Technical Specs
Technical Specs
1.1.4 Testing:
The Contractor is to carry out and attend all tests were nominated in this specification. As a minimum,
the Contractor will carry out the following tests: concrete, cement block, plumbing, steel sections, and
drainage.
The Contractor will supply all necessary appliances and labour for testing of the complete water sup-
ply system at such times and as directed by the Engineer. Such testing shall as a minimum require the
pressurizing of the complete water supply system to a pressure of not less than 4.5bar. The pipe work
B. Memoranda Preparation:
Prepare similar memoranda for the employer and separate contractors if their work requires coor-
dination with each other. This ensures that all relevant parties are informed of the necessary coor-
dination procedures.
C. Administrative Procedures:
Coordinate the scheduling and timing of required administrative procedures with other construc-
tion activities to avoid conflicts and ensure orderly progress of the work. Some of the administra-
tive activities that need to be coordinated include:
1.3 PRELIMINARIES
1.3.1 Pre-Construction work:
1.3.1.1 General:
The Engineer and Contractor will conduct a joint condition-in survey using digital photographs to
record and document the site's condition during handover to the Contractor. This survey will establish
the initial state of the site, which the Contractor must be responsible for returning in the same condi-
tion upon completion of the works.
The Contractor will carry out a detailed site setting out for the works.
A pre‐Construction meeting will be held between the Engineer and the Contractor to review the fol -
lowing information:
Condition-in Survey
Site Survey
Work Method Statement
Work Program
Schedule of Materials and Installed Equipment.
The Contractor must mobilize on the project site within 7 calendar days of the date of issue of the No-
tice to commence.
1.3.1.2 Site restrictions
Site security limitations: It is imperative to comply with any restrictions imposed on the site area, ac-
cess, or working times as advised by the Engineer.
Access: The ability to enter and move within the site, as well as utilizing the site for temporary works
and constructional plant, including working and storage areas, placement of offices, workshops,
sheds, roads, and parking, is strictly limited to the areas depicted on the drawings or as agreed upon
with the Engineer.
1.3.1.3 Occupied areas of site or buildings
For the parts of the site designated as occupied areas in the occupied areas schedule:
Allow occupants to continue using the area for the required period.
Technical Specifications- Civil, Architectural, and Electrical Works
17
for Rehabilitation of Admin Building in Fishery Harbor
1. Make available safe access for occupants.
2. Arrange work to minimize nuisance to occupants and ensure their safety.
3. Protect occupants against weather, dust, dirt, water or other nuisance, by such means
as temporary screens.
1.3.1.4 MISCELLANEOUS Compliance with the law
The Contractor is responsible for compliance with all requirements of authorities. The owner,
before entering into the contract, has given the notices, paid the fees, and obtained the per-
mits, approvals and other authorizations stated in the Prior applications and approvals
3. Demolitions
3.1 GENERAL
Section Includes: Demolition and removal of selected portions of building or structure.
3.2 References:
1. Code of Federal Regulations (CFR)
29 CFR Part 19 10 Occupational Safety and Health Standards
29 CFR Part 1926 Safety and Health Regulations for Construction
2. Uniform Federal Accessibility Standards (UFAS) FED-STD-795.
3.3 Interpretation
Demolished materials classes
A. Remove: Detach items from existing construction and dispose of them off-site
unless indicated to be salvaged or reinstalled.
B. Remove and Salvage: Detach items from existing construction, in a manner to
prevent damage, and store.
C. Remove and Reinstall: Detach items from existing construction, in a manner to
prevent damage, prepare for reuse, and reinstall where indicated.
D. Existing to Remain: Leave existing items that are not to be removed and that are not oth-
erwise indicated to be salvaged or reinstalled.
E. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle
methods and equipment to prevent damage to the item and surfaces; disposing of items
unless indicated to be salvaged or reinstalled.
3.4 Submittals:
1. Engineering Survey: Submit engineering survey of condition of building.
2. Proposed Protection Measures: Submit report, including Drawings, that indicates the mea-
sures proposed for protecting individuals and property for dust control and for noise control.
Indicate proposed locations and construction of barriers.
3. Schedule of Selective Demolition Activities: Indicate the following:
a. Detailed sequence of selective demolition and removal work, with starting and ending
dates for each activity. Ensure Owner's on-site operations are uninterrupted.
b. Interruption of utility services. Indicate how long utility services will be interrupted.
c. Coordination for shutoff, capping, and continuation of utility services.
2. Fair faced concrete finish equivalent to class 1 quality and type finish, with the fol-
lowing additional requirements:
a. Produce a smooth, even finish with an impervious sheet material (e.g. high
quality resin film faced plywood) arranged in an accepted regular pattern as
a feature of the surface. This shall coincide with the architectural features as
indicated on the Design Drawings. Do not replace parts of the formwork
panels where this may cause a change in color in the concrete.
b. Abrupt irregularities shall be not greater than 1mm. Gradual irregularities,
expressed as maximum permissible deviation from a 1m straightedge, shall
be not greater than 3mm.
4.7.2 Preparation
A. It is the whole responsibility of the contractor to assure the following:
6.3 Submittals:
A. Shop Drawings: Submit detail fabrication and placement drawings for all formwork and
reinforcing steel which are correlated with forming and concrete placement techniques
and requirements.
1. Reinforcing shall be detailed on shop drawings reviewed and approved by The
Engineer.
2. The drawings shall be in such detail as to assure that difficulties in execution of
the work in the field are minimized.
3. The drawings shall consist of sections, plans and details clearly showing loca-
tions sizes and spacing of all reinforcing steel, supporting bars and accessories.
Include on the shop drawings, schedules and diagrams to indicate bends, sizes
and lengths of all reinforcing steel bars.
6.6 Executions
6.6.1 Mixing Concrete
A. Ready Mixed Concrete
1. Comply with ASTM C94. Batched mix only shall be used on the site and any account
mixing at site is not permitted.
2. Mixing additional water for consistency during transit or any time of pouring con-
crete is not permitted.
3. Discharge the concrete completely at the Site within one hour after the introduction
of the water to the aggregates. In hot weather reduce this time limit so that no stiff-
ening of the concrete shall occur until after it has been placed.
BS 5628-2:2005 Code of practice for the use of masonry. Structural use of reinforced and pre-
stressed masonry.
BS 5628-3:2005 Code of practice for the use of masonry. Materials and components,
design and workmanship
BS 8000-3:2001 Workmanship on building sites. Code of practice for masonry
BS 12 Portland Cement
BS 3416 Black bitumen coating solutions for cold application.
BS 3148 Methods of tests for water for making concrete.
BS 1199 and 1200 Specifications for Building Sands
ASTM C 144 Specification for aggregate for masonry
ASTM C 476 Specification for mortal for unit masonry
ASTM C 97 Test methods for absorption and bulk specific gravity of natural building stone.
ASTM C 99 Test methods for modules of rupture of natural building stone.
ASTM C 114-88 Test methods for chemical analysis of hydraulic cement.
ASTM C 119 Definitions of terms relating to natural building stone
ASTM C 170 - 09 Standard Test Method for Compressive Strength of Dimension Stone
ASTM C 207-91 Specification for hydrated line for masonry purposes.
ASTM C 241 Test method for abrasion resistance of stone subjected to foot traffic.
ASTM C 503-89 Specification for marble dimension stone
ASTM C 880-92 Test method for flexural strength of dimension stone
ASTM C1201-91 Test method for structural performance of exterior dimension stone cladding
system by uniform static pressure difference.
ASTM C 150 Portland Cement
7.3 Submittals:
E. Samples:
4. Submit two (2) sets of each type of stone, full size units as selected by the Engineer
to the project site, in sufficient number to indicate the full range of color, texture and
each type of finish. One of each of the duplicate samples approved by the Engineer
8. Blockworks:
8.1 General
Give sufficient notice so that inspection may be made of the following:
- Forms for blocks prior to casting blocks.
- Completed blocks prior to use.
- Damp-proof courses, in position. - Built-in items, in position.
Cement Blocks shall be of precast concrete and may be manufactured on or off the Site under the su-
pervision of the Engineer. Blocks from an approved manufacturer or block factories in Yemen/ Aden
may be accepted at the discretion of the Engineer.
The casting of all Automatic blocks shall be made in approved molds and to the required dimensions,
and thoroughly rammed and consolidated by mechanical tamping and vibration. All blocks shall be
sound, square-edged, true to shape and size, and free from cracks and other defects.
8.2 References:
BS 12 Portland Cement
BS 882 Specification for aggregate.
BS 3148 Methods of tests for water for making concrete.
BS 6073 Part 1 and part 2. Precast concrete masonry units
BS 1199 and 1200 Specifications for Building Sands
BS 5628-1:2005 Code of practice for the use of masonry. Structural use of unreinforced masonry.
BS 5628-2:2005 Code of practice for the use of masonry. Structural use of reinforced and pre-
stressed masonry.
BS 5628-3:2005 Code of practice for the use of masonry. Materials and components,
design and workmanship
BS 8000-3:2001 Workmanship on building sites. Code of practice for masonry
BS 1449: Part 2 Specification for stainless and heat-resisting steel plate
BS 729 Hot-Dip Galvanized Coatings on Iron & Steel Articles
8.3 Submittals
A. Samples
1. Submit to the Engineer, in accordance with the requirements of the Contract
document sample of each unit masonry hereinafter listed. Samples will be re-
viewed for color and texture only. Compliance with all other requirements is
the exclusive responsibility of the Contractor. Samples to be submitted are as
follows:
For each the two types of blocks.
2. Submit certified copies of the reports of all tests specified herein. Test reports
shall be accompanied by notarized certificates from the manufacturer certifying
that the tested material is of the same type, quality, manufacture and makes as
that proposed to be supplied.
B. Shop Drawing.
1. Submit shop drawings indicating details of reinforcement, anchors,
inserts, joints, connections to adjoining work or materials. Also include eleva-
tions
indicating setting out and placement of all joints, openings, cut-outs, etc.
H. Mockup
1.Prior to the installation of unit cement block, and preceding pre-installation
conference, provide a sample wall mock-up for each type of unit cement block
work.
2.Provide each sample wall panel using materials, together with bond and joint
tooling, shown or specified for final work.
3.Build each sample wall panel mock-up at the site, as directed, of full thickness
and approximately 1-meter-high x 1.5 meter long, unless otherwise shown,
indicating the proposed texture and workmanship to be expected in the
completed work.
4.The approved mock-up shall constitute the quality of work to be expected
throughout the entire project and shall remain in place for visual inspection un-
til no longer needed as directed by the Engineer. The removal and disposition of
the mock-ups shall be done by the Contractor at his expense without additional
cost .
5.Obtain Engineer’s acceptance of visual qualities of each sample panel before pro-
cessing with the final work.
6.Retain each sample panel mock-up during construction period as a standard for
judging completed masonry work. Do not alter, move or destroy mock-up until
work is completed.
7.Ensure coordination between cement block work and concrete work such that all
inserts and flashing reglets required for the proper installation of masonry work
are correctly pre-installed.
8.7 Executions
8.7.1 Examination
J. Examine Surfaces: Inspect existing surfaces and ensure that they are satisfactory
for
work to proceed as specified. Report unsatisfactory conditions to the Engineer
and do not proceed until rectified to satisfaction of the Engineer.
K. Verify all measurements and dimensions coordinate the installation of inserts for
this work and coordinate and schedule this work with the work of other trades.
Give particular attention to the location and size of cutouts required to accom-
modate mechanical, electrical, and other work or adjoining construction, in ac-
cordance with the reviewed shop drawings for such trade.
8.7.2 Preparation
Removal is not to damage steel and is to be effected using tools and methods
approved by the Engineer. Saws must be fitted with depth gauges to prevent
damage to steel.
9. Plastering
9.1 General:
Portland Cement-Based Plaster.
9.2 References:
9.3 Submittals
A. Provide product data on plaster materials, characteristics and limitation of product
specified.
B. Submit manufacturer's installation instructions.
C. The contractor should make an approved sample before starting the work.
D. Sample Panel:
1. Construct 1000 mm wide x 1000 mm high sample panel with finished surface, us-
ing
materials and methods specified herein, for review by the Engineer.
2. Accepted surface finish of sample establishes minimum standard of quality and
workmanship of cement plaster work on job.
9.4 Quality Assurance
A. Re-rolled framing and framing members containing factory welds will not be allowed.
B. Perform work in accordance with GA-600 and ASTM C1063.
C. Cement Plaster: Perform work in accordance with ASTM C926.
D. The Contractor shall make sample panels at the site at least 300cm x 300cm of plaster
work:
1. The Contractor shall take the approval of the Engineer before start plastering.
2. The accepted panels will be a basis of all work
E. Provide Engineer with a letter certifying that all materials and mixes conform to Project
Specifications.
9.5 Delivery, Storage & Handling
A. Deliver manufactured materials in original unopened packages or containers, identified
with manufacturer's label intact and legible. Deliver materials in sufficient quantity to
assure continuity of work. Select and utilize handling equipment so as to avoid damage
to materials handled and damage to other construction.
B. Keep all materials dry stored above ground, under cover, protect from weather, direct
sun light, surface contamination, aging, corrosion and damage from construction traffic
and other causes.
C. The metal lathing does not store any material directly exposed to standing water or on
grade. All material should be supported so that materials are not in direct contract with
the ground.
D. Provide adequate support for the metal lathing to prevent damage of the material prior
to installation.
E. Remove wet or deteriorated materials from the Site.
9.6 Project Condition
A. Environmental Conditions: Comply with requirements of referenced plaster application
standards and recommendations of plaster manufacturer for environmental conditions
before, during, and after plaster application.
10. Painting
10.1 General:
Surface preparation and field painting of exposed exterior and interior items and surfaces.
Use products specified in this section to finish all surfaces exposed to view, unless
otherwise indicated, including but not limited to the following:
a. interior wall and ceiling surfaces.
b. Opening frames and trim.
c. Exterior plaster and stucco.
d. Exterior concrete and concrete masonry.
e. Exterior metal items.
f. Finish aluminum and stainless steel only if specifically indicated to receive
field finish.
10.2 References:
American National Standard Institute (ANSI).
ANSI A13.1 Scheme for the Identification of Piping Systems.
ANSI Z535-1 Safety Color Code.
American Standard for Testing and Materials (ASTM).
ASTM D16 Standard Teminology Relating to Paint, Varnish, Lacquer, and Related Products.
ASTM D3359 Standard Test Methods for Measuring Adhesion by Tape Test.
ASTM D5138-99 Specification for Liquid Crystal Polymers.
ASTM D4236-94R05 Practice for Labeling Art Materials for Chronic Health Hazards.
Painting and Decorating Contractors of America (PDCA)
PDCA P1-92 Touch Up Painting And Damage Repair Financial Responsibility.
PDCA P5-95 Benchmark Sample Procedure For Paint And Other Decorative Coating Systems.
Steel structure painting council (SSPC).
SSPC-SP7 SSPC-SP7, Brush-Off Blast Cleaning.
SSPC SP.10 SSPC SP.10, Near white blast cleaning.
Steel structure painting manual VOP. 1. Good painting practice 2nd .Pitsburgh PA. SSPC. 1983.
Australian Standard (AS).
AS 1428 Design for access and mobility Set
British Standard
BS 544 Specification for Linseed Oil Putty
BS 1336 Specification for Knotting
10.3 Submittals
A. Product Data: For each paint system indicated. Include block fillers and primers. Manu-
facturer's data sheets on each product to be used, including:
a. Preparation instructions and recommendations.
b. Storage and handling requirements and recommendations.
c. Installation methods.
B. Samples for Initial Selection: For each finish product specified, three (3) complete sets of
color chips representing manufacturer's full range of available colors and finishes.
After color selection, Engineer will furnish color chips for surfaces to be coated.
C. Samples for Verification: For each finish product specified, three (3) samples, minimum
size (150mm) square representing actual product, color, and finish, on representative
Samples of the actual substrate.
10.4 Quality Assurance
A. Manufacturer Qualifications: company specializing in manufacture of coatings of quality
specified with minimum of 10 years experience.
B. Applicator Qualifications: A firm or individual experienced in applying paints and coatings
similar in material, design, and extent to those indicated for this Project, whose work has
resulted in applications with a record of successful in-service performance with three
years documented experience.
C. Field Sample: Provide a field sample for evaluation of surface preparation techniques and
application workmanship, showing sequence of all coats using same materials of paint to
be used.
Finish areas designated by The Engineer.
Do not proceed with remaining work until workmanship, color, and sheen are approved
by The Engineer.
D. Source Limitations: Obtain fillers and primers for each coating system from the same
manufacturer as the finish coats.
E. Performance of Paints: Paints shall be fit for purpose and manufactured specifically for
the applications indicated and uses intended, taking into account the type, nature, loca-
tion, and aesthetic and utility requirements of the project.
10.5 Delivery, Storage & Handling
A. Deliver materials to Project site in manufacturer's original, unopened packages and con-
tainers bearing manufacturer's name and label and the following information:
1. Product name or title of material.
2. Product description (generic classification or binder type).
3. Manufacturer's stock number and date of manufacture and expiry.
4. Contents by volume, for pigment and vehicle constituents.
5. Thinning instructions.
6. Application instructions.
7. Color name and number.
B. Store materials not in use in tightly covered containers in a well-ventilated area at a min -
imum ambient temperature of 7 deg C. Maintain storage containers in a clean condition,
free of foreign materials and residue.
C. Keep storage area neat and orderly. Remove oily rags and waste daily.
10.6 Project Condition
A. Do not apply paint in rain, fog, or mist, or when relative humidity exceeds 85 percent; or
at temperatures less than 3 deg C above the dew point; or to damp or wet surfaces.
10.8.3 Application
A. General: Apply paint according to manufacturer's written instructions. Use appli-
cators and techniques best suited for substrate and type of material being applied:
a. Paint colors, surface treatments, and finishes are indicated in the paint
schedules.
b. Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces, or
conditions detrimental to formation of a durable paint film.
c. Provide exterior doors on tops, bottoms, and side edges the same as exte-
rior faces.
d. Colors: to be selected by the Engineer
e. Location: as per drawings.
B. Scheduling Painting: Apply first coat to surfaces that have been cleaned, pre-
treated, or otherwise prepared for painting as soon as practicable after prepara-
tion and before subsequent surface deterioration:
a. The number of coats and film thickness required are the same regardless
of application method. Do not apply succeeding coats until previous coat
has cured as recommended by manufacturer. If sanding is required to
produce a smooth, even surface according to manufacturer's written in-
structions, sand between applications.
b. If undercoats, stains, or other conditions show through final coat of paint,
apply additional coats until paint film is of uniform finish, color, and ap-
pearance. Give special attention to ensure that edges, comers, crevices,
welds, and exposed fasteners receive a dry film thickness equivalent to
that of flat surfaces.
c. Allow sufficient time between successive coats to permit proper drying.
Do not recoat surfaces until paint has dried to where it feels firm, and
does not deform or feel sticky under moderate thumb pressure, and until
application of another coat of paint does not cause undercoat to lift or
lose adhesion.
C. Application Procedures: Apply paints and coatings by brush, roller, spray, or other
applicators according to manufacturer's written instructions.
D. Minimum Coating Thickness: Apply paint materials no thinner than manufacturer's
recommended spreading rate to achieve dry film thickness indicated. Provide total
dry film thickness of the entire system as recommended by manufacturer.
E. Prime Coats. Before applying finish coats, apply a prime coat, as recommended by
manufacturer, to material that is required to be painted or finished and that has
not been prime coated by others. Recoat primed and sealed surfaces where evi-
dence of suction spots or unsealed areas in first coat appears, to ensure a finish
coat with no burn-through or other defects due to insufficient sealing.
F. Painting on woodwork: All cracks, crevices and holes in the woodworks shall be
scrapped out, primed and made good with hard-stopping, and faced up and
rubbed down to an even and smooth finish.
The hard stopping shall be of an approved make or made up on the Site in accor -
dance with the best local custom and to the satisfaction of the Engineer. All knots
shall be burnt and treated with an approved solution of methylated-spirit shellac.
All woodwork shall receive one priming coat of leadless chromates/Alkyds before
installation. After installation, it shall receive two coats of putty and two coats of
undercoat paint (with each undercoat following each putty coat in succession) and
rubbed smooth after each undercoat, and a final coat of semi-gloss or gloss finish
oil paint as required of an approved colour, conforming to B.S. 2525 and as manu-
11. Insulation
11.1 General:
Membrane waterproofing associated with work in accordance with the requirements of the
Contract Documents. Work includes but is not limited to the following:
a. All structural elements are below grade.
b. Wet areas interior wall and ceiling surfaces.
11.2 References: this section should be comply with following
American Standard for Testing and Materials (ASTM).
ASTM D146-90 Test Method for Sampling and Testing Bitumen- Saturated Belts and Woven.
Fabrics for Roofing and Waterproofing.
ASTM D4258-83 Practice for Surface Cleaning Concrete for Coating.
ASTM D5385-93 Test Method for Hydrostatic Pressure Resistance of Waterproofing Membranes.
ASTM D3767-03 Practice for Rubber/Measurement of dimensions.
11.3 Submittals
A. Product Data: Submit to the Engineer for his approval in accordance with the require-
ments of the Contract Documents, manufacturer's specifications and installation instruc-
tions for the membrane waterproofing system and other data to show compliance with
the Contract Documents.
B. Submit three samples of cold fluid applied waterproofing. Samples shall be 300mm
square, on plywood.
11.4 Quality Assurance
C. Manufacturer Qualifications: The manufacturer shall provide evidence indicating that the
specified materials have been successfully utilized on work of a similar scope to that
shown and specified for this Project. The system examples cited shall have been com-
pleted and in use for a minimum of ten (10) years without any evidence of failure.
D. Installer Qualification: Membrane waterproofing and cold fluid applied waterproofing
shall be executed by an approved Specialist with minimum of five (5) years’ experience in
similar Projects.
11.7 Products
11.7.1 Acceptable Manufacturers
No specified manufacturers for this tender, However Products and materials provided by
the contractor shall comply with the requirements of contract documents and subject to
the Employer and Engineer approval and the Engineer and the Employer have the right to
reject any submittal without any liability towards the contract.
11.7.2 Materials
A. Vapor barrier (separation layer polyethylene sheets) 250 microns (1000 gauge),
including over lapping at joints, taping of joints,
Mastic Tape: ECC STRIP Tape.
Description: Black, double-sided, asphaltic, pressure-sensitive, mastic
tape.
Width: 50 mm
11.8 Executions
11.8.1 Examination
Examine all surfaces to which the membrane waterproofing is to be installed. Do not
proceed with the installation until unsatisfactory conditions have been corrected and
approved by the Engineer's Representative.
11.8.2 Preparation
A. Clean substrate of debris and deleterious material which would impair the
Work.
B. Do not proceed with membrane waterproofing until all drains, piping, conduit,
vents, ducts and other projections through the substrate have been installed
and protected.
C. Treat external and internal corners of substrate as shown and in accordance
with manufacturer's recommendations.
D. For the fluid Waterproofing
a. Apply surface conditioner at a rate not exceeding 1 liter per 10 square
meters nor less than 1 liter per 5 square meters depending on con-
crete surface. Protect surface conditioner from rain or frost until dry.
b. Apply 300 mm wide strip of joint cover sheet over cracks, non-working
joints, and expansion joints, over 1.6 mm but not exceeding 12.7 mm
in width.
c. At expansion joints from 12.7 mm to 25 mm in width, loop cover sheet
down into joint between 1-1/4 and 1-3/4 inch 31.4 and 44.1 mm.
Sheet is to extend at least 6 inches 152 mm on either side of the ex-
pansion joint.
d. Center cover sheet over crack or joints. Roll sheet into 3.2 mm coating
of waterproofing membrane. Apply second coat over sheet extending
minimum of 152mm, beyond sheet edges.
11.8.3 Installation
A. Install vapor retarders in accordance with manufacturer's instructions and
ASTM E 1643 for concrete slabs.
B. Install vapor retarders in largest practical widths. Membrane to be unrolled
with the longest dimension parallel to the direction of the pour.
C. Ensure surface beneath vapor retarders is smooth with no sharp projections.
D. Join sections of vapor retarders and seal penetrations in vapor retarders with
mastic tape with a minimum 6-inch overlap. Ensure vapor retarders surfaces to
receive mastic tape are clean and dry.
E. Immediately repair holes in vapor retarders with liquid mastic or vapor barrier
section with mastic tape.
F. Install membrane and water proofing in accordance with manufacturer's
printed instructions except as hereinafter specified for all installation proce-
dure.
G. Prime surfaces in accordance with manufacturer's instructions.
H. Follow the recommended technique of the membrane manufacturer for clean-
ing, seam, lap and splice areas, for the method and sequence of forming field
joints in the membrane.
I. Flash all pipes, conduits, sleeves, and other projections passing through mem-
brane waterproofing and provide tight construction throughout. Use prefabri-
cated boots or field-fabricated boots, fitted coverings, and other accessories as
required.
J. Provide water cut-off's in accordance with the approved membrane manufac-
turer's recommendations.
K. Install protection board in accordance with manufacturer's instructions.
L. Upon completion of any portion of waterproofing, immediately cover that por-
tion with protective covering.
M. For the fluid Waterproofing
a. At the start of the installation and periodically as work progresses pro-
vide the services of the manufacturer's technical representative at the
job site as often as deemed necessary by the manufacturer to advise
on all phases of this work.
b. Install the system in accordance with the manufacturer's instructions,
except where more stringent requirements are shown or specified.
c. Install cant strips where shown or recommended by the waterproofing
materials manufacturer.
d. Allow waterproofing to cure properly. During this period block off
traffic and protect waterproofing from physical damage.
11.8.4 Application
A. All prepared surfaces shall when dry, be painted with a coat of primer at a rate
recommended by waterproofing manufacturer. All blinding surfaces must be
finished fair-faced or trowel smooth to receive the waterproofing membrane.
B. Apply the waterproof membrane surface against prepared surfaces, in accor-
dance with manufacturers recommendations, ensuring that air is excluded from
under membrane.
C. Adjacent rolls of waterproof membrane should be provided with a minimum
150 mm lap and complete adhesion must be achieved between both layers to
ensure complete waterproofing.
D. All external and internal angles and corners shall be reinforced with an extra
strip of waterproof membrane, minimum 300 mm wide.
E. All internal corners should be provided with a 50 mm X 50 mm minimum fillet.
F. All end of membrane shall be 20mm x 20mm rebate in to concrete.
12.6 Products
12.6.1 Acceptable Manufacturers
Terrazzo and Ceramic Tiles: Manufacturer with experience in the specified product
and approved by the Engineer.
.
12.6.2 Materials
A. Terrazzo
1. Precast terrazzo units ( sizes: 250 x 250 mm and 300 x 300 mm) shall
be formed with a (1:2.5) mix of white or tinted Portland cement and
granular local marble chippings for the topping (wearing layer) set on
cement and sand backing (1:5) mix and shall be obtained from an ap-
proved manufacturer. All in accordance with JSS.
2. The units shall be case in heavy steel moulds under. pressure to the
proportions and sieve sizes approved by the Engineer. The thickness
of the wearing layer shall not be less than 10 mm and the pattern and
dimensions shall be as shown on the drawings and/or stated in the
Bill of Quantities.
3. Grinding shall be done wet by means of a No. 80 Carborundum stone.
Filling shall be carried out with a neat cement grout of the same
colour as the facing mix and this shall be worked into the surface with
a wooden scraper. to fill all voids and air holes. Surplus grout shall be
removed with a dry cloth.
E. Admixtures:
Admixtures to cement: sand Mortar : Admixtures to cement: sand
mortar may be air entraining-, water reducing-, plasticizing-, retarding
agents and shall comply with BS 5075 or an equivalent standard.
Admixtures to Adhesives: Admixtures to adhesives shall be used in ac-
cordance with manufacturer's instructions. They shall not be added to
any adhesive unless approved by the manufacturer of the adhesive.
Bonding Agents: Bonding agents shall comply with manufacturer's in-
structions and shall be certified as suitable for the intended use.
Grouts: Grout shall have low shrinkage and good adhesion and shall be
certified by the manufacturer as suitable for the intended use.
Sand: Cement Grout : The proportions of cement: sand shall be 1:1 for
joints not exceeding 3.0 mm, 1:2 for joints between 3.0 mm and 6.0
mm and 1:3 for joints wider than 6.0 mm. For joint width up to 6.0
mm, sand for grouts shall not exceed 2.36 mm. Necessary alkali-resis-
tant pigments shall be added to achieve white or colored joints as indi-
cated or, if not indicated, as approved by the Engineer.
Cement: sand-bedding mortar shall comply with BS 5385 or an equiva-
lent standard
12.7.3 Installation
A. The installation should be comply with BS 5385-3 or equivalent.
B. Tiles shall be laid to pattern as indicated. If no special pattern is required, sur-
faces to receive tiling shall be centred and balanced.
C. Tile work shall be extended into recesses and under or behind equipment and
fixtures to form a complete covering without interruptions.
D. Tiles shall be closely fit to electrical outlets, piping, fixtures and other penetra-
tions so that plates, collars or covers overlap tile.
E. Cuts shall only be made where no alternative is possible. Generally, cuts shall
be positioned on the outer edges of surfaces and no cuts shall be smaller than
half tile size.
F. Wall tiles shall be laid in full courses to the nearest obtainable dimension unless
otherwise indicated.
G. To ensure that courses of tiles are exactly horizontal, a level line shall be estab-
lished to position the starting course.
H. All joints shall be straight and of even width.
I. All finished areas and surfaces shall be flat, level and true. The surface will be
true, when checked with a (2.0 m) straightedge, any gap found does not exceed
3 mm and the straightedge will not be obstructed by tiles. The max. Deviation
12.7.4 TOLERANCES
There shall be no abrupt irregularities in the surface of plasterwork and other
finishes and there shall be no gradual irregularities exceeding 5 mm in a 2 m
length.
12.7.5 Protection and cleaning
A. On completion of placement and grouting, clean all ceramic tile surfaces in ac-
cordance with manufacturer's written instructions so they are free of foreign
materials.
B. When recommended by tile manufacturer, apply coat of neutral protective
cleaner to completed tile walls and floors.
C. After lying floor tiles, no traffic shall be allowed on the floor for the first 7 days
and after that only light traffic as approved by the Engineer is allowed for the
next 10 days.
13.6.2 Materials
A. Aluminum windows, doors, and Fabrication:
1. Aluminum windows and doors shall be designed and fabricated by
the
Contractor in accordance with BS 4873.
2. Sections shall be extruded aluminum alloy complying with BS EN
485-1, BS EN 485-2+A1, BS EN 485-3, BS EN 485-4, BS EN 515, BS EN
573-1, BS EN 573-2, BS EN 573-3, BS EN 573-5, BS EN 755 and BS EN
12020, British alloy designation 6063
3. Aluminum Components: Alloy and temper best suited to application.
a. Extrusions: ASTM B221.
b. Sheet: ASTM B209.
c. Castings: ASTM B85.
d. Steel Shapes: ASTM A36/A36M.
4. Aluminum Components: Alloy and temper best suited to application.
5. Fabrication:
a. Fabricate with minimum clearances and shim spaces around
perimeter yet enabling installation and dynamic movement.
b. Accurately fit and secure joints and intersections. Make
joints flush, hairline, and weathertight.
c. Fabricate in largest practical units.
d. Conceal fasteners and attachments from view.
e. Reinforce framing members with internal metal (steel or Alu-
minum) when required to support imposed loads.
f. Fabricate so that components will not be excessively
strained under normal conditions of use.
g. Provide slotted holes for erection adjustment and thermal
movements.
13.7 Executions
13.7.1 Preparation
A. Removing the easing wooden window and doors.
B. Remove coatings, including curing compounds and other substances that con-
tain soap, oil, or silicone, dust.
13.7.2 Installation
A. Installation Glass:
a. Clean glazing rabbets; remove loose and foreign matter.
b. Install glass in accordance with glass manufacturer's instructions.
c. Maintain manufacturer's recommended edge and face clearances be-
tween glass and frame members.
d. Installation - Structural Silicone Glazing Method
i. Mask aluminum and glass surfaces adjacent to sealant pock-
ets.
ii. Install temporary glass retainers to align faces of glass.
iii. Apply contact sealant; completely fill pockets. Tool joints and
remove masking tape before sealant skim cure begins.
iv. Allow sealant to cure minimum time required by manufac-
turer.
v. Remove temporary glass retainers.
vi. Insert joint backing to fill void between glass unit edges and
glass spacer.
vii. Mask both sides of glass for full length of joint.
viii. Apply weather seal sealant; tool to smooth, slightly concave
profile.
e. Installation - Silicone Glazing Method
i. Mask both sides of joint for full length.
ii. Install temporary glass retainers to align faces of glass.
iii. Provide temporary joint backing for one side of joint.
iv. Apply sealant to completely fill spaces; tool to smooth,
slightly concave surface.
v. Allow sealant to cure minimum time required by manufac-
turer. Remove temporary backing and fill voids with addi-
tional sealant.
f. Installation - Mirrors
i. For screw hanged mirrors: pre-drilled fixing holes. Mirrors
shall have (5x5) mm stainless steel frame. Mirrors shall be
fixed with 1.5 mm stainless steel hooks plate glued to back of
Performance Requirements:
1. Strength Requirement:
Provide evidence to demonstrate that the works, including ironmongery, have
been tested to meet the minimum acceptance criteria given in DD 171 for the
following:
Slamming shut impact.
Slamming open impact.
Heavy body impact.
Hard body impact.
Torsion.
Download deformation.
Closure against obstruction.
Resistance to jarring and vibration.
Abusive forces on door handles.
2. Ensure that metal doors and frames comply with the minimum requirements of BS
1245
Technical Specifications- Civil, Architectural, and Electrical Works
100
for Rehabilitation of Admin Building in Fishery Harbor
3. All Steel sections should comply with ASTM A36/A36M: Standard Specification for Car-
bon Structural Steel
4. The door assemblies, including the installation method within door openings, shall
comply with the following fire rating requirements:
Copies of test certificates shall be provided to the Engineer prior to manufac-
ture.
All finishes shall provide the required surface spread of flame characteristics in
accordance with the requirements of Local Building Regulations and the re-
quirements, unless otherwise specified, indicated or agreed.
All fire doors and frames including fire seals and all associated materials and in-
stallation shall comply with the requirements of the NFPA.
5. Smoke Passage and Air Leakage: The external door sets shall have certification illustrat-
ing conformance with BS 5588.
14.3 Submittals
A. Shop Drawings - Show: Shop drawings showing fabrication and installation of standard
and custom-made metal doors and frames. Include details of each frame type, elevations
of door types, conditions at openings, details of construction, location and installation re-
quirements of door and frame hardware and reinforcements, and details of joints and
connections. Show anchorage and accessory items.
B. Samples: Samples for initial selection purposes in form of manufacturer’s color charts
showing full range of colors or patterns available for factory-finished doors and frames.
Samples for verification purposes of each type of exposed finish required, prepared on
samples not less than (10 × 15) cm and of the same thickness and material indicated for
the final unit of work.
C. Product Data
a. Provide product data for each type of door and frame specified, including details
of construction, materials, dimensions, hardware preparation, core, label com-
pliance, sound and insulation ratings, profiles and finishes and manufacturer’s
instructions.
b. Provide manufacturer’s certificates for all elements indicated showing compli-
ance with referenced standards and/ or requirements of local authorities.
14.4 Quality Assurance and QC:
A. Products used in the work of this Section shall be produced by manufacturers regularly
engaged in manufacture of similar items and with a history of successful production ac-
ceptable to the Engineer.
B. Qualifications of Installers
a. Use adequate number of skilled workmen who are thoroughly trained and expe-
rienced in the necessary crafts and who are completely familiar with the speci-
fied requirements and the methods needed for proper performance of work.
b. Contractor’s site supervisor(s) shall have knowledge of referenced standards and
at least five (5) years of documented experience.
14.5 Delivery, Storage & Handling
A. Deliver metal doors and frames cardboard-wrapped or crated to provide protection dur-
ing transit and job storage. Provide additional protection to prevent damage to finish of
factory-finished doors and frames.
B. System components and doors at building site shall be under cover. Place units on mini-
mum 10-cm high wood blocking. Avoid use of non-vented plastic or canvas shelters,
which could create humidity chamber. If cardboard wrapper becomes wet during trans-
port, remove carton immediately. Provide minimum 5.0 cm spaces between stacked ele-
ments to promote air circulation.
C. Protect hardware materials during delivery to comply with manufacturer’s directions,
and as required to prevent any damage, especially to plated and polished articles, includ-
ing effects of moisture, condensation and temperature change.
D. Store hardware at building site only originally packed, protect it against dust and dirt and
take care for proper ventilation to prevent condensation.
B. General
1. All work shall be performed by skilled workmen, especially trained
and experienced in this type of work.
2. A high degree of accuracy is required in the fabrication and installa-
tion of the work.
3. Carry out all work and use all materials in accordance with the manu-
facturer's printed recommendations.
4. Accurately cut and form materials to the required shape and with all
exposed surfaces and edges true and free from irregularities and de-
fects, using techniques that will not impair the strength of materials
used.
5. The works elements shall be square, regular to level and plane with
all junctions fitting to the stated tolerances.
6. Ensure that the shadow gaps indicated on the design are maintained
at the head and jamb conditions.
7. The Metal Doors installation shall satisfy the criteria specified herein
based on the design intent, as indicated on the Design Drawings. The
Contractor shall submit full technical data/details regarding all fixings
for review by the Engineer. The Contractor shall remain responsible
for the selection of fixings regardless of any approvals given. Unless
otherwise specified, all fixings to be concealed.
8. All visible welds shall be full penetration butt welds ground smooth
and flush, continuous and hand dressed. All shaped steel to be ma-
chine profile (plasma) cut.
9. Welding using E70 to weld all the steel sections.
10. Metal doors shall be fitted so that gaps around the doors are mini-
mized and no greater than 8mm at the threshold and 6mm else-
where.
11. The metal door system shall be rigid and wobble free.
12. The metal door system shall not rattle, squeak or whistle.
13. The metal door system shall be easy to clean and hygienic.
14. The metal door system shall be easily operable by one person.
14.7 Executions
14.7.1 Examination
1. Examine existing conditions for compliance with schedules and for com-
pleteness of other trades supposed to be finished before starting of doors
installation.
2. Do not proceed with installation until unsatisfactory conditions have been
corrected.
14.7.2 Protection of Components
A. Do not deliver to Site components, which cannot be put immediately into suit-
able dry, covered storage with a dry floor. Stack on bearers, separated with
spacers to prevent damage by and to projecting ironmongery, beads, etc.
Where doors are delivered to Site in a finished condition, any necessary protec-
tion shall be provided to the doors when applying coatings to the frames and
the like, allowing sufficient drying times to coatings to ensure that the doors are
not marked in any way with the coating material.
14.7.3 Preparation
A. Examine doors prior to installation. Minor damages may be repaired on site
provided refinished items are equal in all respects to new work and acceptable
to the Engineer; otherwise replace damaged items as directed.
B. Verify that doors comply with the requirements in schedules for type, size, loca-
tion and swing characteristic.
14.7.4 Installation
A. Particular attention shall be paid to the interface between the door frames and
new and existing walls when preparing the Shop Drawings and during installa-
tion. Interfacing requirements shall be in accordance with the visual require-
ments as indicated on the Design Drawings.
15.4 Submittals
A. Shop Drawings - Show:
a. Vertical section profile drawings showing pipe sizes and manholes, locations, ele-
vations, and other piping in the same trench, including connections to the public
water supply. Diagrammatic drawing(s) identifying all valves and their function.
b. Design Calculations: Signed and sealed by a qualified professional engineer for
selecting seismic restraints.
B. Samples:
a. Full size, for each accessory item to verify design, operation and finish require-
ments.
b. approved full size Samples will be returned and may be used in the Work. C.
Product Schedule:
i. Indicating types, quantities, sizes, and installation locations by room of
each accessory required.
Technical Specifications- Civil, Architectural, and Electrical Works
108
for Rehabilitation of Admin Building in Fishery Harbor
ii. Identify locations using room designations indicated.
iii. Identify products using designations indicated.
c. Warranty: Sample of special warranty.
C. Product Data
a. Manufacturer’s product description and recommended installation instructions
for each plumbing equipment, plumbing fixture category , and pipes specified.
Include selected fixture, trim fittings, accessories, appliances, appurtenances,
equipment, and supports. Indicate materials and finishes, dimensions, construc-
tion details, and flow control rates. Manufacturer’s operating and maintenance
requirements..
15.5 Quality Assurance and QC:
A. Sampling, testing and checking procedures shall be recorded on a daily basis (i.e. indicat-
ing day, month, year) including corrective actions taken by the Contractor if necessary.
B. Reports and records shall be available to the Engineer not later than three (3) days after
testing and checking.
C. Reports and records shall be established and maintained in a manner to ensure traceabil-
ity.
D. Arrangements shall be made in Contractor’s work schedule and time allowed for checking
and testing as indicated.
E. Qualifications of Installers
a. Contractor’s site supervisor shall have knowledge of referenced standards and at
least five (5) years of documented experience in works related to plumbing pip-
ing and shall have successfully completed works similar in design, material, and
extent to that indicated in the Project.
b. Installers shall be familiar with the material and installation procedures indicated
and shall be skilled and trained.
c. Contractor’s personnel performing disinfection of the water distribution system
shall be familiar with the physiological, chemical, and physical properties of the
chemicals being used and shall be trained and equipped to handle any emer-
gency which may arise.
15.6 Delivery, Storage & Handling
A. Whether moved by hands, hoists, or other acceptable method, pipes, components and
equipment shall not be thrown, dropped, dragged, bumped, or allowed to impact on ob-
jects that cause damage.
B. Materials shall not be stored directly on the ground. Pipes and fittings shall be kept free
of dirt and debris, pipe openings shall be closed with caps or plugs during installation.
C. Fixtures and equipment shall be tightly covered and protected against dirt, water and
chemical or mechanical injury.
D. Storage of plastic pipes shall be on wooden sleepers, spaced suitably so as not to allow
deformation of the pipe at the point of contact with the sleeper or between supports.
E. Stacking of pipes shall be limited to a height that will not cause extensive deformation of
the bottom layers of pipes under anticipated temperature conditions. Special attention
shall be given to the ends of each pipe section so that the outer roundness of the pipe re-
mains virtually unchanged.
F. Plastic pipes, fittings or castings that have been in contact with gasoline, lubricating oil or
aromatic compound shall not be stored or installed.
15.7 Products
15.7.1 Acceptable Manufacturers
A. Sanitary fixtures shall have smooth impervious surfaces, be free from de-
fects and concealed fouling surfaces, and shall conform in quality and de-
sign to one of the standards mentioned in this specification
B. Each fixture and device used shall have cast, stamped, or indelibly marked
on it the maker’s mark or name and the type of the product, when such
marking is required by the approved standard that applies.
C. All fixtures shall be new and of first quality, free from scale, lamination
and other defects.
Technical Specifications- Civil, Architectural, and Electrical Works
109
for Rehabilitation of Admin Building in Fishery Harbor
D. Flexible wall supplies shall be with wheel handle control stop, escutcheon
and flexible tube riser.
E. Sizes and colours of sanitary fixtures shall be as specified in the Project
Documents.
15.7.2 Materials
A. POLYPROPYLENE PIPES AND FITTINGS (PP):
1. Company with
DIN 1988 DVGW Code of Practice (Drinking water supply
systems; materials, components, appliances, design and installa-
tion)
DIN 8076 Standard for testing metal threaded joints
DIN 8077 Polypropylene (PP) pipe dimensions
DIN 8078 Polypropylene (PP) pipes; general quality re-
quirements testing & chemical resistance of pipes and fittings
DIN 2999 Standards for fittings with threaded metallic in-
serts
DIN 16962-1 Pipe joint assemblies and fittings for type 1 & 2
polypropylene (PP) pressure pipes; bends produced by segment
inserts for buff welding dimensions
DIN 16928 Installation, pipe and fitting connections
DVS 2207 Welding of thermoplastic pipes and fittings
DVS 2208 Welding machines & devices for thermoplastic
pipes and fittings
2. Soundproof Drainage pipe should be manufactured in accordance
with DIN EN in building and for laboratory installation inside the
building structure and is approved by the German Institute of Building
Technology (DIBt), approval number should be clear on both pipes
and fittings.
3. (The pipes should be made of Polypropylene with Mineral reinforced
Polypropylene middle layer; density should not be less than 1.9 g/
cm³.
4. Pipes with Pn 25 with Aluminium thickness 0.2 mm According to din
8077/78 Special technology with black layer (uv resistant ) for out
door and external installations under sunlight
5. The pipes and fittings should be tested in accordance to DIN EN
14366, DIN 4109 and should have results in UG rear at 4L/S flow rate
of 18dB(A) with sound proof clamps and 25dB(A) with normal clamps
-for vertical installations.
6. Behavior in fire: to correspond to B2 normally flammable (as per the
B2 classification) according to DIN 4102 and D-S3, d0 according to EN
13501-1.
7. Pipes and fittings should be pre-installed with a lip-sealing ring.
8. Material: SBR or EPDM
9. Pipes, fittings and floor traps to withstand a continuous operating
temperature of 90°C, and 95°C for brief load and should have a chem-
ical resistance range of pH 2 to 12
10. All fittings should be of PP-MD (Mineral reinforced Polypropylene)
from the same manufacturer, DIBt approval number should be clear
on each fitting.
11. Pipe installation clamps, supports and other related accessories shall
be of the type to suit the soundproof/low noise piping installations.
The same to be as per the recommendations of the piping manufac-
turer.
B. Above Ground Soil, Waste, Overflow and water Systems (for above
ground drainage installations):
15.8 Executions
15.8.1 Examination
1. Immediately before laying, examine accessories, each pipe and joint again
for soundness and cleanliness and make sure that material and surfaces
which form part of a joint are clean and dry before commencing their as-
sembly. All defective material shall be replaced. Check that the position
and levels of existing drains and services have been established.
2. Examine roughing-in for potable, hot- and cold-water supply piping sys-
tems; soil, waste, and vent piping systems; and supports. Verify that loca-
tions and sizes of piping and locations and types of supports match those
indicated, before installing and connecting fixtures. Use manufacturer's
roughing-in data when roughing-in data are not indicated..
15.8.2 Preparation
A. Where pipes are generally provided with flexible joints, locate joint po-
sitions as closely as practicable to the external faces of structures and
the like, through which the pipes are laid. Where pipes are generally
laid with rigid joints and there is no specified provision for flexible
joints at the above positions, get instructions of the Engineer, if it is re-
quired that such provisions are necessary.
B. All metal water pipes shall be bonded to the electrical installation main
earth terminal as near as possible unless otherwise indicated.
C. Gaskets, seals, sleeves, couplings etc. shall be installed in accordance
with manufacturer’s recommendations for use of lubricants, solvent
cements, glue, etc. and other installation requirements.
D. Where pipe routing is left to the contractor's discretion, he shall after
receipt of the construction drawings prepare detailed and accurate
pipe arrangement plans and obtain Engineer’s approval early enough
to ensure that the necessary slots and recesses are provided. The Engi-
neer’s approval shall not be deemed to limit the contractor's responsi-
bility in any way.
E. Clearances shall be considered under beams, over windows and in sus-
pended ceilings. Piping installation shall be co-ordinated with duct-
work, lighting and other trades.
F. Vertical pipes shall be plumb, horizontal pipes shall be level, and where
two or more adjacent pipes extend in the same direction, they shall be
parallel.
15.8.3 Installation
A. Piping Installation
1. Install cleanouts at grade and extend to where building sanitary drains
connect to building sanitary sewers.
2. Install cleanout fitting with closure plug inside the building in sanitary
force-main piping.
Technical Specifications- Civil, Architectural, and Electrical Works
112
for Rehabilitation of Admin Building in Fishery Harbor
3.
Install wall-penetration fitting at each service pipe penetration through
foundation wall. Make installation watertight.
4. Make changes in direction for soil and waste drainage and vent piping
using appropriate branches, bends, and long-sweep bends. Sanitary
tees and short-sweep 1/4 bends may be used on vertical stacks if
change in direction of flow is from horizontal to vertical. Use long-
turn, double Y-branch and 1/8-bend fittings if 2 fixtures are installed
back to back or side by side with common drain pipe. Straight tees, el-
bows, and crosses may be used on vent lines. Do not change direction
of flow more than 90 degrees. Use proper size of standard increasers
and reducers if pipes of different sizes are connected. Reducing size of
drainage piping in direction of flow is prohibited.
5. Lay buried building drainage piping beginning at low point of each sys-
tem. Install true to grades and alignment indicated, with unbroken
continuity of invert. Place hub ends of piping upstream. Install re-
quired gaskets according to manufacturer's written instructions for use
of lubricants, cements, and other installation requirements. Maintain
swab in piping and pull past each joint as completed.
6. Install soil and waste drainage and vent piping at the following mini-
mum slopes, unless otherwise indicated:
i. Building Sanitary Drain: 2 percent downward in direction of
flow for piping NPS 3 (DN 75) and smaller; 1 percent down-
ward in direction of flow for piping NPS 4 (DN 110) and larger.
ii. Horizontal Sanitary Drainage Piping: 2 percent downward in
direction of flow. 3) Vent Piping: 1 percent down toward ver-
tical fixture vent or toward vent stack. L. Sleeves are not re-
quired for cast-iron soil piping passing through concrete slabs-
ongrade if slab is without membrane waterproofing.
7. Do not enclose, cover, or put piping into operation until it is inspected
and approved by the Engineer
B. Valve Installation
1. Shutoff Valves: Install shutoff valve on each sewage pump discharge.
2. Install gate or full-port ball valve for piping NPS 2 (DN 50) and smaller.
2) Install gate valve for piping NPS 2-1/2 (DN 65) and larger.
3. Check Valves: Install swing check valve, between pump and shutoff
valve, on each sewage pump discharge.
4. Backwater Valves: Install backwater valves in piping subject to sewage
backflow.
i. Horizontal Piping: Horizontal backwater valves. Use normally
closed type, unless otherwise indicated.
ii. Floor Drains: Drain outlet backwater valves, unless drain has
integral backwater valve.
iii. Install backwater valves in accessible locations.
C. Connections
1. Drawings indicate general arrangement of piping, fittings, and special-
ties.
2. Connect soil and waste piping to exterior sanitary sewerage piping.
Use transition fitting to join dissimilar piping materials.
3. Connect drainage and vent piping to the following:
i. Plumbing Fixtures: Connect drainage piping in sizes indicated,
but not smaller than required by plumbing code.
ii. Plumbing Fixtures and Equipment: Connect atmospheric vent
piping in sizes indicated, but not smaller than required by au-
thorities having jurisdiction.
15.8.4 Testing
A. The test pressure shall not be less than 1.5 times the rated pressure for the
weakest part of the pipeline.
B. All intermediate control vales shall be open throughout the duration of the test.
If a network is tested by sections, the ends shall be temporarily closed by
means of suitable joints. Air vents at high points shall be open during the filling
of the network.
C. Slowly fill the pipes with potable water starting from the lowest point, thus
avoiding water hammer and removing all air.
D. Once the network has been completely filled with water, leave the pipeline to
rest for 24 hours. Close the air vents and carry out an initial inspection to check
that all the joints are leaktight.
E. Slowly increase the pressure, using a hand pump, until the required pressure is
obtained. A preliminary application of pressure for 15 min may be made before
the test, so that the elements in the pipeline can settle. For pipelines with diam-
eters of DN 600 or larger, motor pumps shall be used.
F. Isolate the pipeline from the test pump for at least 1 hour. The test is consid-
ered satisfactory if the quantity of water required for re-establishing the re-
quired pressure does not exceed the quantity calculated by the following for-
mula:
G. 3 Litres per kilometre of pipe, per 25 mm of internal diameter, per 0.3 MPa (3
bar) of test pressure, and per 24 hours.
H. For pipe sections not exceeding 30 m in length and 63 mm in diameter, the
pressure loss after the test period of 1 hour shall not exceed 0.05 MPa (0.5 bar).
I. Recording Results of Field Quality Control: For every test and visual inspection,
record the following information and provide copies to the Engineer as re-
quired:
i. -the location of pipeline or other item inspected or tested and
the date of the inspection or test.
ii. Test Pressure
iii. Duration of the test
iv. Serial number of the calibrated pressure gauge used in the
record-the results
v. -the personnel involved
15.8.5 Protection and cleaning
A. After the completed pipelines are tested and approved, the entire sanitary sew-
erage and stormwater drainage system shall be thoroughly flushed with water
until all dirt and mud have been removed.
B. Protect completed sections of pipelines from damage by construction traffic
and work of other trades.
A. The extent of the electrical works includes the supply of materials and equipment, delivery to the site, labor,
installation, testing and commissioning of all electrical services as detailed or referred to in these specifications
and/or shown in the drawings, including all other associated work such as supporting structure and ancillary
works, attendance, etc., and the like. Unless otherwise specifically indicated, the work shall also include the
supply of electrical power to all electrically operated equipment. The electrical power supply point of all sta-
tionary and electrically operated equipment shall be the supply terminal box on the equipment or its nearby
isolating/starting device if the equipment is supplied with a flexible cable and ready for connection. The electri-
cal services shall be complete and in perfect working order.
B. All equipment and/or accessories not specifically mentioned in the specifications or noted in the drawings,
but which are obviously necessary for the proper and normal operations of the various systems shall be in-
cluded. The Contractor shall provide and execute such works as a part of the contract and shall not be entitled
to any extra payment on the account.
C. Without restricting the generality of the foregoing, the electrical installation of the project includes the sup-
ply and installation and testing the equipment and materials detailed in the following specification sections:
Equipment Electrical Connections.
Electrical Raceway System (conduits, trays, ladders, trunking).
Wires and Cables.
Wiring Devices.
Distribution Boards.
Lighting System.
Earthing System.
Fire Alarm and Detection System.
D. All work shall be carried out strictly in accordance with this specifications, and other applicable project spec-
ifications and design drawings.
Technical Specifications- Civil, Architectural, and Electrical Works
116
for Rehabilitation of Admin Building in Fishery Harbor
E. The contractor shall carry out a thorough inspection of all items of electrical equipment for damage prior to
locating the equipment and proceeding with the electrical installation. If any damage is evident or suspected, it
shall be reported to the engineer, who will determine the action to be taken and advise the contractor accord-
ingly.
F. No variation shall be permitted without the written consent of the engineer, who shall reserve the right to
request the substitution of the correct materials and/or equipment. Should any replacement be deemed nec-
essary by the engineer, then the contractor shall bear the cost of substitution, and all of associated builder's
work and the making good of finishes attributed to the work or replacement.
G. Any materials and/or apparatus that are supplied by others for installation and/or connection by the con-
tractor shall be examined on receipt to locate any possible defects in such materials and/or apparatus. Should
any defects be found, the contractor shall immediately notify the engineer to ascertain what action is neces-
sary.
H. The contractor shall also allow for storing, putting into position, fixing where necessary, connecting, and
testing such materials and/or equipment.
I. The contractor shall be responsible for the full protection of all materials supplied to him, or handed to him
by others, for incorporating in the works against damage or loss until the works are handed over to the Engi-
neer.
J. If the contractor refuses or neglects to remedy, in a stipulated period, that which the engineer considers to
be in accordance with the General and Particular Specifications and/or associated schedules, and/or associated
drawings, to be caused by bad workmanship the Engineer may, if he wishes, arrange for the work to be carried
out by others and be entitled to deduct the amount paid from the contract sum.
K. Materials shall be in accordance with the General and Particular Specification herein. Where a standard is
not specified, materials shall be warranted for fitness of purpose under the conditions shown and specified.
L. Materials to be supplied by the contractor shall be available on site by the date stipulated in the bar chart.
Any airfreight costs to meet these dates shall be for the Contractor’s account.
M. Where equipment or products are specified to conform to the requirements of a testing agency and label-
ing service of such agency is offered for such equipment or product, the proper label shall be attached to the
equipment or product as proof of conformance.
N. Unless specifically waived in each instance, testing procedures shall be performed in the presence of the En-
gineer.
O. Materials and devices shall be inspected prior to installation by the engineer as part of the work of this sec-
tion before and after installation to ensure that they are of the quality and type specified herein, free of manu-
facturing defects and subsequent damage, and that they have been installed in the proper manner. In all as-
pects the quality of equipment and documentation shall be governed by BS 5750 Quality Systems/ISO9000 to
ISO 9004.
P. The contractor shall obtain the approval of the local authority for all electrical and telephone work to be un-
dertaken. Any modification required by the local authority shall be considered included in the contractor cost.
16.3 Conduct of Work
All work under this Contract which may interfere with the operation of the Owner’s utilities, shall be done in
such a manner and at such time as may be satisfactory to the Owner.
Make temporary alternations and connections as required to execute work so that all services in the building
are maintained with the minimum possible interruption.
Temporary shutdowns shall be segregated and shall be of the shortest possible duration. All services shall be
kept on continuous operation unless permissions are otherwise granted by the Owner.
All temporary wiring shall be the responsibility of the Contractor at no additional cost of the Owner.
16.4 Service Conditions
A. All electrical equipment, apparatus, accessories and fittings shall be so designed and manufactured to
operate continuously in the electricity supply system having the following characteristics:
B. It is the Contractor’s responsibility to investigate the exact characteristics of the power supply and to
adapt the design accordingly at no additional cost for the Owner.
A. All works within the project and particularly above suspended ceilings or inside vertical shafts shall be
so installed as to be accessible for operation, maintenance, and repair. Deviations from the drawings
may be made to accomplish this, but no change shall be made without written approval from the En-
gineer.
B. Locations of access doors and panels shall be approved by the Engineer before installation work is
commenced.
A. All material and equipment, fixed or unfixed, shall be protected against corrosion, deterioration and
ingress of foreign matter and moisture.
B. All material and equipment shall be kept clear of the floor or ground by means of wooden bearers and
shall be protected against the weather with durable waterproof wrapping and other appropriate
means.
C. The Contractor shall be liable for any loss due to delivery, storage, or site security problems.
A. All signs and notices shall be in Arabic and English with the Arabic version being above or to the right
of the English version.
B. A schedule of all signs and notices with proposed Arabic translations shall be approved by the Engi-
neer prior to manufacture.
C. The entire Electrical Installation shall in all respects comply with the requirements of the latest edi-
tions of the following Standards with any current additions and amendments:
A. Unless otherwise stated on the drawings, the following shall be mounting heights of equipment above
finished floor level subject to full coordination with architectural details, medical equipment’s as de-
tailed in the 1/20 Loaded Drawings and other disciplines/equipment. Any discrepancy found between
these heights and other details/disciplines shall be brought to the notice of the Engineer for clarifica-
tion and final decision.
B. Where accessories with varying mounting heights (e.g., light switch and socket outlet) are shown in
approximately the same location, their center lines shall be aligned vertically.
C. Where wall mounted accessories are shown adjacent to each other they shall be mounted with their
wall plates separated by 50 mm.
A. All items of electrical distribution equipment and cables, including local disconnectors and switches
controlling fixed equipment and appliances, shall be fitted with identification labels and notices as in-
structed by the Engineer. These labels shall bear the equipment designation as shown on the "As-
Built" Drawings plus the supply voltage, phase, frequency, and distribution circuit number.
B. Switchgear shall (in addition to the identification labels) be fitted with a stainless-steel plate fixed in a
prominent position and engraved "DANGER VOLTS" together with the generally adopted “double
flash” danger signal. A number indicating the nominal system shall prefix the word “VOLTS”. The let-
ters shall be 12mm minimum height in signal red code 537 to BS 381C.
C. Switchgear shall (in addition to the identification labels) be fitted with a stainless-steel plate fixed in a
prominent position and engraved "DANGER VOLTS" together with the generally adopted “double
flash” danger signal. A number indicating the nominal system shall prefix the word “VOLTS”. The let-
ters shall be 12mm minimum height in signal red code 537 to BS 381C.
D. The interior of each item of 3-phase equipment shall be clearly marked to show the phases. For this
purpose, either colored plastic discs screwed to fixed components or identification by means of col-
ored plastic sleeving shall be employed.
E. All labels and notices shall be engraved in the English language. Danger labels shall be engraved in
Arabic and English.
F. All cabinets and boxes shall bear clear external marking of their function and the areas covered.
G. All barrier strip outlets and inputs from main equipment shall be labelled as above by means of solidly
mounted engraved plastic strips held in by means of non-corroding flush head screws.
H. All labels shall be of two- or three-layer laminated plastic and shall be fixed by means of screws.
I. General information labels must have block characters on a white background with characters not
less than 6 mm high.
J. Warning labels must have black characters on a yellow background with characters not less than 8
mm high and not more than 25mm.
K. Mandatory labels must have white characters on a blue background with characters not less than 8
mm high and not more than 25mm.
L. All fuse boards, distribution boards and switchboards shall be fully labelled, a main label shall be fixed
to the front of the board detailing the heading or name it appears on the schematic/wiring diagram
and the source of the cable feeding the distribution board.
M. All sub-circuits in distribution boards and fuse boards shall be correctly and clearly labelled in ink or
type setting.
N. All sub-circuits label diagram attached to the inside of the distribution board cover shall also be
marked up to indicate the electrical drawing number of the system being fed from the distribution
board.
A. The Contractor shall demonstrate from time to time, as required by the Engineer, during the execu-
tion of the Works that adequate and accurate records are being kept such as will ensure the ultimate
completeness and accuracy of the As-Built Drawings and that the records drawings are themselves
being progressively completed as the work proceeds on Site.
B. The Contractor will be responsible for the preparation of "As Built" Drawings and will supply these
bound in folios in accordance with the Engineer's instructions and to the Engineer's and Client's satis-
faction. The finished As Built Drawings are to be of a high standard.
16.11 Submittals
I. The Contractor shall submit to the Engineer Submittals, shop drawings and catalogs for equipment,
materials and other items furnished.
II. Equipment shop drawings and engineering catalogues shall be submitted for the following equipment
and systems as applicable and as specified in each section
1. Distribution Boards.
2. Lighting Fixtures and Lamps.
3. Power Sockets and outlets.
4. Air-conditioners
5. Fire alarm system
6. Fire extinguishers.
III. The contractor shall check catalogues and shop drawings for accuracy and contract requirements
prior to submittal. Shop drawings shall be stamped with the date checked and a statement indicating
that the shop drawings conform to the Specifications and Drawings. This statement shall also list all
exceptions to the Specifications and Drawings. Shop drawings not so checked and noted shall be re-
turned.
1. The Contractor shall prepare, based on the Contract drawings, the electrical installation
working drawings to a scale agreed on with the Engineer and shall issue them in accordance
with the requirements of the Contract having due regard to the time required for approval
procedures.
2. Allowance shall be deemed to have been included in the Tender for the preparation of the
working drawings and for executing any revisions required as directed by the Engineer and
for re-submitting to the Engineer for approval.
3. The Contractor may, in certain cases only, and with the Engineer's permission, complete and
detail some of the Contract drawings and use them as working drawings, but the Contractor
shall be deemed to accept full responsibility in so doing.
4. The electrical installation working drawings shall show the position, dimensions, scheme ar-
rangements and fixing of all electrical equipment. The drawings shall comprise, but are in no
way, limited to the following:
a. Dimensioned drawing of raceway systems showing layout of raceways and fittings, spa-
tial relationships to associated equipment and adjoining raceways, if any.
b. Dimensioned drawings of cable routing showing accurately layouts of cables installations
and their spatial relationship to associated equipment and details of installation.
c. Dimensioned drawings showing accurately scaled layouts of the location of the equip-
ment and their spatial relationship to associated equipment.
d. Dimensioned drawings showing layout of the exact routing of all main earth/earth
loops, details of connectors, earth pits and spatial relationship to associated equipment.
e. Dimensioned drawing of lighting system showing reflected ceiling and lighting, fire de-
tection and sound layout as applicable.
f. Dimensioned drawing of fire alarm, telephone systems and all other auxiliary systems
showing layout plans of all equipment, power supply, details of installation and spatial
relationship to associated equipment.
g. Dimensioned drawing of fire alarm, telephone raceways systems and all other auxiliary
systems showing layout of raceway and fittings spatial relationships to associated equip-
ment and adjoining raceways, if any.
h. Schematic wiring diagram
i. Specific architectural or civil engineering requirements associated with the electrical in-
stallation including substations, generator rooms, and electrical closets shall be detailed
on the drawings.
j. Checking of the Contractor's working drawings and builder's work drawings by the Engi-
neer shall not relieve the Contractor of his responsibilities for compliance with the de-
The work to be performed includes, but is not necessarily limited to, all work involved in the supply and instal-
lation of distribution boards as indicated on the drawings and as by the requirements of this Section.
A. The Contractor is responsible for the quality of all its purchased items and as such, must develop and
submit a Supplier Quality Inspection plan for review. The inspection plan shall cover those items in-
tended for shop inspection and the procedures for carrying out the same.
B. Manufacturer:
1. Main Distribution boards shall be the standard products of a manufacturer regularly engaged in
manufacture of such equipment and complying with the requirements of the listed standards and
whose products have been in satisfactory use in similar service for not less than 5 years.
2. MDBs equipment shall be assembled and tested in the workshop of the approved local agent
panel builder/ manufacturer. where any equipment needs to be assembled at site, prior Engi-
neers approval is required.
3. Before placing any DB (S), it shall be insured that the physical sizes of equipment, when installed
shall not infringe any clearance required by the concerned local authorities.
16.13 Samples
A. Samples of wires, cables, conduits, boxes, switches, sockets, pushbuttons, and other items shall be
submitted for approval before their acceptance for installation. Catalogue may be submitted in place
of samples, but they should give complete description and specification of materials.
B. Catalogue of major items such as switchgear, transformers, main distribution boards, main and sub
distribution boards, lighting fittings, etc., shall be also submitted for approval before any of these
items are ordered. The Engineer reserves the right to reject any material that he may consider inferior
or unsuitable for any reasons.
C. Further protection of cables and conduits shall be given as instructed by the Engineer.
A. Contractor is responsible for the quality of all its purchased items and as such, must develop and sub-
mit a Supplier Quality inspection plan for review by the Engineer.
B. Manufacturer: All components shall be the standard products of a manufacturer regularly engaged in
manufacture of components of types, sizes required and complying with the requirements of the
listed standards and whose products have been in satisfactory use in similar service for not less than
5 years.
C. Codes and Standards:
Comply with requirements of the following codes and standards, except as herein modified.
A. BSI - British Standards Institution.
B. BS 7671 Requirements for electrical installation.
C. IEE Wiring Regulations.
D. IEC - International Electro Technical Commission. IEC 60364 Electrical installation in buildings.
16.15 Installation
A. Any work not installed according to the Drawings and this Section shall be subject to change as di-
rected by the Engineer. No extra compensation will be allowed for making these changes.
B. Electrical equipment shall be protected at all times against mechanical injury or damage by water.
Electrical equipment shall not be stored outdoors. Electrical equipment shall be stored in dry perma-
nent shelters. Electrical equipment shall not be installed in its permanent location until structures are
weathertight. If any apparatus has been subject to possible injury by water, it shall be thoroughly
dried out and tested as directed by the Engineer or shall be replaced at no additional cost at the Engi-
neer's discretion.
C. Equipment that has been damaged shall be replaced or repaired by the equipment manufacturer, at
the Engineer's discretion.
D. Contractor shall repaint any damage to factory applied paint finish using touch-up paint furnished by
the equipment manufacturer.
A. Inspections and tests of materials, equipment, or any part thereof and workmanship shall, if required
by the Engineer, be carried out in the presence of the Engineer, his representatives, or his appointed
inspectors at any stage of manufacture or assembly and the Contractor shall serve adequate written
notice to the Engineer of the proposed dates and locations of such inspections and tests. Such written
notice shall be serviced to the Engineer not less than twenty-one (21) calendar days prior to the date
of such inspections and tests. The Contractor shall provide competent personnel and all apparatus, in-
struments, etc., necessary for such inspections and tests.
B. No inspections or test shall be carried out unless the contractor has in hand, approved drawings and
data of the equipment or materials to be inspected or tested.
C. The contractor shall submit for the Engineer's review, an inspection and tests schedule detailing tests
intended to be conducted at the manufacturer's works. Such schedule shall show the proposed date
and location of inspection and tests.
D. The contractor shall supply any shop or detailed drawings that may be requested by the Engineer, his
representatives or his inspectors during inspection and testing carried out in his or their presence.
E. Materials, equipment, or parts thereof, that do not meet the requirements of the Contract Docu-
ments shall be rejected, removed, replaced, revised and/or retested, whichever applies, until the final
product meets the requirements of the Contract Documents. All work performed to satisfy these re-
quirements and conditions shall be the sole responsibility of the Contractor. The presence of the Engi-
neer, his representatives or inspectors during inspections and tests shall not relieve the Contractor of
his responsibilities and obligations under the Contract Documents.
Initial maintenance: For a period of 24 months labor and parts following date when completed and placed in
operation, provide full maintenance. Correct operational faults and restore/replace defective/deteriorated
components and finishes and supply expendable materials as required for proper operations and maintenance.
16.18 Standardization
Materials and products of the same kind and nature shall be the standard product of one manufacturer and of
the same source and an assembly of several components, including enclosures, shall be the standard modular
product of the same manufacturer of such kind of equipment supported by published catalogues (in English)
giving full technical details of all components and finished product or assemblies, standards applicable and evi-
dence that the manufacturer has been involved for at least five (5) years with the professional up-to-date pro-
duction of such equipment.
16.19 Quality and Cleaning
The materials to be used as required by these specifications shall be of the best quality, brand new and of ap-
proved types, obtained from approved manufacturers. Also, all materials shall be thoroughly cleaned of all dirt,
grease, dust or other foreign matter and shall be free from damage or defects.
16.20 Equipment
A. All manufactured items shall be in strict accordance with the specification and free from imperfections
and defects which affect their appearance, or which may impair their durability and service ability.
B. If the equipment is manufactured under license, the Contractor shall submit a written assurance of the
license (the principal manufacturer) for the design and quality of the equipment produced by the li-
censee. This assurance should be submitted along with the submittals without which submittals will
not be considered.
C. All materials, equipment and components shall be brand new bearing stamped ratings as required, the
best of their respective kind, from reputed manufacturers and shall be suitable for prolonged and trou-
ble-free service under the climatic and other service conditions. When the Engineer will consider it
needed, he may require from the Contractor to supply and install equipment identical to those already
installed at no additional cost or compensation of any nature for the Contractor.
D. Should any equipment or material be subjected to possible damage by water, it shall be dried out thor-
oughly and put through an approved special dielectric test as directed, or otherwise repaired.
E. Equipment or material found defective, damaged by water or otherwise, during storage, installation, or
test, or failing any test, shall be replaced or repaired by the Contractor in a manner subject to the ap-
proval of the Engineer.
For each type of led lighting fixtures Contractor shall submit the following details:
1. Catalogue illustrations of luminaire proposed for each specified application.
2. Installation requirements.
3. Photometric curves and is lux diagrams for each luminaire with indication of minimum light output ra-
tio.
4. Luminaires shall be completely self-contained, unless otherwise specified, and include all control
switch, reflectors and diffusers, as required.
5. All Luminaires shall be completely including all control switch, reflectors and diffusers, as required &
must be full- package assembled in the manufacturer factory not somewhere else
6. Luminaires shall be recessed, surface-mounted or suspended as indicated on the drawings, by code
reference and identified in luminaire schedule and data sheets.
7. All diffusers shall be of the light stabilized and non-discoloring type.
8. The design, construction and finish of all luminaires shall be entirely adequate for operation in the
ambient conditions and at the supply characteristics specification. All luminaires shall be designed and
installed to permit easy revamping.
9. All luminaires shall be suitable for connection to rigid conduit, and/or flexible circular sheathed cable.
10. All weather-proof luminaires shall be fully suitable for outdoor use and shall not deteriorate after ex-
tended use in the ambient site conditions state.
11. Ingress protection for indoor use shall be IP20 for the dry places, IP 44 for wet, IP66 for the operation
theaters and high sterilization area.
12. Ingress protection for outdoor lighting shall be IP65, otherwise as specified in the drawings and/or
BoQ.
1200 mm length
A. Connect electrical power supply conductors to equipment conductors in accordance with equipment
manufacturer's written instructions and wiring diagrams. Wherever possible, mate and match conduc-
tors of electrical connections for proper interface between electrical power supplies and installed
equipment.
B. Coordinate installation of electrical connections for equipment with equipment installation work.
C. Prepare cables and wires by cutting and stripping, jacket armor and insulation properly to ensure uni-
form and neat appearance where cables and wires are terminated. Brass cable glands shall be used to
terminate armored cables.
D. Trim cables and wires as short as practicable and arrange routing to facilitate inspection, testing, and
maintenance.
E. Provide PVC-coated conduit and fittings were indicated for highly corrosive atmospheres.
F. Provide liquid-tight flexible conduit and flexible wiring for connection of All electrical equipment
where subject to movement and vibration and also where subjected to one or more of the following
conditions:
1. Exterior location.
2. Moist or humid atmosphere where condensate can be expected to accumulate.
3. Corrosive atmosphere.
4. Subjected to water spray.
5. Subjected to dripping oil, grease, or water.
6. Install disconnect switch, controllers, control stations and control devices as indicated.
7. Modify equipment control wiring with terminal block jumpers as indicated.
8. Provide interconnecting cables, conduits between devices and equipment as indicated.
G. Every connection between conductors and between a conductor and equipment shall provide durable
electrical continuity and adequate mechanical strength.
H. Where a connection is made in an enclosure the enclosure shall provide adequate mechanical protec-
tion against relevant external influences.
I. Every termination and joint in a live conductor or a PEN conductor shall be made within one of the
following or a combination thereof:
1. A suitable accessory complying with the appropriate British Standard.
2. An equipment enclosure complying with the appropriate British Standard.
3. A suitable enclosure of material complying with the relevant glow wire test requirements of BS
6458.
4. An enclosure formed or completed with building material considered to be non- combustible
when tested to BS 476 Part4.
5. An enclosure formed or completed by part of the building structure, having the ignitability char-
acteristics ‘P’ as specified in BS 476 Part 5.
6. Cores of sheathed cables from which the sheath has been removed and non- sheathed cables at
the termination of conduit, ducting or trunking shall be enclosed as required by Regulation 526-
03-02.
7. Except for the following, every connection and joint shall be accessible for inspection, testing and
maintenance.
1. All wires and cables, except where otherwise stated are to have a soft copper core, refined and
tinned, with an electric conductivity of not less than 98%. The core shall be insulated with rubber with
braid for 600 volley service.
2. Samples of cabling and wiring proposed by the contractor, are to be submitted prior to commence-
ment of the work. These must comply with the requirements of the I.E.E, BS and IEC standards to en-
sure a constant voltage in every part of the building.
3. All wires are to be standard [for lighting and power, the neutral wire shall be different in color from
the phase wires].
4. All wires shall be run through conduits and shall be continuous between outlets and boxes. At least
20cm of wire to be left outside the outlet for fixture connection.
5. Where wire size is shown on drawings or specified, it shall be the same size throughout the circuit.
6. Wiring inside panel boards shall be neat and well arranged, using appropriate lugs for termination and
connection of conductors.
7. Joints in the cables or wires are not allowed to be made inside conduits.
8. Wires are to be fixed to boards with an appliance ensuring perfect electrical contact, to the approval
of the Engineer.
9. When drawing wires through conduits, no lubricant is permitted.
10. Cable shoes have to be used for wires of 6 sq. mm. or above.
11. All boxes and distribution boards have to be carefully cleaned from plaster and other foreign material
before drawing any electrical wires or cables.
12. Colours of the cables should be as follows:
Single phase circuits:
Brown for the phase
Black for the neutral
Green & Yellow or White for the earth
Blue for direct [switch Wires].
3 Phase circuits:
Brown, Yellow & Blue for the three phase.
Black for the neutral
Green & Yellow or White for the earth
13. The work to be performed includes, but is not necessarily limited to, all work involved with the supply
and installation of wires and cables and the associated connectors and terminal boards used in electri-
cal power distribution systems.
14. The types of wires and cables specified in this section include the following:
1. Power cables (Insulated & Sheathed)
2. Single Core PVC insulated and sheathed 600/1000V cables.
3. Single core XLPE insulated PVC sheathed (600/1000V) cables.
4. Multicore PVC cables (600/1000V) non-armored cables.
5. Multicore PVC/SWA/PVC cables (600/1000V).
6. Multicore XLPE/PVC (600/1000V).
7. Small power and lighting cables (Insulated)
8. Single core PVC insulated cables (450/750V).
15. The Contractor is responsible for the quality of all purchased items and as such must develop and sub-
mit a supplier Quality Inspection Plan for review.
16. Manufacturer: Cables and wires shall be the products of a manufacturer regularly engaged in manu-
facture of cables and wires of types and sizes required and complying with the requirements of the
The work covered by this specification comprises all materials, installation, labour, services, and all equipment
and materials necessary to install, operate, test, and commission, including, but not limited to, the undermen-
tioned items:
Main fire alarm control panel.
Power supply and standby batteries with charger.
Ionization smoke detectors, heat detectors.
Manual call points.
Remote indication lamps.
Sounders.
Ancillary services.
Siting of control equipment, sounders, visual alarm, detectors and manual call points.
Cabling and wiring.
A. The Contractor shall be responsible for the quality of all its purchased items and as such, must develop
and submit a supplier quality inspection plan for review. The inspection plan shall cover those items in-
tended for shop inspection and the procedures for carrying out same.
B. Manufacturer: Fire alarm and detection system shall be the standard products of a manufacturer regu-
larly engaged in manufacture of fire alarm and detection system of type and sizes required and comply-
ing with the requirements of the listed standards and whose products have been in satisfactory use in
similar service for not less than 5 years and shall be installed by a specialist.
C. Codes and Standards: Comply with the requirements of the following codes and standards, except as
herein modified:
BSI - British Standard Institution:
BS 5445 Components of automatic fire detectors system.
BS 5446 Components of automatic fire alarm systems for residential purposes.
BS 5839 Fire Detection and Alarm Systems for Buildings.
BS 7671 Requirements for Electrical Installations.
The Contractor’s engineer shall prepare a Health and Safety Plan and shall include all matters related to con-
struction site health and safety. Responsibility and liabilities lie with the HS Officer and the Contractor.
The Contractor shall be responsible for the safety of all workmen and other persons entering the Works and
shall, at his own expense (where not otherwise stated) take all measures necessary to ensure their safety.
Provision of proper safety and emergency regulations include fire, gas (if any) and electric shock prevention,
stretchers and first aid boxes, together with rescue facilities generally, for each place of working.
Notices written in relevant languages (Arabic and English) shall be erected at points likely to be used by the
public and warning the public of the existence of the Works. These notices shall be in addition to any statutory
requirements.
Personal protective equipment shall be available and used by the personnel including: safety helmet, eye pro-
tection, ear protection, hand protection, foot protection, harnesses and belts. In addition, all scaffolds must be
secure and strong enough to handle the weight of the workers and equipment with a considerable margin of
safety that takes into account the load of wind. All scaffolds much be equipped with strong guardrails.
Provision and maintenance of suitable lighting to provide adequate illumination of the Works with appropriate
spares and standby equipment.
Provision of good and safe access to any part of the Works.
The contractor shall take all necessary steps to provide safety for project workers, the persons residing near
the project, to the property of the public or others from the project activities arising as a consequence of his
methods of operation.
The Contractor shall comply with all Safety Legislations and its Subsidiary Legislations, Regulations which are in
force in the Country and any amendments or re-enactments.
The Contractor shall not permit any person to do anything not in accordance with the generally accepted
principles of safe and sound practices. The Contractor shall ensure safe environment on site at all times.
The Contractor shall ensure that necessary and sufficient precautions are taken by his workmen when
safety provisions are used.
17.3 Barricading
The Contractor shall provide and maintain guards, fences or barriers around excavations, pits or other similar
potential places of danger to prevent accidents. The barricade should be at least 1.1m high and strong enough
to withstand a lateral point load of 50 kg.
The Contractor shall display warning signs of sizes 900 mm x 600 mm at a minimum of 4 points around the pe-
riphery of the site where the construction activities are located in near the residential area, roads, at locations
where there is a chance of children can come to work site and where trespassing is likely to occur. Such signs
shall have the words "DANGER - KEEP OUT OF SITE".
Fuels shall be stored in a room/ enclosed space, the room/ enclosed space shall have impervious platform and
berm along the periphery of the storage area to contain spills of the fuels.
The Contractor shall employ only qualified operators for the machinery to be used on Site. All the machinery
shall be locked when they are parked to avoid unauthorized operation of the machinery.
At least two first aid kits shall be kept at site for attending the emergency treatment to the victims of accidents
or chemical poisoning or excessive exposure to toxic substances. The first aid kit shall include a leaflet of stan-
dard First-Aid procedure in addition to the medicines and medical tools. At least one staff member who has
undergone First Aid training should be posted at site.
The Contractor shall establish Fire Safety, Emergency and Rescue arrangements to contain fire and take neces-
sary action during emergency. The contractor should place fire extinguishers at the work site, materials stor-
age area and at site accommodation. The contractor should keep minimum 6 fire extinguishers within the
workplace. Coordination with the Civil Defense is necessary to ensure prompt response in the event of fire.
In addition, dispatchable fire exit means must be provided during operations on the site. At any point of imple-
mentation, multiple exit means must be available. These include temporary stairways and/or dispatchable lad-
ders for workers to use as exit means.
All electrical l equip should be listed and labeled, free from hazards, and used in the proper manner.
The electrician should be protected from electrical shocks and provided necessary safety equipment.
All temporary electrical installations in the site should be verified regularly to ensure that all the leaks in the
wires are rectified/ faulty wires are replaced. The contractor should also ensure that all electric joints are leak
proof.
The Contractor shall provide and maintain suitable personal protective equipment for all workmen employed
on the site to provide protection against falling objects and harmful substances which can cause injury. The
Personal protective equipment shall include boots, hand gloves, helmet and goggles. The Contractor shall
record the issuance of all equipment to his workmen and kept in the site office.
17.11 Housekeeping
The Contractor shall provide safe working environment by keeping the site neat and tidy, and free from debris.
All materials shall be stacked safely. All accesses shall be kept free from hazards and debris.
Housekeeping shall be carried out in such a manner and at such times so as not to cause any inconvenience to
either the adjoining owners, occupiers or the public. Debris shall be wetted to minimize the risk of dust. Con-
tainers for debris, rubbish and other wastes shall be provided at the designated places.