Full Text 01
Full Text 01
Fredrik Gransell
2016
by
Fredrik Gransell
Email:
[email protected]
Abstract
The mining industry contains many factors with a high degree of uncertainty.
Therefore, there is a need for decision analysis. The production drill process is an
initial process in underground mining, thus it is important that the most appropriate
drilling method is used for specific mining operations. The current study provides
examples of important variables that can be used in the decision analysis of the given
decision problem. Drill methods included in the decision analysis are hydraulic top-
hammer, pneumatic, and hydraulic down-the-hole hammers. Monte Carlo simulations
are used as decision analysis method and tornado diagrams are used to determine how
large effect the variables have on the results given the variation in each variable. The
Monte Carlo simulations are based on a hypothetical case. It is challenging to analyze
only the drilling process because the results of this process influence other processes
in the mine. Thus, a comprehensive decision model that includes several processes of
the mining operation would be of value to the decision maker. The presented
calculations focus on cost per ton in terms of direct and indirect costs of drilling.
Examples of safety and environmental criteria are given, for a possible extension of
the analysis.
Contents
1 Introduction............................................................................................................. 1
1.1 Background .................................................................................................................. 1
1.2 How the drilling method is typically determined ......................................................... 2
1.3 Problem definition ........................................................................................................ 3
1.4 Delimitations and simplifications ................................................................................. 3
1.5 Related work................................................................................................................. 4
1.6 Disposition.................................................................................................................... 4
2 Introduction to decision analysis ........................................................................... 5
2.1 Decision analysis under uncertainty ............................................................................. 5
2.2 Multi-criteria decision analysis..................................................................................... 6
3 Introduction to underground mining .................................................................... 6
4 Production drilling methods in underground mining ......................................... 7
4.1 Top–hammer drilling .................................................................................................... 8
4.2 Pneumatic DTH-hammer drilling ................................................................................. 8
4.3 Hydraulic DTH-hammer drilling .................................................................................. 8
5 The importance of straight holes ........................................................................... 9
5.1 Dilution ....................................................................................................................... 10
5.2 Ore Recovery .............................................................................................................. 11
5.3 Calculating the influence of deviation on dilution and ore recovery .......................... 11
5.4 Calculating the influence of deviation on the success of the blast .............................. 11
6 Monte Carlo simulations and variables used in the current study................... 11
6.1 Variables used in the simulation ................................................................................. 14
6.1.1 Price of the ore ................................................................................................ 14
6.1.2 The grade of the ore ........................................................................................ 14
6.1.3 Deviation ......................................................................................................... 15
6.1.4 How drill hole deviation influences dilution and ore recovery factors ........... 15
6.1.5 How drill hole deviation influences the success of the blast factor ................. 15
6.1.6 The rate of penetration (ROP)......................................................................... 16
6.1.7 The life span of the percussion unit ................................................................. 16
6.1.8 The life span of the DTH-hammer ................................................................... 16
6.1.9 The life span of drill bits ................................................................................. 16
6.1.10 The life span of drill rods ................................................................................ 16
6.1.11 The cost and use of energy .............................................................................. 17
6.1.12 The cost of operators ....................................................................................... 17
6.1.13 The cost of handling dilution ........................................................................... 17
6.1.14 Drilled meters/ton ........................................................................................... 18
6.2 Tornado diagram ........................................................................................................ 18
7 Examples of Monte Carlo simulations ................................................................ 19
7.1 Calculations ................................................................................................................ 21
7.2 Direct costs of drilling ................................................................................................ 21
7.3 Dilution cost ............................................................................................................... 21
7.4 Cost of ore loss ........................................................................................................... 22
7.5 Cost of an unsuccessful blast ...................................................................................... 22
7.6 To calculate the total cost/ton ..................................................................................... 22
7.7 Input values ................................................................................................................ 22
8 Analysis of the results ........................................................................................... 27
8.1 Sensitivity analysis ..................................................................................................... 31
9 The choice of drilling method as a multi-criteria decision problem................. 35
9.1 Safety criterion ........................................................................................................... 36
9.2 Environmental criterion .............................................................................................. 36
9.3 Multi-criteria decision analysis under uncertainty ...................................................... 37
10 Discussion .............................................................................................................. 38
10.1 Further recommendations ........................................................................................... 39
11 Conclusion ............................................................................................................. 40
References ................................................................................................................... 42
Decision analysis
1.1 Background
Mining is one of the oldest professions. Most modern technology used in mining comes
from centuries of experience through traditional trial and error. However, in modern
mining, it is not always possible to simply try a mining method or technology. The
process has to be determined prior to the mining process. The book Underground
mining methods: Engineering fundamentals and international case studies (W. A.
Hustrulid 2001) provides some examples of this determination.
In cases of a new mine that is under construction, or an existing mine that is reaching
a new ore body to be extracted, a specific drill method will require a specific mine
design. The decision can be complex, mainly because of uncertainties that are often
involved in mining. It is also challenging to use data (acquired through experience) from
another mine as a reference because rock conditions and the shapes of ore bodies are
unique for each mine.
A decision regarding the mining technique to be used must be made prior to mining
in many cases. Different software, based on mathematical models, can be used to
simulate the mining process. This is a cost efficient method. A common simulation
method within decision analysis is the Monte Carlo simulation. However, an extensive
search for documentation regarding the use of simulation methods for decision making
in the mining industry shows limited results, suggesting that they are rarely used.
Several decision analysis methods exist that could be useful for various decisions within
the mining industry, just as in other industries. Though, there appears to be a lack of
knowledge within the mining industry as to how to use these methods for decision
analysis problems as they are rarely used. Therefore, general studies demonstrating how
some of these decision analysis methods can be used for a particular problem within the
industry are valuable. Such a study is presented in the current thesis.
Hustrulid (2001, p 266-267) presents a case study describing the cost distribution of
the underground process at the El Saldado mine. The ore is mined with the siblevel open
stoping mining method. This is also the mining method that the current decision analysis
is based on. In Figure 1, a cost distribution is presented for different underground mining
processes. The figure shows that the total cost of the drill and the blast process is 17%
of the total cost of the underground production process.
1
Cost Distribution
35% 32%
30% 28%
25%
20% 17%
15% 12%
11%
10%
5%
0%
Development Extraction Infrastructure Drill and blast Transport
Figure 1. Cost distribution of the underground mining process at the El Saldado mine,
using sublevel open stoping (after Hustrulid 2001).
The cost distribution between the drill and blast process is unclear. Because drilling
occurs in the beginning of the mining process, it is likely to greatly impact the
subsequent mining processes. The cost distribution seen in the El Saldado mine case
study is focused on the direct cost of a process, for example, it only includes the cost of
drill consumables. However, the result of the drill process can significantly influence
the cost of the subsequent processes. Such indirect costs are included in the decision
analysis model described of the current thesis. Therefore, it is important that the most
appropriate drilling method is used depending on the particular circumstances of the
mine.
Although the decision problem will be different for each mine, the decision analysis
process can be carried out in a similarly structured manner. The decision is often
whether the hydraulic top-hammer, the pneumatic Down The Hole (DTH) -hammer, or
the hydraulic DTH-hammer would be the most appropriate drilling method for
production drilling in underground mining.
2
of the operator, etc. Therefore, it is interesting to analyze how drill hole deviation
influences the overall cost of drilling and, indirectly, the length of the hole to some
degree.
3
1.5 Related work
Limited results arise from an search for related work, where simulations are used to
simulate a decision problem within the mining industry. There has been some research
in mining, or closely related fields, to simulate a mining process or a decision problem
with the help of decision analysis and computer software. Examples include the doctoral
thesis Rock Quarrying prediction models and blasting safety (Olsen 2009, p 120-138),
where a blast result is simulated with Monte Carlo simulations. The research article
Planning Tunnel construction using Markov Chain Monte Carlo (Vargas, Koppe, Pérez,
Juan, 2015, p 1-9) simulates a process in underground mining (tunneling) with Monte
Carlo simulations. One of the leading explosive suppliers and consultancies for the
mining industry (Orica) published the book Tunneling in rock by drilling and blasting
which explains how shock waves during the blast process can be simulated with Monte
Carlo simulations (Spathis & Gupta 2012, p 59-67). Simulations have also been used in
mining to predict rock falls, etc. This can be seen in the book, Practical rock engineer
(Hoek 2006, p 3-6). The mining company Boliden, based in Sweden, has also carried
out the research, namely Monte Carlo reliability simulation of underground drill rig
(Lundberg, AL-Chalabi & Hosseini 2016, p 1-6), to simulate the reliability of a drill rig
to improve productivity. I did not find research related to decision analysis or
simulations for production drilling for underground mining in terms of cost,
environmental, or safety perspectives.
1.6 Disposition
The thesis is divided into 11 chapters.
Chapter 1 – Introduction
In this chapter, the background to the thesis is explained. The definition of the decision
problem and the aim of the study are presented. The delimitations and simplifications
are explained and a brief summary presented.
4
hole deviation, and how it influences the dilution, ore recovery, and the overall success
of the blast.
Chapter 6 – Monte Carlo simulations and variables used in the current study
In this chapter, the Monte Carlo simulation method is explained. The chapter contains
sections for each variable included in the calculations, described in terms of how to
gather data and reflect uncertainty with the use of probability distributions.
Chapter 10 – Discussion
In this chapter, the decision analysis is discussed and recommendations as to how to
further improve the decision model are presented. Reflections are also provided, such
as how such decision models can be introduced to and implemented in the mining
industry.
Chapter 11 – Conclusion
In this chapter, a conclusion is given, including an analysis of how successfully the aim
of the study was met.
5
reasons. Factors that a decision maker cannot control create a decision under
uncertainty. To handle uncertainties and make a decision model representative of the
actual decision problem, graphical representations of decision analysis are often used.
Examples of these include influence diagrams and decision trees (Clemen & Reilly,
2001, p 146). These graphical representations represent alternatives available to a
decision maker given a particular decision problem.
6
The book also highlights the importance of having the proper infrastructure for rock
flow and sufficient ventilation. This is achieved through vertical shafts connecting each
level of the mine. Rock is normally dumped into a shaft with a Laud haul dumper (LHD)
and then collected at a main level and transported by dumpers or trains to a hoist shaft
that brings the rock from the underground to the surface. Ventilation shafts are divided
into two categories, fresh air and exhaust air shafts.
The first step of underground production is drilling blast holes. Blast holes can have
varying lengths and dimensions, but generally, for horizontal drilling, they are between
30–50 mm in diameter and up to 5 m in length, while vertical drill holes are generally
between 64–127 mm in diameter and between 10–40 meters in length. The holes are
charged with explosives and the blast has a designed sequence between each individual
blast hole, therefore, it is important that the blast hole is in the correct position according
to the design. Once the ore has been blasted, the mucking process takes place. As
described, an LHD typically dumps the blasted rock into shafts and dumpers or trains
transport the rock to the hoist shaft. Depending on the hoist shaft, the rock often has to
be crushed into a certain fragmentation size prior to haulting. This is done with an
underground crusher. The book mentions that the typical size of the fragmentation after
the first crushing is 0–250 mm.
Once the ore has reached the surface, it is crushed into even smaller fragments with
secondary crushers and mills. Depending on the mineral being mined, different
separation processes exist to separate the mineral from the waste rock, for example,
flotation or leaching. The book notes the relationship between each process, from the
start of the production to the final product, and the importance of correct planning from
the start. In other words, it is more favourable if the correct decisions are made from the
beginning of the process.
4. The circulation fluid cleans the drill hole from drill cuttings, cools the drill bit,
and can act as a stabilizer for the hole. Generally, air or water is used as fluid.
7
4.1 Top–hammer drilling
Tatiya (2013, p 100) describes top-hammer drilling as a piston strike hitting a shank
adapter and creating a shock wave. The shock wave is transferred through the drill string
(a series of connected drill rods) to the drill bit. The drill bit transfers the energy to the
rock and the surface of the rock is crushed into drill cuttings. Drill cuttings are then
transported away from the hole by means of flushing air, supplied through the flushing
hole of the drill string. Because the drill string is rotating, together with the drill bit, new
rock is constantly being hit and penetrated. The rock drill and the drill string are
arranged on a feeding device. The feed force makes sure that the drill bit is constantly
in contact with the rock to use the impact power at the maximum level. Top-hammer
drilling is the most commonly used drilling method for underground mining due to its
relatively low cost, low energy consumption, and high productivity. However, a
disadvantage of this drilling method is increased deviation over the length of the drill
hole. Atlas Copco (2014, p 95) suggests that deviation can be between 5–10% for holes
that are 30 m in length. The reason why deviation occurs, and the importance of
minimizing deviation, is explained in chapter 5. Tatiya (2013, p 100) also explains that
there is energy loss when energy is transferred through the drill string. DTH-hammer
drilling helps alleviate these disadvantages.
8
necessary, higher accuracy than for hydraulic top-hammers. However, Thompson
(2010, p 23) shows that a hydraulic DTH-hammer can drill significantly straighter holes
than a pneumatic DTH-hammer. Based on these findings, one could argue that in
general, the hydraulic DTH-hammer has the lowest drill hole deviation, followed by the
pneumatic DTH hammer, and then the hydraulic top-hammer.
To power a 152 mm air powered DTH-hammer, roughly 570 liters/second of air is
required. When the compressed air leaves the hammer, the air expands to its original
volume. This generates large volumes of air with a velocity of 40–80 m/second. This
high velocity and volume requires a larger clearance, up to 20 times as high as in a
hydraulic DTH-hammer. Because water is a non-compressible media with no expansion
of volume, the velocity of the water is much lower (0.5–2 liter/second). This also lowers
the energy for drill cuttings which should yield longer life spans of drill rods and
hammer cases.
The disadvantage of this drilling method is the availability of drilling media. When
drilling with pneumatic DTH-hammer, it is rarely difficult to supply the hammer with
compressed air as air is easily accessible. However, it can be more challenging to
provide water to power a hydraulic DTH-hammer. Further, as described on a suppliers
website, the water needs to be relatively clean (maximum particle sizes of 50 micron
and 150 mg/l of particles). If these limits are not met, the overall life span of the hammer
can be severely reduced which will have a large impact on the overall cost and
productivity of the drilling process.
This drilling method is relatively new compared to the other drilling methods.
However, the technical brochure Water powered drilling: The water hydraulic DTH
Technology (Wassara, 2014) notes that the technology’s inventor (LKAB) is using it in
their underground mines, described as the two largest underground iron ore mines in the
world.
9
Figure 2. General drill design of sub level stoping with drill hole deviation that results
in dilution.
In this decision analysis, costs of drilling are categorized into four different costs:
direct cost of drilling, cost of dilution, cost of ore loss, and cost of an unsuccessful blast.
The deviation variable will have a great effect on all of these costs. As increased
deviation increases dilution, additional costs are allocated to handle dilution. Indirect
costs are generated when deviation causes ore loss, meaning a loss in revenue. Increased
cost is generated when deviation causes an unsuccessful blast because the stope needs
to be re-drilled and blasted again with decreased chances of retrieving all of the ore.
Deviation affects the direct cost when it is measured in cost per ton because additional
drill holes can be drilled to allow drill holes to deviate. For example, if the powder factor
(kg explosives per metric ton rock) should be 1 kg/metric ton, 1.2 kg/metric ton can
instead be used as more drill holes are drilled and tightly spaced. Therefore, the direct
cost/ton would also increase, but this is not reflected in the decision model because it is
not a common practice.
5.1 Dilution
Tatiya (2013, p 537) explains that an optimal mining system should maintain dilution
at a minimum level. While mining close to ore boundaries (holes adjacent to the HW
and FW), it is crucial that drill holes do not deviate. If drill holes deviate outside of ore
boundary, additional waste rock (green in Figure 2) is mined. This dilution continues
along the process, all the way to separation ( described in chapter 3), which means
additional operation costs and time is necessary during mucking, haulage, crushing, and
milling. It is also important in terms of safety. Damaging the hanging wall can lead to a
greater risk of additional hanging wall failure, a hazard for both the operator and the
machine. Additional operating times will also increase exposure to hazards. Reducing
operating times reduces risk. Dilution is an important factor in deciding which mining
method to use and general dilution percentages are often described for each mining
method.
Dilution is generally calculated as follows. If the drill design in Figure 2 contains
10,000 tons, but the blast result yield in 11,000 tons, then the dilution would be 10%
10
(1,000 tons), assuming the ore recovery is 100%. If the ore recovery is 95%, but the
total amount of mucked tons was 11,000, the dilution is 15.8% (1,500 tons). Dilution is
usually measured with a caving monitory system (CMS) and summarized in a
reconciliation report.
11
subsequent processes and produces uncertainties. A more feasible method for
calculating or presenting this cost is simulation. A simulation should include all
uncertainties and present the cost over an interval, covering the cost from minimum to
maximum, and a probability assigned to each of these values. A suitable method to
accomplish this is the Monte Carlo simulation method, discussed in the introduction.
The Monte Carlo simulation is described by Clemen and Reilly (2001, p 459-468)
as a useful method for decision analysis when the values of variables are unknown.
Instead of using an exact value for a variable, a probability distribution can be used.
Figure 3 provides an example of a probability distribution created in @RISK, showing
a normal probability distribution of lead ore reserves with the mean value of 3% and a
standard deviation of 0.3%. The calculations in the decision analysis are based on this
ore reserve and probability distribution.
Monte Carlo simulation uses random sampling to obtain numerical results. With the
software @Risk, the simulation can be done on a computer with a mathematical model.
A Monte Carlo simulation (The Oxford dictionary, 2016) is defined as “A technique in
which a large quantity of randomly generated numbers are studied using a probabilistic
model to find an approximate solution to a numerical problem that would be difficult to
solve by other methods”. The software used for Monte Carlo simulations in this decision
analysis is @Risk from Palisade Corporation. The software is presented on their website
(Palisade 2016).
Figure 4 is an example, unrelated to actual simulations in the current study, of a
Monte Carlo simulation created in @RISK. The simulation is based on several different
input variables with assigned probability distributions. In the table, it is possible to read
the minimum, mean, and maximum values that the simulation produced. The X-axis
displays the measured unit for the graph, such as cost ($) per ton. The Y-axis shows the
probability density based on 1,000 iterations in the simulation. The graph presents two
different simulations. As can be seen in the table, the standard deviation is higher for
simulation 2, which results in a graph shape with a greater range in the X-axis, compared
to simulation 1 with a lower standard deviation. The values at the top of the graph
explain that 50% of the iterations had a result below value 10 for simulation 1, and 50%
had a result above 10, while 100% of iterations from simulation 2 had a result above 10.
12
The same simulation can also be presented in a cumulative ascending graph as shown
in Figure 5. In the graph, the X-axis shows the same value as in the probability density
distribution in Figure 4, while the Y-axis shows the percentage of simulations that have
fallen below the X-axis value.
Comparing the values between simulation 1 and 2 in Figure 4 shows that the
maximum value of simulation 1 is lower than the minimum value of simulation 2.
Clemen and Reilly (2001, p 133-134) describes this as deterministic dominance. In this
example, the simulations describe drill cost per ton of rock, and any decision maker that
prefers a low cost would choose the alternative represented by simulation 1. Hence, if
deterministic dominance occurs, it is easier for the decision maker to determine which
alternative is of the highest value for the decision.
13
Figure 5. Results of a Monte Carlo simulation created in @Risk. Cumulative
distribution function (CDF).
14
category is proved, meaning that the ore has been closely sampled, both at the surface
and underground. The certainty of the grade of the ore in the proved category has to be
at least 90%. When production drilling takes place, it is always proved ore that is being
mined. The decision maker should consult a geologist to estimate the value of the
variable and probability distribution to reflect the uncertainty. The grade of the ore will
indirectly affect the costs of drilling because ore price is multiplied by the grade of the
ore to calculate loss in revenue.
6.1.3 Deviation
Variable deviation has already been explained in chapter 5 “The importance of straight
holes”. To determine possible values of this variable for each drilling method, drill tests
can be completed so that drill hole deviation can be measured. If the decision maker
does not have access to such drill tests, drill manufacturers can be contacted for
references and review the drills. A deviation from one reference most likely does not
equal the same deviation the decision maker is analyzing. Studies of deviation of
different drilling methods should be compared in the same project, which will be of high
value because it can give an indication of the relationship between them. Once this is
decided, probability distributions can be assigned to reflect the level of uncertainty.
6.1.4 How drill hole deviation influences dilution and ore recovery
factors
As described in section 1.4, the calculation of the influence of drill hole deviation on
dilution and ore recovery is simplified as aspects other than deviation influence it, such
as rock characteristics. For example, in competent rock, a deviated blast hole might only
damage the hanging wall in one location (causing dilution), while in a soft formation, a
deviated blast hole might cause the entire hanging wall to collapse. The decision maker
should consult with the drill and blast engineer who can calculate how drill hole
deviation influences dilution and ore recovery (section 5.3 explains this in detail).The
probability distribution of how drill hole deviation influences dilution and ore recovery
is used to show how large effect the variables have on the results given the variation in
each variable, rather than describing the uncertainty of the factor itself. It is useful to
include this variable in tornado diagrams to compare the change of value of this variable
with the variation of other variables. If the deviation-dilution factor is 0.25, a 1% drill
hole deviation results in 0.25% dilution.
6.1.5 How drill hole deviation influences the success of the blast factor
Section 5.4 described how the decision maker can calculate how drill hole deviation
influences the risk of having an unsuccessful blast. If the decision maker does not have
available data from the particular mine where the decision is relevant, references from
a similar mine can be used. A probability distribution can be used to reflect the level of
uncertainty of this variable. In this case, a pert probability distribution is used and its
minimum value set to 0 to avoid negative values in the probability distribution. The
input value of the deviation-unsuccessful blast factor used in the calculations is
presented in Table 3. This input value is based on several mine sites where I gained
experience in a career as a mining engineer. For specific drill hole lengths, with a drill
hole deviation of around 4%, the unsuccessful blast rate is about 10%. By using an
influence factor of 1.5, the drill hole deviation generates a probability of 6% (4*1.5)
that an unsuccessful blast will occur, while the remaining probability (10-6=4%) arises
from other factors described in section 1.4. This variable differs depending on the drill
and blast design for each mine, therefore the decision maker needs estimate the
influence factor for each particular case.
15
6.1.6 The rate of penetration (ROP)
The ROP is important for the simulation for several reasons. It affects the amount of
energy used, the cost per meter of percussive units, the life span of the drill bits and drill
rods, and the total operating cost. To determine the rate of penetration, references from
the suppliers should be used. Rock properties have a great influence on the rate of
penetration. Aalizad and Rashidenejad (2015, p 715-716) describe that rock properties
that affect the ROP are density, rock quality designation (RQD), uni-axial compressive
strength, Brazilian tensile strength, porosity, Mohs hardness, Young modulus, and P-
wave velocity. Geologists should be consulted for the decision analysis to gain
knowledge concerning rock properties. However, rock properties differ from stope to
stope, so there is still uncertainty regarding the rate of penetration. Rock and geological
conditions are generally described as uncontrollable parameters, though other
parameters (such as the drilling method) also affect the rate of penetration. Probability
distributions can be assigned to the ROP to reflect the level of uncertainty.
16
6.1.11 The cost and use of energy
The cost of energy ($/kWh) should be forecasted by the decision maker as it varies with
time and location. Similar to forecasting metal prices, the decision maker can get help
from companies specialized in these forecasts. Alternatively, mines can agree on a fixed
price of power consumption for a certain time period. In this case, there is no uncertainty
regarding the price, which would be favorable for the decision maker.
The amount of energy is measured with the percussive units for each drilling method.
It depends on the ROP if the amount of energy is measured per drilled meter or per ton
of rock. The difference in energy that the drill rig itself consumes (except for the
percussive unit) is negligible, therefore it is not included in the decision analysis.
17
to provide the decision maker with the required input data for the probability
distributions.
The cost of haulage and separation are dependent on the technique used and the
fragmentation of the rock. For example, a very fine fragmentation will result in
a larger volume and less density. If the fragmentation is fine, the productivity
of the ore that can be hauled will be lower. This uncertainty can also be reflected
by a probability distribution.
18
Figure 6. A tornado diagram shows the variables on the Y-axis and the total cost value
on the X-axis. How large effect the variables had on the results given the variation in
each variable is shown.
19
Table 2. Calculation spreadsheet of the Monte Carlo simulation for all costs of
the drill methods.
Drill Method Value Probability distribution / Formula
Deviation C26 Normal
20
7.1 Calculations
Calculations are based on tables 1 and 2 from the previous section. Calculations are set
up identically for all three drilling methods. Methods to determine the variables used in
these calculations are explained in section 6.1.
21
7.4 Cost of ore loss
The ore loss (%) is calculated by multiplying the deviation by the deviation-ore loss
factor. This factor and its calculation are described in sections 5.3 and 6.1.4:
C51 = C26*C9.
The total loss of revenue - processing cost ($)/t is the product of ore loss (%), grade of
the ore (%), and price of the ore ($/ton), subtracted by the product of ore loss (%) and
the handling of dilution cost ($/t):
C52 = (C51*C19*C20)-(C51*C17).
22
holes are 25 m (estimated deviations are used for this length). It is important to present
and analyze a simulated result for decision makers to understand the process, hence the
need for input values. Tables 3–6 describe the values used in the calculations. As the
values are based on data from mining operations in both northern Europe and Australia,
the results should be somewhat realistic. It important to note that the reader should not
make a general conclusion based on the results presented here, for example, that one
drilling method is more favorable, since it is very likely to differ from mine to mine.
23
Table 4. Input values of the Top-hammer drilling method to simulate a result
Top-Hammer drilling method Value Probability distribution
Deviation 4% Normal µ 0.04 σ 0.004
Dilution 1%
Cost of dilution ($)/t 0.13
Ore loss 1%
Cost of ore loss ($)/t 0.40
24
Table 5. Input values of the pneumatic DTH-hammer drilling method to simulate
a result
Pneumatic DTH-hammer drilling method Value Probability distribution
Deviation 2% Normal µ 0.02 σ 0.002
Dilution 0.5 %
Cost of dilution ($)/t 0.06
25
Table 6. Input values of the hydraulic DTH-hammer drilling method to simulate
a result
Hydraulic DTH-hammer drilling method Value Probability distribution
Deviation 1% Normal µ 0.01 σ 0.001
Dilution 0.25 %
Cost of dilution ($)/t 0.03
26
8 Analysis of the results
As described in chapter 7, the input values used in the calculations are based on data
from mining operations in Northern Europe and Australia to produce a more realistic
result to analyze. Figures 7–9 show the simulation results of the total cost/ton.
Figure 7. Probability density graph showing the total cost/ton of each drilling method.
Figure 8. A cumulative distribution function (CDF) shows the total cost/ton of each
drilling method.
27
Figure 9. A CDF shows the total cost/ton of each drilling method, zoomed in version of
Figure 8.
None of the drilling methods presented in Figures 7–9 have deterministic dominance,
as in Figures 4 and 5. First-order stochastic dominance occurs for the Pneumatic and
Hydraulic DTH-hammer over the top-hammer, which Clemen and Reilly (2001, p 134-
135) describe as occurring if the graphs simulation results do not cross and there is space
between the curves. That is, if a graph of two cumulative simulation results are such
that no part of alternative 1 lies to the left of alternative 2, and at least some part of it
lies to the right of alternative 2, then alternative 1 stochastically dominates alternative
2. The hydraulic DTH-hammer has the lowest mean value, while the top-hammer has
the highest mean value.
It can also be interesting to break down the total cost/ton into the four different costs
described in the previous chapter: direct cost of drilling, cost of dilution, cost of ore loss,
and cost of having an unsuccessful blast. Table 7 shows these costs.
The mean values of the simulation results presented in Table 7 are also shown is
Figures 10–12. It can be useful for the decision maker to analyze each cost to understand
the total cost picture. It can also be interesting to compare the direct cost of drilling, cost
of dilution, cost of ore loss, and cost of having an unsuccessful blast between the
different drilling methods. Figures 10–12 show results of such simulations.
28
Figure 10. A CDF shows the direct cost of drilling/ton for each drilling method.
Figure 11. A CDF shows the cost of dilution/ton for each drilling method.
29
Figure 12. A CDF shows the cost of ore loss/ton for each drilling method.
Based on the values from the simulation results given in Figures 10–12 and Table 7,
it is clear that the top-hammer method is the cheapest drilling method in terms of direct
costs of drilling, but also the most expensive method in terms of indirect costs, the
opposite of the hydraulic DTH hammer. These kinds of presentations can help a
decision maker understand how costs are allocated between different drilling methods.
The cost/ton value has a very wide range and the maximum value is 10–20 times
higher than the minimum value. The wide range of the cost/ton value depends on what
parameter values and input values that were used in the calculations. The values used in
the binomial function that was used to represent the success of the blast generates values
for either a successful or unsuccessful blast which will also contribute to the wide range
of cost/ton value. Such wide range of the cost/ton value is a severe risk for the decision
maker. If an unsuccessful blast generates the maximum cost values, the cost is likely to
be above the breakeven point (when the cost is as high as the revenue). If the risk of
having an unsuccessful blast cannot be decreased, it can be useful to analyze graphs to
determine the probability of a certain cost interval. For example, if the breakeven point
for the particular mine is 0.46 $/ton in terms of drilling cost, the following functions can
be used based on the input values and cells from previous tables. Figure 13 shows graphs
of the functions below by setting the 0.46 value at the delimiters at the top of the figure.
These functions calculate the probability of having a cost below the given cost (0.46
$/ton) based on simulation results:
Top-hammer = RiskTarget (C62,0.46) = 5% (see Table 4)
Pneumatic DTH-hammer = RiskTarget (G62,0.46) = 84.5% (see Table 5)
Hydraulic DTH-hammer = RiskTarget (K52,0.46) = 88.5% (see Table 6)
30
Figure 13. A CDF shows simulations for each drilling method where the probability of
having a cost below 0.46 $/t is presented. By adjusting the vertical line to 0.46, the
same values can be viewed directly in the graph.
These breakeven values can be useful as an efficient way to determine which drilling
methods to eliminate as alternatives. In this example, it is unlikely that the top hammer
would be a more appropriate drilling method than the other two alternatives if the
probability of having a drill cost below the breakeven point is 5%.
31
Figure 14. Tornado diagram showing how large effect the variables had on the results
given the variation in each variable with the top-hammer drilling method.
For the pneumatic DTH-hammer (described in Figure 15) and the hydraulic DTH-
hammer (described in Figure 16), the cost of an unsuccessful blast is also the variable
that had the highest effect on the results given the variation of each variable. The price
of the ore is the variable that had the second highest effect on the results given the
variation of each variable with the pneumatic DTH-hammer while the amount of drill
meters/ton and ROP had a higher effect on the results with the hydraulic DTH-
hammer giving the variation used in the model. This is likely explained by the fact that
the direct cost of drilling is higher with the hydraulic DTH hammer compared to other
drilling methods.
Figure 15. Tornado diagram showing how large effect the variables had on the results
given the variation in each variable with the pneumatic DTH-hammer drilling method.
32
Figure 16. Tornado diagram showing how large effect the variables had on the results
given the variation in each variable with the hydraulic DTH-hammer drilling method.
Following this, three different values for the deviation–unsuccessful blast factor
were used and separate simulations completed. Table 8 describes the different values of
33
the factor at each fractile and the simulation results are shown in the column “mean
value of total cost” and in Figure 18.
Figure 18. A CDF shows simulations with the different values of the deviation–
unsuccessful blast factor.
As shown in Figure 18, the change of value did not change the drilling method with
the lowest mean value.
Another sensitivity analysis was also completed to analyze how large effect the
deviation variable have on the results given a variation of the variable. The 5%, 50%
and 95% fractiles were used again. Table 9 describes the different values of the
deviation used in the sensitivity analysis and the column “mean value of total cost” and
Figure 19 shows the results.
34
Table 9. Values used for the sensitivity analysis of the deviation.
Mean value of Total cost
Fractile Deviation Simulation
($/ton)
Top-Hammer 5% 3.34% 1 0.65
50% 4.0% 2 0.75
95% 4.66% 3 0.86
Figure 19. A CDF shows the simulations with the different values of the deviation.
By comparing the mean values in Figure 19, the change in deviation did not change
the drilling method with the lowest expected cost/ton.
35
9.1 Safety criterion
Coleman and Kerkering (2007, p 1) describe that it is common for injuries to be
measured with the Lost-Time Injury (LTI) scale which measures the number of injuries
during a certain number of worked hours. This value can also reflect an indication of
risk in the work environment. In risk management, there are several methods to improve
the work environment by handling risks in different ways. Mattsson (2003, p 344)
describes risk management, suggesting one method to approach risk is to decrease
exposure to the risk. If a work task can be completed more quickly, for example, by
substituting a drilling method for another drilling method, risk exposure to certain risks
can be decreased. For example, in underground production drilling, there is always a
risk that a rock fall appears near the production front, which means a potential risk that
the drill rig and operator will be buried under the rock. By completing the job more
quickly, controlled by the ROP in this case, risk exposure would be lower. The top-
hammer drilling method likely has the highest ROP which means that it would reduce
time exposure to certain risks. However, as described in chapter 6.1.13, Singh and Sinha
(2012, p 164) note that an even fragmentation of the rock can increase productivity in
the subsequent processes (such as crushing) by up to 25%. The top-hammer drilling
method is more likely to have higher deviation than other, comparable drilling methods,
hence the overall risk exposure may be higher for this alternative, despite the higher
ROP. This demonstrates the importance of analyzing the consequences of drill deviation
rather than simply direct safety aspects around drilling.
If the decision maker receives additional information regarding how drill hole
deviation influences fragmentation (not included in the decision analysis), a scenario
can be simulated to estimate how much additional time a certain deviation would yield
for the subsequent processes. If the capacity of the crusher, for example, is 100 tons/hour
under the best circumstances, uneven fragmentation results in a maximum capacity of
80 tons/hour, and there would be an additional 15 minutes of crushing to crush a total
of 100 tons. This means that exposure to risks associated with crushing increases. The
value of risk exposure could be calculated with a Monte Carlo simulation in a similar
set up as with the cost criterion.
Besides risk reduction, the decision maker has to evaluate whether drilling methods
will eliminate or substitute risks associated with the drilling process. One of the
hydraulic DTH-hammer suppliers’ website (Wassara, 2016b) describes that if a high-
pressure water hose (used to transport water from the pump to the DTH-hammer) should
fail, the pressure immediately disappears. Just like a garden hose, the supplying hose
will lose the stiffness created by the high-pressure water. A failing hose used for air-
powered drilling (compressed air) will act like a powerful whip, generating high risk of
harm to both equipment and people. This could also be reflected in calculations as it is
likely that the hydraulic DTH hammer eliminates this particular risk. The methods also
differ in that the top-hammer and pneumatic DTH-hammer use compressors to
compress air, while the hydraulic DTH-hammer uses a pump to power the percussive
unit. One possible risk with great consequences in underground mining is fire. The
decision maker should compare the probability of a compressor and a water pump
beginning a fire. By using one of the techniques, the risk can be reduced through
substitution.
36
future generations to meet their own needs. The following paragraphs are based on a
review on sustainable mining practices completed by Kumar (2014). The review is
based on concepts from the Brundtland report and discusses how the mining industry
can implement the concepts. Hence, the review contains the opinions of the author
which are yet to be considered widely accepted within the mining industry.
Kumar (2014, p 26-27) describes that mining can become more environmentally
friendly and sustainable by adopting and integrating innovative technology, social,
environmental, and economic developments that minimize the environmental impact of
mining operations. One of these commonly measured factors is the amount of energy
used in the mining process. Sustainable development in this sector suggests a concept
of needs, an idea of limitations, an oriented paradigm, and a process of change.
Kumar (2014, p 27) further describes that for a mining company to achieve
sustainability, it needs to be economically viable, financially cost effective, and
technically efficient or even innovative. This enables the mining company to maintain
continuous, environmental, socio-economic improvements. In operational terms,
sustainable development in the mining sector implies a mix of scientific mining,
technological developments, environmental responsibility, socioeconomic development
in local communities, stakeholder engagement, and transparency in communication.
These are the necessary underlying factors to ensure the growth and sustainability of the
industry. Modes to achieve sustainable mining can be narrowed down to two aspects.
The people who are responsible for deciding the most appropriate mining method
(scientific mining) will indirectly determine the technology to be used (technological
advancement).
Kumar (2014, p 27) also describes that the objective or purpose of scientific mining
is primarily to improve the environmental impact and concerns which include
innovative mining methods and practices originating from a systematic approach to
mine development and operations. This involves a continuous development of
technology reflected in equipment advances and management practices. In the
technology advancement process, it is common that mining companies encourage
suppliers to develop innovative solutions to the mining industry that will empower
technological advancement and contribute to a more sustainable mining process.
Some criteria are easier to measure and simulate, for example, energy consumption,
which can be simulated with a Monte Carlo simulation in a similar set up as the cost
criterion. Another aspect of the environmental criterion for this decision analysis could
be negative aspects, such as contaminated water from hydraulic DTH hammer drilling
methods, compared to compressed air with a higher energy cost from pneumatic DTH
hammer drilling methods.
37
10 Discussion
I personally believe that the use of decision analysis will become increasingly common
in the mining industry. As presented in this thesis, underground mining processes
consist of many uncertainties and it is challenging to design a simulation because
production varies from area to area, unlike manufacturing plants with fixed machinery.
I believe that decision analysis will become more common because of changes that the
mining industry is currently facing and experiences. These changes include moves
towards automation by adapting to lean principles and turning relatively uncontrolled
production into leaner controlled production. Rio Tinto is one of the largest mining
companies and its CEO, Sam Walsh, reinforced in an interview (Mining global, 2014)
the importance of working with lean principles in the mining industry. Lean production
principles in the mining industry enable better circumstances for the use of decision
analysis because the processes are measured and standardized over time. This likely
reduces the degree of uncertainty and also provides decision makers with better
circumstances to design more representative decision models based on a mine.
One challenge this thesis demonstrates is how processes influence other processes in
a mine. It is challenging to narrow down the decision problem by only analyzing the
cost of the drill process because the results of the drilling influence the subsequent
processes. Based on the input values used, the simulation results demonstrates that
indirect costs of drilling could be higher compared to direct costs of drilling. I believe
that Monte Carlo simulations are an efficient method to calculate and demonstrate this
aspect. Tornado diagrams show that the uncertainty surrounding an unsuccessful blast
is the uncertainty causing the largest variation in cost. The unsuccessful blast variable
is based on the product between the deviation and the factor that describes how drill
hole deviation influences the risk of having an unsuccessful blast. The decision makers
should be careful to suggest that factors such as deviation of the blast hole determine
the decision because other aspects may be more important. For example, the deeper the
mine is, the more expensive it may be to handle dilution, which means the operational
cost for handling dilution may be the main determinant. More importantly, the decision
maker also needs to evaluate whether uncertainty (variation of value from the baseline)
is modeled correctly for a particular decision and its circumstances. If not, the
simulation results shown in the tornado graphs can be misleading in terms of how large
effect the variables have on the results given the variation in each variable.
It is also important to evaluate how useful the decision analysis model (based on the
calculations) is in its current state, or if delimitations and simplifications make the
calculations inaccurate. When evaluating the probability of an unsuccessful blast, it is
important to evaluate whether the probability is reasonable. As in this example, the
mean value of 4% deviation of the top-hammer yields in a 6% probability of having an
unsuccessful blast due to the deviation. This rate of unsuccessful blasts, based on
personal experiences, appears reasonable for sub level stoping, especially for narrow
stopes which are more likely to freeze compared to wider stopes. Although, the decision
maker still needs to evaluate how often a blast freezes from other factors. If a mine
usually experiences 10% freezes (which appears to be a high number), the calculations
above that yields in a 6% probability of having an unsuccessful blast due to drill hole
deviation suggest that 60% of unsuccessful blasts would be due to hole deviation and
the other 40% for other reasons.
As explained in section 1.4, calculation of ore loss during an unsuccessful blast were
simplified to be 5% in the simulations. This will vary from blast to blast and it also
impacts the total cost. The deviation of the unsuccessful blast factor is likely to be
different depending on the dimension of the stope in terms of width and height. Often
stope width for a mine is similar unless the ore body has a varied width and the height
is determined by the mine design. Also, the additional cost of an unsuccessful blast was
simplified, as I used the same direct drill cost/ton for re-drilling the stope, and the cost
of the additional blast was set to the same value. From my personal experience, the cost
38
of drilling and the cost of charging are similar, but certainly this will be different for
every mine and depends on the dimensions used.
The factor that describes how drill hole deviation influences dilution and ore
recovery is certainly important for the decision. As described, the factor used in this
decision analysis to some extent simplified. It is possible to calculate the factor to some
degree of certainty, as explained in chapter 5, but other factors (such as rock condition)
will also influence this factor, as explained in section 6.1.4. Hence, the deviation of the
dilution and ore recovery factor can vary depending on ground conditions.
The mine could also design the drill and blast designs to include redundancy for the
drill hole deviation, which means deviation would only cause additional dilution. For
example, if an ore-body is 3 m in width, the stope width would usually be designed to
be 3.5 m to ensure that all of the ore is recovered by the blast. Although, severe drill
hole deviation will still cause ore loss. By designing with drill hole redundancy, the
stope width could instead be 5 m, meaning a severe amount of dilution would be mined
but minimum amount of ore loss would be achieved. In fact, this could be another
valuable decision analysis. By increasing the drilled meters/ton to avoid the probability
of having unsuccessful blasts and ore loss due to deviation, would the additional direct
cost of drilling and dilution be lower than the cost of having an unsuccessful blast and
ore loss? Performing drill and blast tests and measuring the results over time would
likely be a useful approach.
It is interesting but challenging to determine which drilling method is the most
environmentally friendly. Even when reducing this to energy consumption, it will be a
discussion. Reducing energy consumption of a single process is favorable. However,
the drilling method that may be the most energy effective (the hydraulic DTH-hammer)
method consumes significant volumes of clean water and fresh water becomes
contaminated in the drill process. Clean water is a limited resource in many areas and
the decision as to whether high energy consumptions or contamination of fresh water
has the largest, negative impact on the environment needs to be analyzed. The answer
to this question may be on a governmental level with many stakeholders. Although, it
is important for the mining company to determine if their vision or policy includes
environmental responsibility.
39
this. It would be meaningful if the policy of a company stated that all of important
decisions regarding production process were to be taken with decision analysis
methodology.
For mining companies that want to analyze a specific decision, like the decision
problem in this thesis, an experienced decision analysis consultant within the field
would be a good alternative. Even if the decision analysis consultant does not have
proper mining knowledge, this should not be a limitation because mining engineers can
provide the necessary information for the consultant. Complex decisions usually have
many stakeholders and it is important that all are involved in the decision analysis
process.
The mining industry would benefit greatly from decision analysis, just as in other
industries, as it increases the chance that decision makers make decisions with the
greatest confidence. Perhaps a “political commission” could enhance this development
even further. An example of a similar initiative is the innovation partnership
commenced (European commission, 2014) on raw materials with the overall objective
of joining efforts with other stakeholders to make Europe an even more competitive and
sustainable society. The mining industry is an important supplier of efficient and
sustainable solutions to meet the needs of modern society for metals and minerals. Safe,
lean, and green technology, and an innovative organization should attract talented young
men and women to meet the sizable, future challenges and opportunities of mineral
supply. The specific objective in this partnership is to review existing research and
projects regarding sustainable mining and prepare a roadmap for a future research
program. The pre-study completed in 2014 demonstrated a coherent and effective
programme that can support sustainable development in the mining sector. The future
programme will focus on the core of sustainable development in the mining sector and
be useful for mining companies that wish to integrate sustainability issues into their
operations and strategies. It will not be targeted directly to leaders of mining
corporations. Moreover, policy leaders on national, regional, and local levels will be an
important target group.
11 Conclusion
Many variables with uncertain values are included in the decision analysis presented
and they affect subsequent processes, resulting in indirect costs. The variables with
uncertain values presented in this study are likely to be uncertain in most cases regarding
this decision problem. The indirect costs are not easily available for reflection when the
prices of drilling equipment are presented. Hence, the use of decision analysis
methodology for this decision problem is favorable since it enables decision makers to
structure decisions and focus on variables that had the highest effect on the results given
the variation in each variable. For example, if the grade of the ore variable had the
highest effect on the results given the variation in each variable, the decision maker
should prioritize to reduce the uncertainty of this variable. By doing that, the variation
of the variable will be decreased, hence decreasing the effect it had on the result.
This thesis was completed to demonstrate how drill hole deviation affects indirect
costs, such as cost of handling dilution, cost of ore loss, cost of having an unsuccessful
blast, and how large indirect costs can be in relation to direct costs of drilling, often
presented when drilling methods are compared (see chapter 7 for the indirect and direct
costs). The results, based on a method presented for determining how drill hole
deviation influences indirect costs with input values from existing mining operations,
show that indirect costs are much higher than direct costs. Like the results presented by
Olsen (2009, p 89) for open pit mining, drilling straighter holes is economical profitable.
In this case, the top-hammer drilling method, which has the highest drill hole deviation,
results in the largest cost per ton, even if the actual direct drill cost per ton was the
lowest. As explained, it would be too generalized to make such conclusions as they will
vary from mine to mine for underground mining.
40
As discussed in section 1.2, a specific drill hole length (associated with a deviation)
can often act as a rule of thumb for which drilling method to use. For example, for a 25
m drill hole, it is likely that top-hammer drilling would be recommended because it is
explained by manufacturers as the cheapest drilling method in terms of drill
consumables, the quickest drilling method in terms of ROP, and has a drill hole
deviation less than 5% (see chapter 4 for drill hole deviation among drilling methods).
This likely sounds like a good alternative for the decision maker. However, the
simulation results presented in this thesis, based on the input values and simplifications,
shows that drilling methods with low deviation at an higher consumable cost and
decreased ROP can be more favorable in terms of total cost/ton. Although it is unlikely
that a general conclusion can be reached and many of simplifications and uncertainties
should be reduced. For example, for any drill hole that is under 15 m in length, the
difference in drill hole deviation between drilling methods would likely be so small that
the top-hammer drilling method would be most cost efficient. However, if the ore mined
is an ore of an exceptionally high grade and price, the most appropriate drilling method
could again differ. Each decision will be unique.
41
References
Aalizad, S.A., Rashidenejad, F. (2015). Prediction of penetration rate of rotary non-
percussive drilling using artificial neural networks. Arch. Min. Sci. 57(3), 715-728
Atlas Copco (2014). Underground mining: A global review of methods and practices.
Brundtland (1987). Our Common Future: Report of the 1987 World Commission on
Environment and Development, Oxford, Oxford University Press
Clemen, R. T., Reilly, T. (2001). Making hard decisions. 2nd edition. Duxbury Thomson
Learning
Coleman, P. J., Kerkering, J. C. (2007) Measuring mining safety with injury statistics:
Lost workdays as indicators of risk. National institute for occupational Safety and
health, Spokane research Laboratory 38(5), 523-533.
EHS Data (2016). Managing environmental impacts can create a significant burden for
mining companies
http://ehsdata.com/articles/managing-environmental-impacts [2016-06-21]
Hammond, J. S., Keeney, R. L., Raiffa. H. (2002). Smart choices: A practical guide to
making better decisions. Harvard Business School Press
Lundberg, J., AL-Chalabi, H., Hoseinie, S. H. (2016). Monte Carlo reliability simulation
of underground drill rig. Springer. Lecture Notes in Mechanical Engineering, 633-643
Lunenburg, F.C (2003). The power of intuition: how to use your gut feeling to make
better managerial decisions, Sam Houston State University
Mattsson, B. (2003). Att värdera risker. In B. Grimwall, G., Jacabsson, P., Thedeen, T
Risker I tekniska system, (p 339-363). Studentlitteratur AB
42
Mining global. (2014). Interview with CEO of Rio Tinto, Sam Walsh, Lean production
http://www.miningglobal.com/operations/522/How-to-Implement-Lean-Principles-in-
the-Mining-Industry [2016-05-16]
Olsen, V. (2009). Rock Quarrying Prediction models and Blasting safety, Norwegian
University of Science and technology
Singh, P.K., Sinha, A.A. (2012). Rock fragmentation by blasting: Fragblast 10. CRC
Press
Spathis, A., Gupta, R.N. (2012). Tunneling in rock by drilling and blasting. CRC Press
Thompson, M.J (2010). M.Sc. thesis: Hydraulic hammer drilling technology to replace
air hammer drilling in deep BHE design, The school of renewable energy science
Vargas, J. P., Koppe, J. C., Pérez, S., Juan, P. (2015). Planning tunnel construction using
Markov Chain Monte Carlo. Mathematical Problems in Engineering. Volume 2015, 1-
8
Wassara (2014). Water powered drilling: The water hydraulic DTH Technology
brochure.
43