502012004【b】sun (3 10) k g03 组串说明书 ver2.0 deye 12.5a 1
502012004【b】sun (3 10) k g03 组串说明书 ver2.0 deye 12.5a 1
User Manual
About This Manual
The manual mainly describes the product informa�on, guidelines for installa�on, opera�on and
maintenance. The manual cannot include complete informa�on about the photovoltaic (PV) system.
Family load
Applica�on of inverter in photovoltaic power system
1. Introduc�on
1.1 Appearance Introduc�on
On-grid Inverter can convert solar panel DC power into AC power which can directly input to
the grid. Its appearance is shown below.These models contain SUN-3K-G03, SUN-4K-G03,
SUN-5K-G03, SUN-6K-G03, SUN-7K-G03, SUN-8K-G03, SUN-10K-G03.
The following is collec�vely referred to as “inverter”.
RS232 485
ON
M16X1.5
OFF RS485
M12X1.5
DC SWITCH limiter
DC AC Normal Alarm
DC AC Normal Alarm
User
manual
Warning:
Warning symbol indicates important safety instruc�ons, which if not correctly
followed, could result in serious injury or death.
Shock Hazard:
Cau�on, risk of electric shock symbol indicates important safety instruc�ons,
which if not correctly followed, could result in electric shock.
Safety Hint:
Note symbol indicates important safety instruc�ons, which if not correctly
followed, could result in some damage or the destruc�on of the inverter.
Warning:
Electrical installa�on of the inverter must conform to the safety opera�on rules
of the country or local area.
Warning:
Inverter adopts non-isolated topology structure, hence must insure DC input and
AC output are electrical isolated before opera�ng the inverter.
Strictly prohibit grounding the posi�ve and nega�ve poles of the PV string.
Otherwise it will damage the inverter.
Shock Hazard:
Prohibit disassembling inverter case, there exis�ng shock hazard, which may
cause serious injury or death, please ask qualified person to repair.
Shock Hazard:
When PV module is exposed to sunlight, the output will generate DC voltage.
Prohibit touching to avoid shock hazard.
Shock Hazard:
While disconnect the input and output of the inverter for maintenance, please
waits for at least 5 mins un�l the inverter discharge the remnant electricity.
1. Inverter should be installed and maintained by qualified person under local standard
regula�ons.
2. Must disconnect the AC side first, then disconnect DC side while doing installa�on and
maintenance, a�er that, please wait at least 5 mins to avoid ge�ng shocked.
3. Local temperature of the inverter may exceed 60 ℃ while under opera�ng.Do not touch
to avoid ge�ng injured.
4. All electrical installa�on must be in accord with local electrical standards, and a�er
obtaining the permission of the local power supply department, the professionals can
connect the inverter to the grid.
5. Please take appropriate an�-sta�c measure.
6. Please install where children can not touch.
7. When star�ng the inverters, first close the circuit breaker at the grid side, then close the
DC side; when closing the inverters, first disconnect the circuit breaker at the AC side, then
disconnect the DC side.
8. Don’t insert or remove AC and DC terminals when the inverter is in normal opera�on.
9. The DC input voltage of the inverter must not exceed the maximum value of the model.
3. Opera�on Interface
3.1 Interface View
DC AC Normal Alarm
Safety Hint:
Do not place or store any items next to the inverter.
1 5
5 00mm
Anchoring
Moun�ng bracket
Inverter
2. Ensure that the posi�on of the installa�on holes on the wall is in accordance with the
moun�ng plate, and the moun�ng rack is horizontally placed.
3. Hang the inverter to the top of the moun�ng rack and then use the M4 screw in the
accessory to lock inverter heat sink to the hanging plate, to ensure that the inverter will not
move.
Safety Hint:
Please don’t connect PV array posi�ve or nega�ve pole to the ground, it could
cause serious damages to the inverter.
Safety Hint:
Before connec�on, please make sure the polarity of the output voltage of PV
array matches the “DC+” and “DC-” symbols.
Safety Hint:
Before connec�ng inverter, please make sure the PV array open circuit voltage is
within the 1000V of the inverter.
Safety Hint:
Please use approved DC cable for PV system.
Cross section
Cable type
Range Recommended value
Industry generic PV cable 4.0~6.0
4.0(12AWG)
(model: PV1-F) (12~10AWG)
c) Insert the contact pin to the top part of the connector and screw up the cap nut to the top
part of the connector. (as shown in picture 5.5).
Warning:
Sunlight shines on the panel will generate voltage, high voltage in series may
cause danger to life. Therefore, before connec�ng the DC input line, the solar
panel needs to be blocked by the opaque material and the DC switch should
be 'OFF', otherwise, the high voltage of the inverter may lead to life-
threatening condi�ons.
Warning:
Prohibit using a single circuit breaker for mul�ple inverters, prohibit the
connec�on of load between inverter circuit breakers.
Model Cable CSA Cable outer dia AWG Breaker Max cable length
Step 1: Remove the cable sealing ring and sleeve in sequence from the AC connector.
Step 2: Use strippers to strip the protec�ve sheath and insula�on layer of the AC cable to the
right length, as shown in Picture 5.8.
Step 3: Insert the cable (L1, L2, L3, NPE) into the sealing sleeve.
Warning:
Be careful to dis�nguish the L1, L2,L3,N and PE of the AC cables.
Step 4: Use the hexagon screwdriver, loosen the bolts of the socket in turn, and insert each
cable core into the corresponding jack, and set each screw. The connec�on hole of AC
connec�on terminal labeling is shown in Picture 5.9.
Pic 5.9 AC Connector Hole Pa�ern
Warning:
Inverter has built-in leakage current detec�on circuit, If an external leakage
current protec�on device is connected, its opera�ng current must be greater
than 300 mA or higher, otherwise inverter may not work properly.
5.4 Max. over current protec�on device
In order to protect the inverter AC connec�on, it is recommended to install a circuit breaker to
prevent overcurrent. See table 5.3 below.
Phone
GPRS
PC
a). The maximum open voltage of each set of photovoltaic modules shall not exceed
1000Vdc under any condi�ons.
b). Each input of the inverter be�er use the same type of photovoltaic module in series.
c). Total output power of pv shall not exceed the maximum input power of inverter, each
photovoltaic modules shall not exceed the rated power of each channel.
When start up the three phase string inverter, should fellow below steps
2. Turn on the DC switch of the photovoltaic module, and if the panel provides sufficient
star�ng voltage and power, the inverter will start.
3. When the ac voltage and DC voltage are normal, the inverter start-up is readyto begin.
The inverter will first check the internal parameters and the grid parameters, while the liquid
crystal will show that the inverter is self-checking.
4. If the parameter is within acceptable range, the inverter will generate energy.
NORMAL indicator light is on.
2. Wait for 30 seconds, turn off the DC switch (if any), or simply disconnect the DC input
connector. The inverter will close the LCD and all LED within two minutes.
7 Zero export func�on via SUN limiter
The inverter has external zero export func�on. This func�on is op�onal. It can collect counter-
current power to control the output power of the inverter, so that the power of inverter and
load can be offset, and the excess power will not be fed back to the grid. If you purchase the
inverter with zero export func�on, an external zero export device ( SUN limiter or energy meter)
will be included in the package which is necessary for the func�on.The SUN limiter shows as
Pic 7.1.You can see corresponding line mark next to the green interface. The green terminals
on the le� are the interface of three-phase AC line (L1, L2, L3) and N Line (N), and the the right
are the interface between three sets of current sensor and one set of control terminals. SUN limiter
will collect voltage and current from these interfaces and send control signals to the inverter.
When you are reading this, we believe that you have completed the connec�on according to the
requirements of chapter 5, if you has been running your inverter , and you want to use the limiter
func�on, please turn off AC and DC switch of the inverter, and wait for 5 minutes un�l the inverter
completely discharged.In order to make it easier for you to use the limiter func�on, we have
specifically given the wiring diagram, as shown in Picture 7.2, the yellow/green/red live line
(L1,L2,L3) connected to the u�lity grid live line (U/V/W), blue line means the neutral line.
We recommend installing an AC switch between the inverter outlet and the u�lity grid, the specs
of the AC switchis determined by the load capacity. The AC switch we recommend to connect to
the inverter output refer to Table 5.2.
L1(L)
L1(K)
Solar panels
L2(L)
L2(K)
L3(L)
L3(K)
Limiter
L1
DC AC Normal Alarm
L2
L3
N
Control signal V
DC AC Normal Alarm
N
Distribution Box
Control signal
Load
The SUN limiter will measure the voltage and current of three phases separately, and this manual
only introduces the installa�on steps of one phase, the other two phases are the same. The
specific installa�on steps are as follows:
(1) Connect SUN limiter to the grid. Connected to the grid is to measure the voltage of grid. Before
connect to the grid, please turn off the switch to avoid the risk of electric shock. Choose one wire
from the bo�om of the three-phase DC switch. (any phase of U,V,W) to connect with L1 terminal,
then �ghten the line with a screwdriver.
(2) Connect SUN limiter to clamp senor. Clamp senor can measure the current of the AC side, it
should be connected to the front side of the load (domes�c appliance ect.) to achieve this func�on.
Only when the SUN limiter collects the voltage and current of the same phase can it judge the
power of the phase. So the clamp senor should be connected to the same phase as the before.
Open the side buckle of the clamp senor, then clamp the senor to the AC line on the DC switch,
the arrow direc�on on the senor should towards that of the load. The clamp senor has two lines
(shown as below), and the white line corresponds to K terminal, black line corresponds to L
terminal. Connect the white line to the L1(L) and L1(K) terminal refer to the line mark of the SUN
limiter and �ghten the line with screwdriver. This is the whole installa�on process of one phase.
Load
Pic 7.3 Clamp Senor Pic 7.4 Clamp Senor internal arrow
(3) A�er you finish the installa�on in process 1 and 2, connect the N line (N) to the N terminal
of the limiter and �ghten the line.
(4) Connect the control line. There are two numbers 1 and 2 on the interface of SUN limiter, and
the same on the waterproof terminal of the inverter. Twist the waterproof terminal and connect
the red line to number 1 and black line to number 2 shown as the picture. A�er that connect
the terminal to the interface of the SUN limiter. The other side of the line should be connected to
the control terminal.
6.If set up successfully, you can return to the menu interface, and display the LCD to [home page]
by press the [up down] bu�on. If it displayed as [u�lity power], the limiter func�on se�ngs will
be completed. Shown as picture 7.10.
*Fun GFDI OFF Utility Power:
Limiter ON << 20W
* This item is not avaiable for some FW verison
Pic 7.10 Limiter func�on turn on
7. [u�lity power] showing posi�ve means grid power is consuming energy, and there is no
backflow. If [u�lity power] shows nega�ve, which means there’s excess PV energy flows to
grid or current transformer arrow direc�on is in wrong direc�on. Please read more on
chapter 7.9.
8. A�er properly connec�on is done, wait for inverter star�ng. If the power of the PV array
meets the current power consump�on, the inverter will maintain a certain output to
counteract the power of the grid without backflow .
Inverter Grid
Solar Panel array
DC AC Normal Alarm
N N
L3 L3
L2 L2
L1 L1
meter
RS485 Communication
VCC_5V 2 3 485_A
GND 1 4 485_B
Family load
Pic 7.12 Connec�on diagram of CHINT meter
Warning:
Ensuring grid input cables connect 1/4/7/10 port of energy meter, and inverter
AC output cables connect 3/6/9/10 port of energy meter when connec�ng.
7.4.2 Use of zero-export func�on
When the connec�on is completed, the following steps should be refered to use this func�on:
1. Turn on the AC switch.
2. Turn on the DC switch, wai�ng for the inverter's LCD is turned on.
3. Press Enter bu�on on the LCD panel in the main interface into the menu op�ons, select
[parameter se�ng] to enter setup submenu, and then select [running parameters] as shown
in picture 7.13, at this �me please input the default password 1234 through pressing the
bu�on [up down, enter], enter the opera�on parameter se�ng interface, shown as
picture 7.14.
4. Operate the bu�on [up down], move se�ng cursor to energy meter and press the bu�on
[enter]. At this �me you can turn on or turn off the energy meter by choosing [up down]
bu�on, please press [enter] bu�on to confirm when se�ng done.
5. Move the cursor to [OK], press [enter] to save the se�ngs and exit the running
parameters page, otherwise the se�ngs are invalid.
6. If set up successfully, you can return to the menu interface, and display the LCD to [home
page] by press the [up down] bu�on. If it displays [meter power XXW], the zero-export
func�on se�ng is completed. Shown as picture 7.15.
Meter Power:
20W
Pic 7.15 Zero-export func�on via energy meter turn on
7. Meter power XXW shows posi�ve means grid is supplying the load, and no power fed into
grid. if meter power shows nega�ve, it means PV energy is being sold to grid or energy meter
wiring connce�on has problem.
8. A�er properly connec�on is done, wait for inverter star�ng. If the power of the PV array
meets the current power consump�on, the inverter will keep a certain output to counteract
the power of the grid without backflow .
7.5 Notes while using zero export func�on
For your safety and the opera�on of limiter func�on of the inverter, we put forward the
following sugges�ons and precau�ons:
Warning:
Under zero export mode we strongly recommend that the two PV arrays are
formed by the same number of PV panels of the same size, which will make the
inverter more responsive to limit the power.
Safety Hint:
While the u�lity power is nega�ve and inverter has no output power, that means
the orienta�on of the current sensor is wrong, please turn off the inverter and
change orienta�on of the current sensor.
(when using SUN limiter, the arrow of current sensor points to the load)
UA and UB Device
informa�on
Load PV VA
Comm param
LoadEp
From the ini�al interface, you can check PV power, PV voltage, grid voltage, inverter ID, model
and other infoma�on.
Power: 0W Power: 0W
State: Standby State: Com.Error
Pic 8.2 The ini�al interface
Press UP or Down, you can check inverter DC voltage, DC current, AC voltage, AC current and
inverter temperature.
21 - 05 - 2020 Meter
15 : 57 : 08 Power: 0W
Pic 8.7 Time Pic 8.8 Meter power
Total : 0.00KWh
Pic 8.9 Electrical energy
Total : 0.00KWh
Pic 8.10 Electrical energy
LoadEp: Daily consump�on;
LoadEp: 0.00KWh Total: Total energy consump�on.
Total : 0.00KWh
Pic 8.11 Load consump�on
E-Total : 134KWh
Pic 8.12 PV genera�on
ID:0000000012
Ver0201 Ver1970
Pic 8.13 Device informa�on
8.2.2 Fault Record
It can keep Eight fault records in the menu including �me, customer can deal with it depends
on the error code.
8.2.4 PV VA se�ng
Protect Param
Comm. Param <<
Pic 8.17 Submenus of the parameter setup
8.3 System param se�ng
System Param includes �me set, language set, display set and factory reset.
Note:
Password required-- only for access-authorized engineer. Un-authorized access
may avoid the warranty. The ini�al password is 1234.
PassWord
ReactiveP 0% <<
Pic 8.25
Pic 8.29
WindTurbine
Pic 8.30
Those parameters is used for setup wind
WindTurbine << trubine MPPT curve.
OK Cancel
OK <<
Cancel
Pic 8.31 WindTurbine set
Note:
Engineer Only.
We will set the param depends on the safety requirements, so customers don't
need to reset it. The password is same as 8.4 Running param
PassWord
00 INMETRO 00 EN50438
00 EN50549 << 00 IEC61727 <<
00 CUSTOM
OK Cancel <<
Note:
Engineer only.
AC OverVoltage << AC LowVoltage <<
265.0V 185.0V
Please set the proper grid parameters according to the requirements of your current country's
grid regula�ons.If you are not clear about it, please consult your installer.
Address: 16 <<
BaudRate: 9600
Pic 8.34 Com. Param
Warning:
When the device is running, the local temperature is too high and the touch can
cause burns. Turn off the inverter and wait for it cooling, then you can clean and
maintain.
Warning:
No solvent, abrasive materials or corrosive materials can be used for cleaning
any parts of the inverter.
F03 DC leakage current fault Hardly appear the code. Never ever happened so far
F04 Ground fault GFDI Check the solar panel output connec�on.
F05 Read the memory error Failure in reading memory (EEPROM). Restart the inverter if the
fault s�ll exists, contact your installer or Deye service.
F06 Write the memory error Failure in wri�ng memory (EEPROM). Restart the inverter if the
fault s�ll exists, contact your installer or Deye service.
F07 GFDI blown fuse Hardly appear the code. Never ever happened so far
F08 GFDI grounding touch failure Hardly appear the code. Never ever happened so far
F09 IGBT damaged by excessive drop Hardly appear the code. Never ever happened so far.
voltage
F11 AC main contactor errors Hardly appear the code. Never ever happened so far
F12 AC auxiliary contactor errors Hardly appear the code. Never ever happened so far
F14 DC firmware over current Hardly appear the code. Never ever happened so far.
F17 Three phase current, Hardly appear the code. Never ever happened so far.
over-current fault
F19 All hardware failure synthesis Hardly appear the code. Never ever happened so far.
Error code Description Ongrid - Three Phase
1. Check whether solar panel output current is within the
allowed range.
F20 DC over current fault of the 2. Check DC current sensor and its detec�on circuit.
hardware 3. Check if the inverter FW version is suitable for the hardware.
4. Restart the inverter, if the error s�ll exists, please contact your
installer or Deye service.
F21 DC leakage flow fault Hardly appear the code. Never ever happened so far.
F22 Crash stop (if there is a stop Contact your installer for help.
bu�on)
F25 DC feedback fault Hardly appear the code. Never ever happened so far
F27 DC end insula�on error Hardly appear the code. Never ever happened so far
F28 Inverter 1 DC high fault Hardly appear the code. Never ever happened so far
F29 AC load switch failure Hardly appear the code. Never ever happened so far
1. At least one Relay can't be closed. Check relays and its driver
F31 signal. (Old inverter not have relays detec�on func�on)
Dc boost so� start 2. Restart the inverter, if the fault s�ll exists, contact your
installer or Deye service.
F32 Inverter 2 dc high fault Hardly appear the code. Never ever happened so far
F33 AC over current Hardly appear the code. Never ever happened so far
F34 AC current over load Hardly appear the code. Never ever happened so far
F37 AC three-phase voltage unbalance Hardly appear the code. Never ever happened so far.
failure
F38 AC three-phase current unbalance Hardly appear the code. Never ever happened so far.
failure
F40 DC over current Hardly appear the code. Never ever happened so far
F46 AC Line U,V low voltage Check the AC voltage protec�on se�ng.
F49 U phase grid current DC Hardly appear the code. Never ever happened so far.
component over current
F50 V phase grid current DC Hardly appear the code. Never ever happened so far.
component over current
F51 W phase grid current DC Hardly appear the code. Never ever happened so far.
component over current
F52 AC inductor A, phase current Hardly appear the code. Never ever happened so far.
DC current high
F53 AC inductor B, phase current Hardly appear the code. Never ever happened so far.
DC current high
F54 AC inductor C, phase current Hardly appear the code. Never ever happened so far.
DC current high
F58 AC grid U over current Hardly appear the code. Never ever happened so far.
F59 AC grid V over current Hardly appear the code. Never ever happened so far.
F60 AC grid W over current Hardly appear the code. Never ever happened so far.
F61 Reactor A phase over current Hardly appear the code. Never ever happened so far.
F62 Reactor B phase over current Hardly appear the code. Never ever happened so far.
F63 Reactor C phase over current Hardly appear the code. Never ever happened so far.
Note:
If your string inverter has any of the fault informa�on shown in Table 10-1,and
when you reset the machine and s�ll don’t solve the problem,please contact our
distributor and provide the below details: