PM_Report_Schedule_B_VCT
PM_Report_Schedule_B_VCT
SR#:
Date:
PM Report Schedule B
PM Frequency: months
PRELIMINARY TASKS
Last PM Inspection
Verify last PM Inspection
PM Schedule Sys B
Initial Procedures
Check Temperature and Humidity
Room Temperature Humidity Pass/Fail Comments/Follow-up
Scan room Temp &
Humidity
System Options
Task Pass/Fail Comments/Follow-up
Nemoto Injector Inspection
Collimator Inspection
Task Pass/Fail Comments/Follow-up
Aperture and Filter Positions and Operation
Protective Window & Opening,
Inspection
NGPDU
Task Pass/Fail Comments/Follow-up
Finalization
System Scanning Test
QA Phantom
Task Location Gantry Serial #
Serial #
General Tasks
Task Select Comments/Follow-up
X-ray On Indicators
Scan Control Pushbuttons Test
Completed
Update Site Log
Complete PM Paper Work
Complete Customer Reports
Characters Remaining:
Tools Used:
Description Serial Number Bar Code Cal Due Date
Add Tool
Remove Tool
GE Representative: