2024-7 (3)
2024-7 (3)
10-01
Cost Management
§ Cost is a resource expended to achieve a specific objective,
in our case, a project.
§ Cost management in projects is the process by which
companies control and plan the costs of implementing
projects.
§ Before a project is started, the anticipated costs should be
identified.
§ These costs should then be evaluated and approved before
any procurement.
§ During the implementation of a project, all costs should be
recorded, tracked and monitored to control the costs and
kept in line with initial expectations.
Copyright © 2016 Pearson Education, Ltd 9-8
Project Costs
§ Direct costs: Direct material and labor costs used solely for
a project
§ Indirect costs: Any material and labor costs that are not
used in a single project
§ Fixed costs: Remain constant regardless of changes in the
level of project activities
§ Variable costs: Vary in direct proportion to changes in the
level of project activities
§ Overhead costs: Primarily those indirect costs associated
with project implementation
§ General and administrative costs: Costs primarily
associated with general management and administration of
the project Copyright © 2016 Pearson Education, Ltd 9-9
Project Costs
§ Tangible costs: Quantifiable costs related to an identifiable
resource or asset
§ Intangible costs: Unquantifiable costs relating to an
identifiable source
§ Sunk costs: Incurred costs that cannot be changed by any
decision and that cannot be recovered
§ Opportunity costs: Potential benefit given up when an
alternative activity is selected over another activity
Dozer Excavator
(Construction) (Construction)
Example—Given the WBS
Level 0
Modular House
(1.0)
Site Modules
Level 1
(1.1) (1.2)
Level 4
Structure Appearance
(1.1.1.1.1) (1.1.1.1.1)
Remove trees Clean found. terrain Level found. terrain Dig trench Build structure
Level 5 (1.1.1.1.1.2) (1.1.1.1.1.3) (1.1.1.1.1.4)
(1.1.1.1.1.1) (1.1.1.1.1.5)
2 1 3
Clean Foundation
Terrain
0 2 2 3 1 4 4 1 5 5 7 12
Remove Site Trees Dig Trench Build Structure
0 0 2 4 0 5 5 0 12
2 2 4
Level Foundation
Terrain
2 0 4
Cost Variances
Actual Cost of Work Performed (AC) = 40 = 8+11+8+13
Cost Performance Index = .75 = 30/40 = EV/AC
Estimated Cost to Completion = 50.7 = (1/.75)x38
Ø 50/50 Rule
vLevel of detail
vProcess evaluation