02-ITP

The document outlines the Inspection and Test Plan (ITP) for the installation of fan coil units at the RAK Mangrove Hotel project. It details responsibilities, frequency of checks, acceptance criteria, and required documentation for various activities including material submittals, method statements, and inspections. The plan is structured to ensure compliance with project specifications and includes control points for oversight by various stakeholders.

Uploaded by

Muthu Krishnan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

02-ITP

The document outlines the Inspection and Test Plan (ITP) for the installation of fan coil units at the RAK Mangrove Hotel project. It details responsibilities, frequency of checks, acceptance criteria, and required documentation for various activities including material submittals, method statements, and inspections. The plan is structured to ensure compliance with project specifications and includes control points for oversight by various stakeholders.

Uploaded by

Muthu Krishnan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION AND TEST PLAN FOR INSTALLATION OF FAN COIL UNIT

Project RAK MANGROVE HOTEL RAS AL KHAIMAH ITP Ref No. SEC/RAK/CC/MEP/MSS/ITP/116

Client SECURE ENGINEER Revision No. 1

Employer ACCURATE Date ###

Consultant ATKINS

Contractor CHIEF CONTRACTING LLC

MEP Contractor ELECTRON ELECTROMECHANICAL

DESCRIPTION OF RESPONSIBLE FREQUENCY REFERENCE CONTROL POINT


S.N. ACCEPTANCE CRITERIA VERIFYING DOCUMENT REMARKS
ACTIVITY PERSON OF CHECK DOCUMENTS
ELCTRON CHIEF ATKINS

A APPROVAL / PERMITS/ PRELIMINARIES

Project / Site
Engineer , QAQC Prior to Start Material submittal to have
A.1 Material Submittal Project Speciation Project Speciation H R/S A
Engineer Activity minimum status of code B

Project / Site
Engineer , QAQC Prior to Start Method statemen to have
A.2 Method statement Project Speciation Project Speciation H R/S A
Engineer Activity minimum status of code B

Project / Site
Engineer , QAQC Prior to Start Project Spec & IFC Drawing to have minimum status
A.3 Shop Drawing IFC Drawing H R/S A
Engineer Activity drawing of code B

B MATERIAL INSPECTION ON DELIVERY

Project / Site
Engineer , QAQC For Each Project specification &
B1 Materials inspection Approved Material Approved Material Submittal H R/S A
Engineer Delivery Material submittal

C Civil Clearance

Project / Site
Engineer , QAQC Prior to Start Project Spec & IFC
C1 Civil Clearance Engineer Approved Civil WIR Civil WIR and checklist H R/S A
Activity drawing

D WORK AND TESTING COMMISSIONING INSPECTION

Project / Site
Engineer , QAQC During Shop drawing & Material As per specIfied project
D.1 Installation Inspection Engineer WIR and checklist H R/S A
Installation Approval requirement

Project / Site
Testing and
Engineer , QAQC During Shop drawing & Material As per specIfied project
D.2 commissioning WIR and checklist H R/S A
Engineer Installation Approval requirement
Inspection

C+B19:L27ONTROL POINTS : A-Approval H-Hold W-Witness DS- Submittal R-Rview SR- Surveillance