0% found this document useful (0 votes)
5 views

121

This document is a checklist for inspecting block work installations in a construction project, detailing compliance with approved submittals, construction drawings, and technical specifications. It includes specific criteria for wall masonry works on different floors, with sections for remarks and signatures from responsible personnel. The form must be submitted at least 24 hours before the actual inspection.

Uploaded by

alnoel tordilla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

121

This document is a checklist for inspecting block work installations in a construction project, detailing compliance with approved submittals, construction drawings, and technical specifications. It includes specific criteria for wall masonry works on different floors, with sections for remarks and signatures from responsible personnel. The form must be submitted at least 24 hours before the actual inspection.

Uploaded by

alnoel tordilla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

F-QM-AR-001

BLOCK WORKS PROJECT:


LOCATION:
INSTALLATION DATE PREPARED: CONTROL NO.:

CHECKLIST
AREA/FLOOR LEVEL: INSPECTION DATE/TIME:
GRIDLINE/AXES:
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND
TECHNICAL SPECIFICATIONS : :
Complied
PARTICULARS REMARKS
Y N

A. WALL MASONRY WORKS


1 First Floor
a. CHB unit size and strength complying, with no cracks  
b. Layout based on approved plan  
c. Reinforcing bars size, specification, splicing & spacing checked  
d. All cells fully grouted according to approved mix  
e. Stiffener columns and lintel beams checked if required  
f. Vertical & horizontal alignment checked  
f. Joint fillers properly installed were required  
g. Plaster mix and plumbness checked  
h. Proper location of embedded pipes, conduits, sleeves & elec'l  
boxes checked
i. Checked for wavy surface; bush hammered & replastered  

2 Second & Suceeding Floors


a. CHB unit size and strength complying, with no cracks  
b. Layout & coursing as per plan  
c. Vertical & horizontal alignment checked  
d. Reinforcing bars size, specification, splicing & spacing checked  
e. All cells fully grouted according to approved mix  
f. Joint fillers properly installed were required  
g. Plaster mix and plumbness checked  
h. Proper location of embedded pipes, conduits, sleeves and boxes  
checked
i. Checked for wavy surface; bush hammered & replastered  
j. Random dye penetrant tested for welded joints  
k. For verge angles securely and tightly fits precast panels  

REMARKS

NOTE : This form must be submitted to The OPERATIONS, duly accomplished and signed by the corresponding Contractor's
Personnel-in-Charge at least 24 hours before actual INSPECTION.
PREPARED BY: INSPECTED BY: APPROVED BY:

( SubCon QA/QC Engr.) (NIA Project-in-Charge) (NIA Architect/Designer)


DISTRIBUTION : Subcon NIA Document Control
Revision No. :000 (Nov.22, 2024)

You might also like