Arc Flash Study
Arc Flash Study
COM
We cannot de-energize the circuit for the above activities in the case of critical process
Generator
industries. The plant may suffer from various losses if we do so.
Motor
Solar
inverters
Starter
Transformer
Transmission
Line
Power System
Studies
Arc Flash
Study
Load Flow
Study
Relay
Coordination
Study
Short Circuit
Study
Traction Power
System
Uncategorized
1. Could you guarantee that your workplace will not have an electrical accident including
Arc-Flash in the future?
2. Could you avoid the maintenance activities of switchgear at energized conditions by
affording the various loss of offline maintenance?
3. Is your system voltage level lesser than 208V?
If your answer is NO for any one of the above questions, then say absolute YES to Arc Flash
Study.
An Arc Flash study must be completed before a worker is exposed to an electrical hazard.
An Arc Flash risk assessment should be reviewed every five years, or any time
modifications such as changes in the load or protective equipment are made to the facility
that can affect the outcome of the study.
Who Can Perform Arc Flash Studies?
Arc Flash studies should be performed by experienced and qualified electrical engineers
knowledgeable in power system engineering, IEEE 1584, NFPA 70E, short circuit, device
coordination, and Arc Flash studies.
The study’s final results are used to select Arc-rated PPE and clothing with a sufficient arc
rating and establish what is known as an Arc Flash boundary. The PPE category method
relies on tables in NFPA 70E that assign PPE categories based on the equipment type and
specific parameters.
Following steps to calculate the incident energy and define Arc-Flash boundaries as
recommended by IEEE1584:2018.
Step 1: Collect the system and installation data
A qualified Engineer needs to visit the plant and collect the required data to perform the
Arc Flash study.
One-line diagrams must be developed or updated to show the current configuration and
modes of operation for the power system.
Step 4: Determine typical gap and enclosure size based on system voltages and classes
of equipment
Actual gap measurements from the installed equipment may be used if available.
If not, we need to follow the values provided in the standard.
Arc-Flash protection is typically based on the incident energy level on the person’s head
and torso at the working distance and not the incident energy on the hands or arms.
Typical working distances can be found in IEEE 1584:2018 based on the class of
equipment.
The total arcing current at a given location is calculated based on the total bolted fault
current available at that location.
The calculated arcing current is lower than the bolted fault current due to arc impedance.
The arc duration is defined as the time it takes the upstream energizing source of arcing
current to stop providing current or energy to the arc fault.
Typically, the clearing time of overcurrent protective devices depends on the magnitude
and/or direction of the arc current passing through their current sensing equipment
(current transformers, relays, etc.).
Incident energy calculations should be performed at each of the switchgear, panels, and
DBsthat are defined to determine the highest magnitude incident energy or “worst-case”
condition.
The Arc-Flash boundary is the distance from a prospective Arc Flash where the incident
energy is 5.0 J/cm2 (1.2 cal/cm2).
WHAT’S NEXT!?
After calculating the incident energy, the Arc flash boundaries for all the equipment. The
study’s final results are used to select Arc-rated PPE and clothing with a sufficient arc rating
and establish an Arc Flash boundary.
And it is recommended to paste the Arc Flash labels on the front side of every panel to
create awareness among the workers.
It is advisable to mark Arc Flash boundary and limited approach boundary in front of every
panel as per IEEE1584 & NFPA 70E 2021 recommendations.
Arc Flash Labels
And it is recommended to paste the Arc Flash labels on the front side of every panel to
create awareness among the workers.
The labels have the details of Incident energy level, Working distance, Limited approach
boundary, Restricted approach boundary, Arc Flash boundary, and recommended Arc Rated
PPE.
Arc Flash Mitigation Hierarchy Triangle
This triangle shows the best technics to get rid of Arc Flash hazards.
Ajithkumar Sivaprakasam
– Power Systems Studies Engineer
CONNECT WITH US