the array
• Array temperature 3.4.3.7
• Power tolerance of the module (i.e. manufacturer's warranted 3.4.3.6
minimum)
• The type of regulator to be used. Available energy will vary 3.4.3.3
between a maximum power point tracking (MPPT) and switched
regulators.
AS 4509.2 provides guidance on the above and equations that will allow the array to be sized
correctly for both (MPPT) and switched regulators.
The wiring and safety aspects of photovoltaic arrays including product standards are covered
in section 6.
Provided seasonal variation for hydro resource is allowed for micro hydro
3.2.4
turbines will provide predictable and consistent power to a stand-alone
power system all year around. Manufacturer's recommendations should be consulted and a
turbine chosen to suit the site conditions and available flow and head of the hydro resource.
In summary sizing of hydro turbines should consider:
• Hydraulic losses in the pipe work and losses from fouling over time
• Cable losses between the turbine and batteries
• Seasonal resource variations
• The characteristics of the turbine at the available head and flow, including efficiency
Section 4.4.3 discusses hydro resource in more detail.
Section 8 discussion micro hydro turbines in more detail.
4.8 Batteries
Batteries are the heart of any stand-alone power system and attention should be given to
ensure that the batteries chosen are the most suitable.
AS/NZS 3000
AS 3011.1
AS 3011.2
AS 2676.1
AS 4509 AS 4086.2
AS 2676.2
AS 4509.1
AS 4509.2
AS 4509.3
Figure 3: Battery standards map
There are a number of standards that relate to the design, installation and maintenance of
batteries in stand-alone power systems.
The considerations relating to batteries are listed below with the standards that should be
referenced are shown on the right.
Battery box (a.k.a. dedicated Equipment room Dedicated area (fenced off in
enclosure) a larger area)
A revision to AS 4509.1 will provide more clarification about enclosures and battery
installations in general when published in late 2009.
Refer to section 4.15 for information on electrical wiring, protection and isolation.
Refer to section 4.19 for information on signage required for battery installations
Note that the standards listed are for the design and installation of batteries with a nominal
voltage of <115V d.c. Refer to AS 3011 for install of batteries with nominal voltages >115V
d.c.
4.8.3 Transportation
Batteries used for SPS typically fall into one of two UN dangerous goods categories:
However some batteries such as lithium may fall into a different category
The volume of batteries that you are carrying and the w w w .nzta.govt.nz
purpose for carrying those batteries will generally
determine whether you need a licence to carry the batteries, and your responsibilities. If you
carry batteries for hire or reward a dangerous goods licence will be required. Table 1 provides
a summary of requirements for each category. For more information you should consult the
New Zealand Transport Agency.
Regardless of the battery type that you are carrying you should give consideration to:
• Preventing short circuit including keeping the batteries dry
• Packaging
• Securing the load and preventing the batteries tipping over
• Damage and puncture of the batteries
• Appropriate signage
Generators are usually used as a backup power source and should be sized to suit the surge
and sustained demand which will be determined by the load assessment (section 4.3) and
system configuration. Demand requirements will depend on whether the system is a:
• Series system 3.4.11.2 to
3.4.11.4
• Switched system
• Parallel system
The available power of the generator will be affected by the location (e.g. 3.4.11.5
altitude effects) and operating conditions (e.g. temperature) and should be
power derated to suit.
Nominal generator run time can be calculated and will be useful in 3.4.11.6
determining fuel costs.
4.15.2 Isolation
Some equipment may not be able to be used with AS/NZS 5033 5.2
certain earthing arrangements. The manufacturers
requirements should be consulted.
PV arrays see section 6.3.4
4.18 Documentation
Guidance on the documentation that should be AS 4509.3 12.0
provided to the owner of a stand-alone power system
is given in AS 4509.3
Note: Further clarification will be provided in a revision of AS 4509.1 to be published in later
2009.
4.21 Maintenance
The maintenance of an SPS is important to ensure reliable and safe operation.
The maintenance requirements for an SPS are given AS 4509.3 11.0
in AS 4509.3. The working area and equipment
including battery banks should be made safe before work commences.
Maintenance of PV arrays AS/NZS 5033 Appendix H
4.22 Software
There are a number of ways to design the appropriately sized renewable energy system.
Software such as PVsol, PVsyst and Homer provide time step calculations that will allow
calculation of system size for given load and renewable energy resource to a high level of
accuracy. However they do not provide provision to directly assess compliance with the
standards.
The Clean Energy Council (CEC) in Australia provides two spreadsheets that calculate
system sizes based on the requirements of the standards. These spreadsheets are made
available to CEC accredited installers only.
Using the guidelines in Appendix B of AS 4509.2 it is possible to create a spreadsheet that
will complete these calculations.
Other simulation packages are available see Appendix B for more information.
The document does not distinguish between requirements (SHALLS) and best
practice (SHOULDS) in the Standards as requirements are often conditional and best
covered by the standard itself.
The Standards should always be referred to when clarifying requirements.
AS 3008
IEC 61215
AS 3011.1 EN 61215
AS 3011.2
IEC 61730.2
EN 61730.1
AS/NZS 3010 EN 61730.2
AS 4509.1
AS 4086.2
AS 4509.2
AS 2676.1
AS 4509.3 AS 2676.2
AS 4777 AS 1940
AS 4777.1
AS 1319
AS 4777.2
AS 4777.3
Figure 9: Grid-connected inverter systems standards map (note: grey objects and links
only apply to systems with battery backup)
5.2.3 Isolation
3. A fixed budget.
5.3.1 Solar PV
There are no standards for calculating grid-connected solar energy yield. Considerations
should be given to:
• Solar radiation in plane with the collector field, including localised weather effects
such as mist. Section 4.4.1 discusses solar radiation data and some possible sources
of data are provided in Appendix A.
• PV module characteristics including, rated power, manufactured power tolerance
• Cell operating temperature and cell temperature coefficients
• Module soiling
• Inverter characteristics including, efficiency at MPP operating voltage
• Effects of array shading on a daily and seasonal basis
• Wiring losses in the PV array and inverter to point of connection cabling
Typically energy yield for a grid-connected photovoltaic array will be calculated on an annual
basis. It may be necessary to compare daily generation profiles with daily load profiles if
import and export tariffs for electricity vary in order to calculate the expected financial gains
from the system. Grid-connected arrays differ from SPS arrays in that there is effectively an
unlimited load and all energy generated can be utilised or exported (SPS yield is limited to the
amount of energy generated that can be used directly or stored).
Much of the information provided in AS 4509.2 with AS 4509.2 3.4.3
regards to the estimation of energy yield for SPS
arrays connected to maximum power point tracking charge controllers is applicable and can
be used as a guide.
The voltage and power of the PV array should match the inverter. Many inverter suppliers
provide tools to assist in correct sizing. Allowance should be made for the effect of
temperature on the PV module output.
PV array sizing and energy yield estimation guidelines w w w .bcse.org.au/default.asp?id=96
are provided by the Clean Energy Council (CEC). The
guide can be downloaded from the BCSE website.
A number of software packages are available and are discussed in section 5.6.
The array voltage should not exceed maximum AS/NZS 5033 3.2
module voltage.
See section 6.0 for further information on solar PV arrays.
5.3.2 Wind
There are no standards for the calculation of grid-connected small wind turbine generator
yield. Allowance should be made for the local wind resource as discussed in section 4.4.2
including the effects of obstructions and local topology.
Software tools area available that will allow estimations of yield against a certain wind
distribution given the power curve of a turbine.
Care should be taken to ensure that the power and voltage input limits of the inverter are not
exceeded, especially under no load conditions. For example when the inverter is
disconnected from the grid due to a grid failure. Overvoltage input into the inverter can cause
damage and may void the warranty.
A dump load may be required to dissipate excess energy in the case of disconnection from
the grid. Some wind turbine generators may include this functionality in the turbine control
system.
See section 7.3 for information on regulation and control of wind turbine generators.
5.3.3 Hydro
There are no standards for the calculation of grid-connected micro hydro turbine energy yield.
Allowance should be made for the local hydro resource as discussed in section 4.4.3.
Care should be taken to ensure that the power and voltage input limits of the inverter are not
exceeded, especially under no load conditions. For example when the inverter is
disconnected from the grid due to a grid failure. Overvoltage input into the inverter can cause
damage and may void the warranty.
A dump load may be required to dissipate excess energy in the case of disconnection from
the grid. Some hydro turbine generators may include this functionality in the turbine control
system.
See section 8.2 for information on regulation and control of hydro turbines
A contract will be required between the owner of the grid-connected system and the electricity
retailer for the purchase of any electricity that is exported to the grid.
A meter (or meters) will be required that can measure the energy flow both to and from the
property as required by New Zealand regulations. These requirements should be discussed
with the electricity retailer. More
information is also provided on w w w .seanz.org.nz/documents/doc_dow nload/23-dg-metering-guide
the SEANZ website.
Most inverter manufacturers will supply proprietary software for the electrical conformance
checks on inverters with a specified PV array. It is important to note that the yields provided
within these simulations are typically indicative only and should not be relied upon as a
specific yield.
Other simulation packages are available see Appendix B for more information.
The document does not distinguish between requirements (SHALLS) and best
practice (SHOULDS) in the Standards as requirements are often conditional and best
covered by the standard itself.
The Standards should always be referred to when clarifying requirements.
AS/NZS 1170.3
AS/NZS 1170.2
IEC 61730.1
IEC 61730.2
EN 61730.1
EN 61730.2
IEC 61215
AS/NZS 3000 AS/NZS 5033
IEC 61646
AS/NZS 1768
AS/NZS 3008
AS 1319
Figure 10: Photovoltaic (PV) array standards map
6.2.1 Grid-connected
The sizing of grid-connected PV systems and calculation of annual energy yield are
discussed in section 5.3.1
The yield of a PV array in a SPS is not typically calculated for an annual basis. The focus
when designing a SPS system is to size an array to meet the desired or optimal percentage of
daily energy requirements for the worst time of year, i.e. when the ratio between energy
generation and energy demand is the lowest.
Further discussion of the sizing of SPS PV arrays is provided in section 4.7.1.
Array
String
cable
Sub array
cable
String
Cell Module
The device that converts or regulates the power produced from a PV array (generically known
as a “power conditioning unit” in the standards) should be sized to suit the voltage and power
output of the array. This is discussed in more detail in previous sections:
• Standalone power system – charge regulator for d.c. coupled systems or inverter for
a.c. coupled systems. Section 4.9
• Grid-connected inverter systems – grid-connect solar inverter. Section 5.3.1
6.3.2 Protection
6.3.2.1 Diodes
Diodes are commonly installed with-in PV modules to AS/NZS 5033 2.2
reduce the effects of cell shading and to protect cells
from damage caused by reverse currents. Generally these diodes are installed by the PV
module manufacturer but if they are installed by a system installer then the guidance in the
standard should be followed.
Diodes can also be used as a blocking device to prevent reverse current from a battery
(usually integrated into the charge controller) or from other PV strings. They are not a
substitute for string fault current protection covered in section 6.3.2.2.
If using blocking diodes installers should consider:
• The appropriate rating and other AS/NZS 5033 2.3
considerations of the standard
• The energy losses that will result from a diode
• The energy yield loss as a result of a failed diode
6.3.3 Disconnection
A device to disconnect the PV array from the “power conditioning unit”, i.e. the inverter or
charge controller will be required in most situations. Consideration should be given to:
• The location of the device AS/NZS 5033 Table 2.4
• The type and rating of the device Table 2.3
AS/NZS 5033
4.0
• It is necessary to disconnect some charge controllers from the PV array before the
battery is disconnected from the controller to prevent damage to the controller. This
should be considered in the design and installation of the system.
5.0
6.3.4 Earthing
2.6
AS/NZS 5033
Appendix C,
The complete system should be considered when
determining both protective earthing and equipotential D&E
bonding requirements of PV arrays.
• Voltage drop
• Required physical properties of cables for insulation and environment conditions
Useful summaries and case studies are provided in Table 3.1
AS/NZS 5033
the standard. Appendix J
Earth fault protection requirements should be AS/NZS 5033 Table 2.5
considered when selecting cable for PV arrays. A
summary of requirements is given in the standard.
Consideration should be given to the component and product requirements, see section 6.7.
See section 6.5 for labelling requirements.
6.6 Documentation
See the relevant sections in SPS and grid-connected inverter systems.
Stand-alone power systems – section 4.18
Grid-connected inverter systems – section 5.5
Figure 12: Wind rated solar PV array frames (Elemental Energy, Powersmart)
Often the most practical and cost effective solution is to use a pre-engineered framing system
that has been design to withstand the expected snow and wind loads.
Roof penetrations and attachment of the frame to a building or another structure should be
considered.
• Roof penetrations should be waterproof and
NZBC G12/AS2
durable. Guidance on some acceptable roof
penetrations are provided in the solar water heating acceptable solution.
• The fixing of an array frame to a building
NZBC G12/AS2
rafter, purlin or similar can impose loads on
the structure that it would not otherwise see. Some guidance on this is provided in the
solar water heating acceptable solution. If in doubt a structural engineer should be
consulted.
• Areas of high pressure on a roof (e.g. near the ridge and edges)
The document does not distinguish between requirements (SHALLS) and best
practice (SHOULDS) in the Standards as requirements are often conditional and best
covered by the standard itself.
The Standards should always be referred to when clarifying requirements.
AS 3008
AS 4509.1
AS 1319
AS 4509.2
AWEA 9.1
AS 4509.3
A standard developed by the American wind energy association for micro wind turbine
generators has been adopted in America and the United Kingdom and may be useful as a
reference for those involved in micro wind turbine generators in New Zealand.
Sizing and energy yield estimation for wind turbine generators is discussed in the relevant
sections of SPS and grid-connected inverter systems.
Local council district plans will have requirements on
maximum height limits and noise levels. The turbine's AS 4509.2 4.7
noise characteristics as provided by the manufacturer can be compared to the council's noise
limits. Comparison should be made at the boundary of the property and consideration given to
the ambient noise levels at the site for various wind speeds.
Further information on resource consent considerations EECA Council Guidance Document..
is provided in council guidance document produced by
EECA.
7.2.1 Grid-connected
The sizing of grid-connected wind turbine generators systems and calculation of annual
energy yield is discussed in section 5.3.2
The yield of a wind turbine generator in a SPS is not typically calculated for an annual basis.
The focus when designing a SPS system is to size an wind turbine generator to meet the
desired or optimal percentage of daily energy requirements for the worst time of year, i.e.
when the ratio between energy generation and energy demand is the lowest.
Further discussion of the sizing of SPS wind turbine generators is provided in section 4.7.2.
7.4.1 Wiring
For general cable sizing and selection requirements refers to AS/NZS 3008.1.2 or AS/NZS
3000 clause C4.1-
Generally for wiring design and installation should consider:
• The minimisation of line to line, line to earth faults
• All wiring should be protected from AS 4509.3 2.2
mechanical damage and other “external AS/NZS 3000 Including:
influences” such as sunlight and heat. This is 3.3, 3.9 &
covered in detail in The New Zealand Wiring 3.10
Rules. 7.3.5.1
7.4.2 Protection
The wind turbine generator should be capable of being isolated from the system.
See section 5.2.3for isolation requirements for grid-connect inverter systems.
See section 4.15.2 for isolation requirements for SPS.
7.6 Structural
Wind turbine generators need to be capable of AS/NZS 1170.2 General
withstanding the wind forces that are applied to them AS 4509.2 4.3.3
over their installed life and the environmental conditions where they are installed. Expected
maximum wind speeds can be determined from the wind code.
The worst case wind speed should be determined and the ability of the wind turbine generator
and tower, including its foundation to withstand this wind speed checked.
Tower or Tower, guy wires and guy wire 1. Designed by structural engineer
mast Guyed attachment to ground capable of
2. Pre engineered design supplied
withstanding load applied from
by tower or turbine manufacturer/
turbine and wind at maximum site
supplier
wind speed
Often the most practical and cost effective solution is to use a pre-engineered tower and
foundation that has been design to withstand the expected wind loads.
Towers and foundation design should also be resistant to fatigue stress and non-resonant
under normal operating conditions.
Cp
Maximum power = ×× A× 3
2
Where :
Note: Small wind turbine generators are likely to have a Cp = 0.4 or less
8.0 HYDRO
Micro hydro turbines can be a very effective means of generating power when a suitable
water resource is available. When installed correctly they can operate reliability and have little
or no effect on the environment.
The document does not distinguish between requirements (SHALLS) and best
practice (SHOULDS) in the Standards as requirements are often conditional and best
covered by the standard itself.
The Standards should always be referred to when clarifying requirements.
• The characteristics of the turbine at the available head and flow, including efficiency
More information is provided on hydro resource in section 4.4.3
Information on sizing hydro generators for SPS is provided in section 4.7.3
Information on estimating yield of hydro generators in grid-connect systems is provided in
section 4.7.3
8.4 Structural
The installation of all equipment should be designed to be capable of withstanding the likely
operational loads, flooding and other environmental conditions.
The water intake should be designed to prevent fish, invertebrates and other objects from
entering the penstock. Where there are fish in the stream the intake structure should not
prevent free movement up or down the stream.
8.6 Software
See Appendix B
Homer analysis.nrel.gov/homer/
HOMER is a computer model that simplifies the task of evaluating design options for both
off-grid and grid-connected power systems for remote, stand-alone, and distributed
generation (DG) applications. Homer provides tools to evaluate the financial performance
of various options as well as energy yield.
PV watts www.nrel.gov/rredc/pvwatts/
NREL's PVWattsTM calculator determines the energy production and cost savings of grid-
connected photovoltaic (PV) energy systems throughout the world.
PVsyst www.pvsyst.com/
PVSYST 4.35 is a PC software package for the study, sizing, simulation and data analysis
of complete PV systems.
It is suitable for grid-connected, stand-alone, pumping and DC-grid (public transport)
systems, and offers an extensive meteorological and PV-components database.
PVsol www.valentin.de/
A Dynamic Simulation Programme for the Design and Calculation of Stand-Alone and
Grid-connected Photovoltaic Systems