Deliverable List Rev. 01

The document outlines the project details for the Al-Sonober & Al-Keena N.G. Feeding Pipeline, including the client, engineer, and contractor information. It provides a comprehensive list of project deliverables, their submission statuses, and due dates. The document is structured into various sections covering project management, HSE, QA/QC, engineering, and cathodic protection, detailing specific reports and plans required for the project.

Uploaded by

Mohab Mohamed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views5 pages

Deliverable List Rev. 01

The document outlines the project details for the Al-Sonober & Al-Keena N.G. Feeding Pipeline, including the client, engineer, and contractor information. It provides a comprehensive list of project deliverables, their submission statuses, and due dates. The document is structured into various sections covering project management, HSE, QA/QC, engineering, and cathodic protection, detailing specific reports and plans required for the project.

Uploaded by

Mohab Mohamed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Project

Al-Sonober & Al-Keena N.G. Feeding Pipeline


Name
Client FAJR Project AMMAN - JORDAN
Co. Location
Document
2819-660-SNB-101 Rev. Date Page
No.
Document Project Deliverable
01 01/03/2017 1
Description List

Project : Al-Sonober & Al-Kena N.G. Feeding Pipeline


Project No. : 2819 – 660
Client : Fajr Jordanian Egyptian Company
Engineer : Tractebel Engie
Contractor : Egypt Gas

28 Feb. 17 01 For Approval Sherif Rifai


5 Feb. 17 00 Approved Sherif Rifai
Date Rev. Status Prepared Approved
Item
Document Description Document No. Rev. 0 Submission Date
No.
1 Project Management
1.1 Project Deliverables List 2819 - 660 - SNB - 101 Submitted
1.2 Organization Chart 2819 - 660 - SNB - 102 Submitted
1.3 Project Execution Plan 2819 - 660 - SNB - 103 Submitted
1.4 Baseline Schedule 2819 - 660 - SNB - 104 Submitted
1.5 Equipment List 2819 - 660 - SNB - 105 30-Apr-17
1.6 Monthly Progress Report 2819 - 660 - SNB - 106 Submitted
1.7 Weekly Progress Report 2819 - 660 - SNB - 107 Submitted
1.8 Daily Progress Report 2819 - 660 - SNB - 108 Submitted
2 HSE
2.1 Qualitative and Quantitative Risk Analysis Study 2819 - 660 - SNB - 201 Submitted
2.2 HSE Policy and Master Plan 2819 - 660 - SNB - 202 Submitted
2.3 Emergency Preparedness Plan 2819 - 660 - SNB - 203 Submitted
2.4 Personal Protective Equipment Matrix 2819 - 660 - SNB - 204 5-Mar-17
2.5 Waste Management Plan 2819 - 660 - SNB - 205 Submitted
2.6 Job Risk Analysis 2819 - 660 - SNB - 206 Submitted
2.7 Safety Aspects Control Measure 2819 - 660 - SNB - 207 Submitted
3 QA/ QC
3.1 Quality Plan 2819 - 660 - SNB - 301 10-Mar-17
3.2 ITP (Mechanical) 2819 - 660 - SNB - 302 10-Mar-17
3.3 ITP (Civil & Electrical) 2819 - 660 - SNB - 303 15-Apr-17
3.4 Material Receiving, Handling and Storage Procedure 2819 - 660 - SNB - 304 10-Mar-17
3.5 Welding Consumables Handling and Storage Procedure 2819 - 660 - SNB - 305 10-Mar-17
3.6 VT Procedure 2819 - 660 - SNB - 306 10-Mar-17
3.7 PT Procedure 2819 - 660 - SNB - 307 10-Mar-17
3.8 UT Procedure 2819 - 660 - SNB - 308 10-Mar-17
3.9 MT Procedure 2819 - 660 - SNB - 309 10-Mar-17
3.10 RT Procedure 2819 - 660 - SNB - 310 10-Mar-17
3.11 WPS (1) 2819 - 660 - SNB - 311 10-Mar-17
3.12 WPS (2) 2819 - 660 - SNB - 312 10-Mar-17
3.13 WPS (3) 2819 - 660 - SNB - 313 10-Mar-17
3.14 Welding Repair Procedure 2819 - 660 - SNB - 314 10-Mar-17
3.15 Welding Book 2819 - 660 - SNB - 315 10-Mar-17
3.16 Mechanical Data Book 2819 - 660 - SNB - 316 10-Mar-17
4 Engineering (Mechanical)
4.1 P & ID 2819 - 660 - SNB - 401 Submitted
4.2 Hydraulic Analysis Report 2819 - 660 - SNB - 402 2-Mar-17
4.3 Design Basis 2819 - 660 - SNB - 403 2-Mar-17
4.4 HAZOP Study 2819 - 660 - SNB - 404 26-Mar-17
4.5 HAZID Study 2819 - 660 - SNB - 405 26-Mar-17
4.6 HAZOP Action Plan 2819 - 660 - SNB - 406 27-Mar-17
4.7 Wall Thickness Calculation Report 2819 - 660 - SNB - 407 2-Mar-17
4.8 Stress Analysis Report 2819 - 660 - SNB - 408 20-Mar-17
4.9 Pipeline Class 2819 - 660 - SNB - 409 5-Mar-17
4.10 Pipeline MTO 2819 - 660 - SNB - 410 Submitted
4.11 Pipeline Alignment Sheet 2819 - 660 - SNB - 411 7-Mar-17
4.12 Piping Class 2819 - 660 - SNB - 412 5-Mar-17
4.13 Piping MTO 2819 - 660 - SNB - 413 Submitted
4.14 Piping General Arrangement 2819 - 660 - SNB - 414 30-Mar-17
4.15 Hot Tap Valve Room Detail 2819 - 660 - SNB - 415 10-Apr-17
4.16 Piping Isometrics 2819 - 660 - SNB - 416 10-Apr-17
4.17 HDD Design 2819 - 660 - SNB - 417
4.18 Typical Trench Detail 2819 - 660 - SNB - 418 Submitted
4.19 Typical Crossing existing Pipeline Detail 2819 - 660 - SNB - 419 9-Mar-17
4.20 Typical Crossing with High Tension Cable 2819 - 660 - SNB - 420 9-Mar-17
4.21 Pipe Support Stress Analysis 2819 - 660 - SNB - 421 15-Mar-17
4.22 Pipe Support Model Detail 2819 - 660 - SNB - 422 15-Mar-17
4.23 Pipe Support Design 2819 - 660 - SNB - 423 15-Mar-17
4.24 Data Sheet for Line Pipe 2819 - 660 - SNB - 424 Submitted
4.25 Data Sheet for Hot Bend 2819 - 660 - SNB - 425 Submitted
Item
Document Description Document No. Rev. 0 Submission Date
No.
4.26 Data Sheet for Cold Bend 2819 - 660 - SNB - 426 15-Mar-17
4.27 Data Sheet for Stud Bolts 2819 - 660 - SNB - 427 Submitted
4.28 Data Sheet for Insulation Joints 2819 - 660 - SNB - 428 Submitted
4.29 Data Sheet for Fittings 2819 - 660 - SNB - 429 Submitted
4.30 Data Sheet for Flanges 2819 - 660 - SNB - 430 Submitted
4.31 Data Sheet for Gaskets 2819 - 660 - SNB - 431 Submitted
4.32 Data Sheet for GOV - Valve 2819 - 660 - SNB - 432 Submitted
4.33 Data Sheet for Ball Valve 2819 - 660 - SNB - 433 Submitted
4.34 Data Sheet for Globe Valve 2819 - 660 - SNB - 434 Submitted
4.35 Data Sheet for Hot Tap 2819 - 660 - SNB - 435 Submitted
4.36 Data Sheet for Heat Shrinkable Sleeve 2819 - 660 - SNB - 436 Submitted
4.37 Data Sheet for Paints 2819 - 660 - SNB - 437 Submitted
4.38 Material Requisition for GOV - Valves 2819 - 660 - SNB - 438 5-Mar-17
4.39 Material Requisition for Ball Valves 2819 - 660 - SNB - 439 Submitted
4.40 Material Requisition for Isolating Joints 2819 - 660 - SNB - 440 1-Mar-17
4.41 Material Requisition for Fittings 2819 - 660 - SNB - 441 Submitted
4.42 Material Requisition for Flanges 2819 - 660 - SNB - 442 1-Mar-17
4.43 Material Requisition for Gaskets 2819 - 660 - SNB - 443 1-Mar-17
4.44 Material Requisition for Pipes 2819 - 660 - SNB - 444 Submitted
4.45 Material Requisition for Hot Bends 2819 - 660 - SNB - 445 1-Mar-17
4.46 Material Requisition for Globe Valve 2819 - 660 - SNB - 446 Submitted
5 Engineering (Civil)
5.1 Hot Tap Valve Room Foundation Details 2819 - 660 - SNB - 501 30-Mar-17
5.2 PRMS Foundation Details 2819 - 660 - SNB - 502 Upon Receiving Elester Information
5.3 Heater Foundation Details 2819 - 660 - SNB - 503 Upon Receiving Elester Information
5.4 Pipe & Valve Support Foundation Details 2819 - 660 - SNB - 504 30-Mar-17
5.5 Control Shelter Foundation Details 2819 - 660 - SNB - 505 Upon Receiving Elester Information
5.6 Calculation Sheet for Control Shelter 2819 - 660 - SNB - 506 Upon Receiving Elester Information
5.7 Road & Fence Foundation Details 2819 - 660 - SNB - 507 30-Mar-17
5.8 Lighting Poles Foundation Details 2819 - 660 - SNB - 508 30-Mar-17
5.9 Lightening Poles Foundation Details 2819 - 660 - SNB - 509 30-Mar-17
5.10 Cable Trench Detail 2819 - 660 - SNB - 510 30-Mar-17
5.11 Warning Tape Procedure 2819 - 660 - SNB - 511 30-Mar-17
5.12 Pipeline Marker Design 2819 - 660 - SNB - 512 30-Mar-17
5.13 PRMS Layout 2819 - 660 - SNB - 513 Submitted
5.14 Offtake Layout 2819 - 660 - SNB - 514 Submitted
6 Engineering (Architecture)
6.1 Road & Fence Layout 2819 - 660 - SNB - 601 15-Mar-17
6.2 Fence Details 2819 - 660 - SNB - 602 15-Mar-17
6.3 Gates Details 2819 - 660 - SNB - 603 15-Mar-17
7 Engineering (Instrumentation)
7.1 Data Sheet for Pressure Indicator 2819 - 660 - SNB - 701 Submitted
7.2 Instrument Mechanical Hook Up Drawing 2819 - 660 - SNB - 702 Upon Receiving Elester Information
7.3 Instrument Index 2819 - 660 - SNB - 703 Upon Receiving Elester Information
7.4 Instrument Cable Routing 2819 - 660 - SNB - 704 Upon Receiving Elester Information
7.5 Material Requisition for Pressure Indicator 2819 - 660 - SNB - 705 5-Mar-17
8 Engineering (Electrical)
8.1 Earthing Layout 2819 - 660 - SNB - 801 30-Mar-17
8.2 Earthing Calculation Report 2819 - 660 - SNB - 802 30-Mar-17
8.3 Lighting and Sockets Layout 2819 - 660 - SNB - 803 30-Mar-17
8.4 Lighting Calculation Report 2819 - 660 - SNB - 804 30-Mar-17
8.5 Lightning Protection Layout 2819 - 660 - SNB - 805 30-Mar-17
8.6 Lightning Protection Calculation Report 2819 - 660 - SNB - 806 30-Mar-17
8.7 Electrical Cable Sizing 2819 - 660 - SNB - 807 30-Mar-17
8.8 Electrical Cable Schedule 2819 - 660 - SNB - 808 30-Mar-17
8.9 Electrical Cables Routing Layout 2819 - 660 - SNB - 809 30-Mar-17
8.10 SLD 2819 - 660 - SNB - 810 30-Mar-17
8.11 Data Sheet for Distribution Panel 2819 - 660 - SNB - 811 30-Mar-17
8.12 Data Sheet for Cables 2819 - 660 - SNB - 812 30-Mar-17
8.13 Data Sheet for Lighting 2819 - 660 - SNB - 813 30-Mar-17
Item
Document Description Document No. Rev. 0 Submission Date
No.
8.14 Data Sheet for Earthing & Lightning 2819 - 660 - SNB - 814 30-Mar-17
8.15 Hazardous Area Classification and Schedule 2819 - 660 - SNB - 815 30-Mar-17
8.16 Electrical Installation Detail 2819 - 660 - SNB - 816 30-Mar-17
8.17 Distribution Panel Material Requisition 2819 - 660 - SNB - 817 30-Mar-17
8.18 Cable Material Requisition 2819 - 660 - SNB - 818 30-Mar-17
8.19 Lighting Fixtures Material Requisition 2819 - 660 - SNB - 819 30-Mar-17
8.20 Lightning Protection and Earthing Material Requisition 2819 - 660 - SNB - 820 30-Mar-17
8.21 Sockets and Switches Material Requisition 2819 - 660 - SNB - 821 30-Mar-17
9 Cathodic Protection
9.1 Cathodic Protection Design Report 2819 - 660 - SNB - 901 Upon Approval of Evaluation Report
9.2 Cathodic Protection Drawings 2819 - 660 - SNB - 902 Upon Approval of Evaluation Report
9.3 Cathodic Protection Materials Data Sheet 2819 - 660 - SNB - 903 Upon Approval of Evaluation Report
9.4 Cathodic Protection Materials Requisition 2819 - 660 - SNB - 904 Upon Approval of Evaluation Report
9.5 Cathodic Protection Evaluation Report 2819 - 660 - SNB - 905 Submitted
9.6 Soil Resistivity Report 2819 - 660 - SNB - 906 Submitted
10 Procurement
10.1 Material Supply Status Report 2819 - 660 - SNB - 1001 7-Mar-17
10.2 Materials Receiving Report 2819 - 660 - SNB - 1002 7-Mar-17
10.3 Shipping Documents 2819 - 660 - SNB - 1003 30-Apr-17
10.4 Technical Evaluation Report for Ball Valve 2819 - 660 - SNB - 1004 30-Apr-17
10.5 Technical Evaluation Report for GOV - Valve 2819 - 660 - SNB - 1005 30-Apr-17
10.6 Technical Evaluation Report for Isolating Joint 2819 - 660 - SNB - 1006 30-Apr-17
10.7 Technical Evaluation Report for Pipes 2819 - 660 - SNB - 1007 30-Apr-17
10.8 Technical Evaluation Report for Fittings 2819 - 660 - SNB - 1008 30-Apr-17
10.9 Technical Evaluation Report for Flanges 2819 - 660 - SNB - 1009 30-Apr-17
10.10 Technical Evaluation Report for Gaskets 2819 - 660 - SNB - 1010 30-Apr-17
10.11 Technical Evaluation Report for Plug Valve 2819 - 660 - SNB - 1011 30-Apr-17
10.12 Technical Evaluation Report for Hot Tap 2819 - 660 - SNB - 1012 30-Apr-17
10.13 Technical Evaluation Report for Distribution Panel 2819 - 660 - SNB - 1013 30-Apr-17
10.14 Technical Evaluation Report for Cables 2819 - 660 - SNB - 1014 30-Apr-17
10.15 Technical Evaluation Report for Lightning Fixtures 2819 - 660 - SNB - 1015 30-Apr-17
10.16 Technical Evaluation Report for Lightning Protection & Earthing 2819 - 660 - SNB - 1016 30-Apr-17
10.17 Technical Evaluation Report for Sockets and Switches 2819 - 660 - SNB - 1017 30-Apr-17
10.18 Technical Evaluation Report for Pressure Guages 2819 - 660 - SNB - 1018 30-Apr-17
10.19 Technical Evaluation Report for Cathodic Protection Materials 2819 - 660 - SNB - 1019 30-Apr-17
10.2 Vendor Document for Pipeline 2819 - 660 - SNB - 1020 30-Apr-17
10.21 Vendor Document for piping 2819 - 660 - SNB - 1021 30-Apr-17
10.22 Vendor Document for Valves 2819 - 660 - SNB - 1022 30-Apr-17
10.23 Vendor Document Distribution Panel 2819 - 660 - SNB - 1023 30-Apr-17
10.24 Vendor Document for Pressure Guages 2819 - 660 - SNB - 1024 30-Apr-17
11 Pipeline Construction
11.1 Pipeline Construction Procedure 2819 - 660 - SNB - 1101 4-Mar-17
11.2 Method Statement for Installation 2819 - 660 - SNB - 1102 6-Mar-17
11.3 Hot Tapping Procedure 2819 - 660 - SNB - 1103 7-Mar-17
11.4 Field Joint Coating Procedure 2819 - 660 - SNB - 1104 Submitted
11.5 Painting Procedure 2819 - 660 - SNB - 1105 Submitted
11.6 Hydrostatic Testing Procedure for Pipeline 2819 - 660 - SNB - 1106 21-Mar-17
11.7 Hydrostatic Testing Procedure for Above Ground Piping 2819 - 660 - SNB - 1107 21-Mar-17
11.8 Gas Leak Testing and Purging Procedure 2819 - 660 - SNB - 1108 21-Mar-17
11.9 Precommissioning & Commissioning Procedue 2819 - 660 - SNB - 1109 21-Mar-17
11.10 Operating and Maintenance Manuals 2819 - 660 - SNB - 1110 Upon commissioning
12 Civil Construction
12.1 Tech. Offer for Geotech. Study 2819 - 660 - SNB - 1201 Submitted
12.2 Final Land Survey 2819 - 660 - SNB - 1202 Submitted
12.3 Geotechnical Study Bore Holes Coordinates 2819 - 660 - SNB - 1203 Submitted
12.4 Geotechnical Study Report 2819 - 660 - SNB - 1204 28-Feb-17
Numbering Legend

Symbol /
Designation
Number
2819 - 660 Contract Number
NUQ Project: Nuqul Group
100's Project Management
200's HSE
300's QA / QC
400's Engineering: Mechanical
500's Engineering: Civil
600's Engineering: Architeture
700's Engineering: Electrical
800's Engineering: Instrumentation
900's Cathodic Protection
1000's Procuement
1100's Pipeline Construction
1200's Civil Construction