GDI
GDI
ARBAMINCH UNIVERSITY
WATER TECHNOLOGY INSTITUTE
WATER RESOURCES AND IRRIGATION ENGINEERING DEPARTMENT
ACKNOWLEDGEMENT
Firstly we would like to give our almighty God who allocates all things to prepare this
project and fulfilmement of our whishes.
Secondly, we would like to express our deepest hearted thanks to Arbaminch
University for giving the chance to prepare this design document. And our thanks are
also for our department water resources and irrigation engineering for the preparation
of advisors to guide ourselves.
Our sincere thanks extends to our advisors to ato Gabr Mehari (MSC) and ato Fisha
Sahlie (BSC) for the proper guidance, comments, allocations and suggestions during
our design reports to reach up to the points of goal.
We would like to thanks for Arbaminch university library workers for giving
reference materials whenever we required without any tiredness‟s.
Last but not the least our heartful and grand thanks give for our families to help to
prepare this design document reports both in their finically and economically and in
their guidance for our life span in our educations from the begging up to the end today
know.
i
EXCUTIVE SUMMARRY
This report describes the over view of the development of irrigation water delivery in
the area of gedi irrigation project. In our preliminary design of gedi irrigation project,
the report has been divided in ten chapters.
In the first chapter, the overview, the project area, the geological data, and the
topography of the project are described. In chapter two the estimation of peak
discharge in relation of peak rainfall has to be described. The special water
requirement, the selection of crop, the type of crop and the schedule of irrigation by
using crop watt window 8 soft ware have to be explained under the third chapter. In
the fourth chapter the water demand design especially furrow method design
describes in this chapter. The layout, design and construction of irrigation canal is
located under chapter five. In the sixth chapter the selection of weir, the location of
weir, the type of weir, the construction methodology of weir and the construction
method of weir parts such as head regulators, guide walls (u/s &d/s), under sluce have
to be located under this chapter. The layout of , the design means and proper
construction of drainage canal describes under chapter seven. In chapter eight the
estimation of excavation (cut & fill) and the cost of the project has to be describes.
The impact assessment, mitigation measures and impact of the project on
environmentally and socially (negative& positive aspects) have to be located under
chapter nine. In last but not the least the recommendation and conclusions of our
report have to be describes in chapter ten.
ii
TABLE OF CONTENT
ACKNOWLEDGEMENT .............................................................................................. i
EXCUTIVE SUMMARRY ...........................................................................................ii
TABLE OF CONTENT ............................................................................................... iii
LIST OF TABLE .......................................................................................................... vi
LIST OF FIGURE...................................................................................................... viii
LIST OF ABBRBATION ............................................................................................. ix
1. INTRODUCTION ................................................................................................. 1
1.1 General ............................................................................................................ 1
1.2 Objective of the project ................................................................................... 2
1.3 The Project Area.............................................................................................. 2
1.3.1 Background .............................................................................................. 2
1.3.2 Location and access of the project area ................................................... 2
1.4 Topography ..................................................................................................... 4
1.5 Geology ........................................................................................................... 4
1.5.1 Geology along headwork structures......................................................... 4
1.5.2 Construction Materials Availability......................................................... 4
1.6 Soil .................................................................................................................. 5
1.7 Water Quality .................................................................................................. 5
2. HYDROLOGICAL ANALYSIS ........................................................................... 6
2.1 Data Availability ............................................................................................. 6
2.2 Climates........................................................................................................... 6
2.3 Water Source Potential .................................................................................... 7
2.4 Peak Rainfall Determination ........................................................................... 7
2.5 Peak Discharge Determination ...................................................................... 15
2.5.1 Rational method ..................................................................................... 16
2.5.2 Empirical formula .................................................................................. 17
2.5.3 Unit Hydrograph Technique .................................................................. 18
2.5.4 SCS Curve Number Method .................................................................. 18
3. WATER DEMAND, AGRONOMY AND WATER DELIVERY ASPECTS ... 21
3.1 Crop selection ................................................................................................ 22
3.2 Cropping pattern ............................................................................................ 22
3.2.1 Crop land allocation ............................................................................... 23
3.2.2 Optimization .......................................................................................... 24
3.2.3 Crop coefficient (Kc) ............................................................................. 24
3.3 Crop water requirement ................................................................................. 26
iii
3.3.1 Determination of crop water requirement (ETcrop) .............................. 27
3.3.2 Irrigation Requirement ........................................................................... 28
3.4 Irrigation efficiencies .................................................................................... 32
3.4.1 Field application efficiency (Ea) ............................................................ 32
3.4.2 Field canal efficiency (Eb) ..................................................................... 32
3.4.3 Conveyance efficiency (Ec) ................................................................... 32
3.4.4 Project efficiency (Ep) ........................................................................... 33
3.4.5 Net irrigation requirement (NIR) ........................................................... 33
3.4.6 Leaching Requirement (LR) .................................................................. 33
3.4.7 Field irrigation Requirement (FIR) ........................................................ 33
3.4.8 Gross Irrigation Requirement (GIR) ...................................................... 34
3.5 Irrigation Scheduling ..................................................................................... 34
3.5.1 Depth of irrigation.................................................................................. 35
3.5.2 Irrigation Interval (T) ............................................................................. 35
3.6 Determination of Design Discharge .............................................................. 36
3.7 Methods of Water Delivery and Delivery Scheduling .................................. 38
3.7.1 Main System .......................................................................................... 38
3.7.2 Tertiary System ...................................................................................... 38
4. SURFACE IRRIGATION METHODS ............................................................... 39
4.1 Choice of Irrigation Method .......................................................................... 39
4.2 Surface Irrigation Method ............................................................................. 39
4.3 Furrow Irrigation ........................................................................................... 40
4.4 Design Consideration of Furrow Irrigation ................................................... 40
5. DESIGN OF CANALS AND CANAL STRUCTURES ..................................... 50
5.1 Canal Alignment ........................................................................................... 50
5.2 Hydraulic Design of the Canal ...................................................................... 51
5.2.1 Permissible velocity ............................................................................... 53
5.2.2 Tractive Force ........................................................................................ 54
5.3 Full Supply Discharge (FSD) ........................................................................ 55
5.4 Design of Main Canal ................................................................................... 58
5.4.1 Design of Right block Main Canal ....................................................... 58
5.4.2 Design of left block main canal ............................................................. 60
5.5 Tertiary Canal Design ................................................................................... 63
5.6 Design of Canal Structures ............................................................................ 64
5.6.1 Culverts .................................................................................................. 64
5.6.2 Canal Drop ............................................................................................. 65
5.6.3 Division Box .......................................................................................... 68
iv
5.6.4 Farm turnout........................................................................................... 69
5.6.5 Flow control structures(Gates) ............................................................... 70
5.6.6 Access Roads ......................................................................................... 71
6. DESIGN OF DRAINAGE CANALS .................................................................. 72
6.1 Design of Surface Drainage Canals .............................................................. 72
6.2 Alignment of surface drainage ...................................................................... 73
6.3 Types of drainage canals ............................................................................... 76
7. HEAD WORK DESIGN...................................................................................... 82
7.1 Location of Diversion Weir......................................................................... 82
7.2 Selection of Type of Weir ............................................................................. 82
7.3 Design of head work structures ..................................................................... 83
7.3.1 Hydraulic Design of A Weir .................................................................. 83
7.3.2 Weir wall design (Structural) ................................................................. 86
7.3.3 Design of impervious floor and protection works ................................. 88
7.3.4 Water profile downstream of the weir ................................................... 92
7.3.5 Water surface profile upstream of the weir............................................ 96
7.3.6 Stability Analysis of the Weir ................................................................ 96
7.3.7 Design Of Under Sluice Protection........................................................ 99
7.3.8 Design of Canal Head Regulator ......................................................... 100
7.3.9 Divide Wall .......................................................................................... 102
7.3.10 Design of Silt Excluder ........................................................................ 103
7.3.11 Guide Bank .......................................................................................... 104
8. COST ESTIMATION ........................................................................................ 109
9. ENVIRONMENTAL IMPACT ASSESSMENT .............................................. 111
9.1 Description of potential Impact ................................................................... 111
9.1.1 Positive environmental impact of the project ...................................... 111
9.1.2 Negative impacts of the project ........................................................... 112
9.2 Mitigation measures .................................................................................... 113
10. CONCLUSION AND RECOMMENDATION . ............................................ 115
10.1 Conclusions ............................................................................................. 115
10.2 Recommendations ................................................................................... 116
REFERENCES .......................................................................................................... 117
ANNEXES ................................................................................................................. 118
v
LIST OF TABLE
Table 2-1 Maximum daily rainfall Values of 23 years for Meteorological station of ... 8
Table 2-2 Guide line for selecting return periods for different hydraulic structure ..... 10
Table 2-3 Normal Distribution method detail calculation ........................................... 11
Table 2-4 log- Pearson type III distribution method detail calculation ....................... 14
Table 2-5 Summary of the results of all methods ........................................................ 15
Table 2-6 Summary of the results of all methods ........................................................ 20
Table 3-1Selected crops, planting date & land allocation ........................................... 23
Table 3-2 seasonal cropping arrangement ................................................................... 24
Table 3-3 growing stage (days) and Kc values of the proposed crops season one .... 25
Table 3-4 growing stage (days) and Kc values of the proposed crops season two . 26
Table 3-5 Summary of the result of effective rainfall calculated using different
methods in mm............................................................................................................. 30
Table 3-6 Irrigation requirement .................................................................................. 31
Table 3-7 Irrigation schedule ....................................................................................... 36
Table 3-8Scheme Supply wet season ........................................................................... 36
Table 3-9Scheme Supply dry season ........................................................................... 37
Table 4-1furrow infiltration and inflow rate ................................................................ 41
Table 4-2 spacing between rows and plants ................................................................ 41
Table 4-3Relation of maximum non erosive flow rates to critical slope of furrows ... 43
Table 4-4 Furrow irrigation design for the selected crops .......................................... 47
Table 4-5Furrow irrigation design for the selected crops ............................................ 49
Table 5-1permissible velocity for unlined canal .......................................................... 53
Table 5-2 Permissible velocity (lined canal) ............................................................... 54
Table 5-3 Critical tractive force for different soil ........................................................ 54
Table 5-4 Side Slope for Various Soils........................................................................ 56
Table 5-5The Value of N for Different Type Of Bed Material. .................................. 57
Table 5-6 Factor f-values of the shape of the cross section (Adapted from Meijer
1989) ............................................................................................................................ 59
Table 5-7 Summary of right main canal calculation .................................................... 62
Table 5-8Summary of left main canal calculation ....................................................... 62
Table 5-9Summary of tertiary canal calculation .......................................................... 63
Table 6-1capacity of left Drainage canal ..................................................................... 75
vi
Table 6-2 Hydraulic parameters of left drainage canal ............................................... 78
Table 6-3 Hydraulic parameters of left drainage canal ............................................. 80
Table 7-1 result of water surface profile before the jump ........................................... 94
Table 7-2 Water surface profile after jump.................................................................. 95
Table 7-3 u/s water profile ........................................................................................... 96
Table 7-4 Force and moment acting on the weir ......................................................... 98
Table 7-5 Stability analysis of D/s guide wall ......................................................... 107
Table 7-6 Stability analysis of U/s guide wall bank ................................................. 108
Table 8-1Cost estmation ............................................................................................ 109
vii
LIST OF FIGURE
Figure 1-1 Loaction Map of Southern Nations & Nationalities regional state .............. 3
Figure 1-2 Location of the Woreda for Geddii Irrigation project on the Regional M .. 3
Figure 5-1 typical cross section of main canal.......................................................... 62
Figure 5-2 typical cross section of tertiary .................................................................. 64
Figure 5-3 Division box .............................................................................................. 69
Figure 6-1 capacity of left Drainage canal .................................................................. 74
Figure 6-2Typical cross section 0f drainage canal ...................................................... 81
Figure 7-1 Downstream channel section..................................................................... 83
Figure 7-2Stage-Discharge Curves .............................................................................. 84
Figure 7-3 Weir floor thiknees and protection work ................................................. 92
Figure 7-4 Force acting on the weir .......................................................................... 97
Figure 7-5 Force U/S Guide Bank ............................................................................. 107
viii
LIST OF ABBRBATION
ix
Final Year Project on Gedi Small Scale Irrigation Project 2013
1. INTRODUCTION
1.1 General
Ethiopia is one of the developing countries and around 85% of the total population
depends on agriculture most of the agricultural practice is rain fed crop production.
However, due to the back ward method farming, un reliable rainfall, including
population and drought. The nation faced series food shortage. . These food shortages
were followed by sever famines that resulted in the loss of the lives of millions of
citizens. Hence, it is obvious that the agricultural system has to be improved and
irrigation practice should be spread extensively to bring about sustainable food self-
sufficiency and to earn foreign exchange.
1.3.1 Background
There is very limited experience in the project area on the development and use of
irrigation. There is an effort to divert the flow in Geddii stream. This effort is not
being used successfully by the farmers. The main reasons are lack of capacity to
effecively maneuver the undulating terrains and conflict of social interest on equitable
water usage.
from Addis Ababa- via-Jima Addis Ababa highway. The stream passes through a
other villages in highland areas, before passing throug Chebaro, and Midabo kebeles,
and continuing further downstream to other kebeles.
Figure 1-1 Loaction Map of Southern Nations & Nationalities regional state
Figure 1-2 Location of the Woreda for Geddii Irrigation project on the Regional Map
The project area is located in Kaffa Zone, Gewata Woreda. The irrigable area and the
headwork are found in Chebaro Kebele, close to the Woreda town Konda.
Access ; Access to the project area is possible through Jimaa or Bonga towns. The
Jima road is preferred for access from Addis Ababa. The other route passing through
Bonga is used when accessing the project from the regional capital Hawassa.
The distance from the nearest zonal town Bonga to Konda woreda is 105Kms on an
all weather road. Currently it takes about 2.5 to 3 hours drive with a 4WD vehicle.
Access to the site is possible from a junction to the road from Gimbo to Konda, called
Midabo. Midabo is an adjacent kebele to Chebaro, the project area, and is found about
8Kms from before reaching Konda town.
The project is located about 5 kms from Midabo, which can be accessed using 4WD
cars in dry seasons through a temporary road. To allow year round access,
maintenance and upgrading of this access is required. (Tefera, 2012)
1.4 Topography
The command area begins immediately from a few meters from the head work. The
command area is on both sides of the river with in the villages.The command area has
some undulating topography on the sides of the command and a little sloppy area on
the tail of the command. Generally the slope of the area is from 2-10%. Therefore, the
furrow alignment, planting geometry and irrigation application method has to be
considered. (Tefera, 2012)
1.5 Geology
The weir site is located at a point where straight flow regime is found, by considering
the required head for irrigating the identified command area. At this location, silty
clay surface geology is obtained, with weathered basalt stones available in close
proximity. The overall condition at the selected weir axis is considered suitable for
planning and constructing a diversion structure.
The subsurface geology at the weir location is best described by the Geological Cross
section map shown below (adopted from the Engineering Geological report). The
foundation condition for the structure will be highly weathered rock formation
dictating a design for pervious condition.
1.6 Soil
In all the test pits taken at the command area the depth of the soil is very deep which
is greater than 2 m. The command area is highly dominated by clay soil. (Tefera,
2012)
2. HYDROLOGICAL ANALYSIS
All water resources system must be planned for future hydrological events for which
the time of occurrence can be forecasted. In order to forecast the hydrological events,
data is necessary. The available data is daily heaviest rainfall of 23 years.
For Geddii project area, however, finding representative data was difficult in nearby
locations. The closest metrological stations found were that of Bonga and Chira
towns, located 34 and 26 kms away respectively. These stations yield sufficient data.
Other stations were reported to exist closer to the project. However, either the
available data was of short duration, or incomplete or both. Hence the hydrologist
analysis is limited to the use of the above two stations, namely bonga station and
Chira station.
The flood forecasting is based on data from Chira station, because it is located closer
to the project area, as compared to the other station. (Tefera, 2012)
2.2 Climates
The nearby meteorological stations around the project area are Chira and Bonga,
which are about 26 km north east and 34 km south west of the project site
respectively. Since chira station is an agronomic station, most of the climatic variables
were taken for the study. Only rainfall and temperature data was used from Bonga
station. In this case, Chira station is assumed to represent meteorological parameters
required for the estimation of evapotranspiration (Temperature, Relative Humidity,
Wind speed and Sunshine Hours).
The mean maximum and minimum temperature of the project area is 27.36 and
12.31oc respectively. The mean annual temperature of the project site is 19.83oC. The
temperature of the project area is estimated from Bonga station. Maximum
temperatures of greater than the mean occur from November to April, and minimum
temperatures less than the mean occurs from November to February and The average
annual rainfall at Bonga Station is about 2997.8 mm.
Monthly wind speed variation of the project site is from 0.77 to 0.98 m/sec. The
yearly average is 0.86 m/sec. The average daily duration of sunshine hours at Chira is
6.1 hours. Sunshine hours duration is maximum in the dry season, October to April,
and minimum in the rainy season May to September. The maximum sunshine hours
duration of 8.16 hours occurs in January. The average relative humidity varies from
about 66.70% in February to 82.09 % in July. Relative humidity is the maximum in
July and August. The yearly average is 73.21%. The daily maximum rainfall data was
used from 1985 to 2007 was used for peak flood estimation. The data source is the
National Meteorological Services Agency (NMSA).These data have been taken from
Chira meteorological station. (Tefera, 2012)
The available water source for Gedi irrigation scheme is Gedi River, which contains
plenty of water all over the year.and it is mainly a spring source(very clear water)
located in the upper watershed.
Flow measurement was carried out on the stream. A fairly appropriate site was found
about 100 meters downstream of the selected weir site. Using a float-method, flow
rate was measured to be 175 liters per second. (berhe, 2012)
Hydrologic processes such as floods are exceedingly complex natural events. They
are result of a number of component parameters and are therefore very difficult to
model analytically. For example, the floods in a catchment depend upon the
characteristics of the catchment‟s, rainfall and antecedent conditions, each one of
these factors in turn depend upon a lots of constituent parameters. This makes the
estimation of the flood peak a very complex problem leading to many different
approaches.
Due to the lack of flow (discharge) data we are forced to analysis the peak daily rain
fall for computation of peak discharge.
The prediction of peak flows from rainfall over a catchments involves estimation of
daily maximum rainfall for a given return period and conversion of the daily
maximum rainfall to run off hydrograph at the desired location.
Table 2-1 Maximum daily rainfall Values of 23 years for Meteorological station of
Gedi
year of record 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996
Daily Heaviest 46.6 52 46.7 62.5 40 70 70.3 36.1 44.5 54.3 40.1 70
Rainfall
year of record 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
Daily Heaviest 70.5 55 50.8 44.5 54.5 40 47 50.3 38 45.6 40
Rainfall
Outlier test
This test helps to avoid those data lie out of the range in between the lowest datum
and the highest datum .The lowest datum and the highest datum are calculated as
follows.
Let ………………………….………….…..…….2. 1
Lowest datum
Highest datum
Where YL = ……...........………………....……2. 2
YH = ………..……….……...…………..2. 3
Therefore the smallest datum is 29.785 mm. Since there is no any data lower than this,
all the available data can be if they satisfy condition in next step.
To analyze the maximum discharge expected in T years we can use the frequency
distribution function listed below, but the data in hand may fit to only one of them.
Therefore, before employing the methods it have to be checked for the fittest one.
Some of the commonly used frequency distribution functions for the prediction of
extreme maximum values are;
I. Normal distribution method
II. Gumbel distribution method
III. Log-Pearson type III distribution method
IV. Log-normal distribution method
Table 2-2 Guide line for selecting return periods for different hydraulic structure
Taking return period of 50 years (subramanya, 1994)the design rainfall for the project
area can be determined as follows.
W =√ ( ) = 2.797
Therefore, KT = 1.9603
̅ = 50.839
=√
It is one of the widely used probability distribution function for estimation of peak,
maximum rain falls, wind speed etc and expressed by the equation,
̅ ……………………………………………2. 5
Where XT = annual maximum of mean flow of T year return period
KT = frequency factor and expressed as,
n-1 = standard deviation of the sample size.
̅
. . . …………………………………………..…………2. 6
. .. . . . . . . . . . .. . …………………….………2. 7
√∑ ̅̅̅
( )
= 3.902
KT =
XT = ̅ +K n-1
= 50.839+3.121*11.0523
= 86.317 mm
III. log- Pearson type III distribution method
In this method the flow data is first transformed in to logarithmic form (base ten) and
the transformed data is then analyzed. If X is the variety of random flow series then
the series of Z varieties where, Z are obtained for this series for any recurrence
interval T.
.2. 8
̅ ………………. . . . . . . . . . ….. . . . . . . . ……. . . . . . . . . . .2. 9
Where, kz = a frequency factor which is a function of T and the coefficient of
skewness, Cs
z= standard deviation of Z variety sample.
∑ ̅
= √
∑ ̅
Cs = . .………………………………..………… . . . 2. 10
Table 2-4 log- Pearson type III distribution method detail calculation
= 39.02832/23
= 1.696883
∑ ̅
z= √
=√ = 0.091
∑ ̅
Cs = .
= = 0.43
Therefore, ̅
= 1.696883+2.276 *0.091
= 1.904mm
XT = 10Zt = 101.904
=
80.168mm
IV. Log-Normal Distribution Method
Log-normal distribution is a special type of Pearson type III distribution with C s = 0,
i.e. from table (4A) in the annex for Cs =0 and T50, Kz = 2.054
̅
= 1.884
XT = 10Zt = 101.884
= 76.524mm
Table 2-5 Summary of the results of all methods
Estimation method Maximum mean rain fall(mm)
predict the highest water level that occurs average once every T years ,where T is the
selected return period of the discharge . The Qmax. Determines the water afflux on
the weir and hence the height of the weir, wing walls and the cross bridge is estimated
.It also gives information to determine the height of dykes if required.
The following methods can be used to estimate the magnitude of peak flood.
1. Rational Method
2. Empirical Method
3. Unit Hydrograph Technique
The rational formula is found to be suitable for peak flow prediction in small
catchments areas of up to 50km2.The equation of rational method is given by;
. . . . . . ……………………………………2. 11
( ) ……………………..…………2. 12
√
( )
√
2) Rainfall Intensity, I
The rainfall intensity, I, is the average rainfall rate, in inches per hour, for a storm
duration equal to the time of concentration for a selected return period .Rainfall
intensity, duration curve and frequency curves are necessary to use the Rational
method. Itcp =125mm/hr( from graph in annex 1E ) that is a function of return period
and time of concentration
3) Runoff Coefficient, C
The runoff coefficients for different land uses within a watershed are used to generate
a single, weighted coefficient that will represent the relationship between rainfall and
runoff for that watershed.The ground cover and a host of other hydrologic
abstractions considerably affect the coefficient. Recommended coefficients for
various land uses based on soil type and land slope parameter is given in ( in the
annexes 1F) C=0.3
Therefore the peak discharge is calculated as follows
The empirical formula used for the estimation of peak flood are essentially regional
formula based on statistical correlation of the observed peak and important
catchment‟s properties. To simplify the form of the equation, only a few of the many
parameters affecting the flood peaks are used. For example, almost all the formulae
use the catchment‟s area as a parameter affecting the peak flood and most of them
neglect the flood frequency as a parameter. In view of these the empirical formula are
applicable only in the region for which they were developed.
E.g. Dr. Admassu′s empirical formula is one of the applicable for some part of
Ethiopia.
T = return period
Cv = the average coefficient of variation
= 0.38 for most catchment.
The empirical formula method is not convenient for the determination of peak flood
of Gedi River.
A unit hydrograph is defined as the hydrograph of direct run-off resulting from one-
unit depth (1cm) or rainfall excess occurring uniformly over the basin and at a
uniform rate for specified duration in hours, (Subramanya, 2000). This method is
convenient for watershed areas ranging 25-5000km2. The proposed watershed area for
the gedi project (Gedi River Basin) is out of range, and also this method requires a
large number of observed data, for which more number of gauging stations required to
install in the watershed. The unit hydrograph method is not convenient for the
determination of peak flood of Gedi River.
The SCS peak flow method calculates peak flow as a function of drainage basin area,
potential watershed storage and the time of concentration. This rainfall-runoff
relationship separates total rainfall into direct runoff, retention, and initial abstraction.
Assumptions
Basin should have a fairly homogenous CN values
CN should be 40 or greater
Ia /p should be between 0.1 and 0.5
TC should be 0.1 and 10 hr
Basin should have one main channel or branch with nearly equal time of
concentration
Neither channel nor reservoir routing can be incorporated
Fp factor is applied only for ponds and swamps that are not in the tc flow path
……………..........................……………..2. 15
…………………………………….…………2. 16
from annexes1G
Coefficients,c0, c1,c2 are
C0 = 2.54004
C1 = -0.61624
C2 = -0.15691 from annexe 1G
Peak flow using equation
( )……………...…….……………2. 17
( )
= 0.264767 m3/s/km2/mm
There are no vital requirements of crop than water. It has a number of useful functions
in the process of plant growth, it is the important constituents of plants. The following
are the main functions of irrigation water. It acts as a solvent for nutrients. Water
forms the solution of the nutrients and this solution is absorbed by roots. Thus, water
acts as the nutrients carrier. The irrigation water supplies moisture, which is essential
for the chemical action, which is with in the plant leading to its growth. The irrigation
water supplies moisture, which is essential for the life of bacteria, which are
beneficiary for plant growth. Water acts as an active reagent in photosynthesis and
hydrolysis.
Factors that affect the water requirements of a plant are;
Type of soil
Type of plant
Metrological variants like:
Sunshine,
Temperature,
Humidity,
Rainfall and wind.
Water is the critical input for obtaining maximum production of a particular crop
which has its own tolerance limits of soil moisture variation that do not affect its
yield. The moisture availability in the root zone of the crop could be maintained
within the crop tolerance limits by adopting water management practice.
Crop Water requirement is the depth needed to meet the water loss through
evapotranspiration of a disease free crop growing in large fields under restricting soil
condition including soil water and fertility achieving full production potential under
the given growing environment (FAO, Guide Lines for computing crop water
requirement, Irrigation And Drainage Project Paper 56, 1994)
The knowledge of total crops water requirement is important in determining the crops
needed. The major things needed are the following:
o Loss through evaporation
o Loss through transpiration
o Plant metabolism
Selecting suitable crop in relation to the available water supply and climatic condition
of an area is very essential step in crop water demand assessment.
Generally crop selection is based on the following variables:
Suitability of soil– the selected crops should give a maximum possible yield
wit little or no additional inputs which will increase the soil nutritive value
and provide adequate drainage facility during high impoundment.
Method of irrigation
Climate – the climate should be suitable for crops
Availability of labor & farm machineries
Water requirement – It should be considered so that availability of water to
meet the plant needs is ensured
Market & profit – priority should be given to those high markets.
Socio economic aspect value
Farmers‟ preference
Yield response factor and water utilization efficiency.
Taking the above variables into consideration, the following crop types were selected
for Gedi Irrigation Project: Maize, ,Haricot Bean, Spiceses Vegetable and
fruits(Onion, pepper ,potato carrot, cabbage) and Coffee . (Tefera, 2012)
Type of soil:-Detail soil survey should be conducted to determine the suitable type of
crop for a particular land.
Climatic conditions:-Crops requiring more water should be grown in the when
rainfall is available.
Value of crop:- As far as possible, the crops which have high market value should be
grown.
Socio-economic aspects:- While deciding the cropping pattern, the socio-economic
aspects and specific requirements of the region should be considered.
Generally there are two cropping seasons for a year season:
Season one
Season two
The crop allocation has been based on the soil data taken from the field to be
irrigated. Crops are allocated to suit a particular soil so that maximum amount of crop
production is obtained on the basis of this. There for the various crops are allocated
using the optimization technique. It is a system by which one obtains maximum profit
from a given plot of land by subtracting all the costs involved during its production
the benefit that would be obtained. Since the important data such as crop yield, labor
required per hectare & labor price per day from local people for computation of the
net benefit was not available.
Table 3-1Selected crops, planting date & land allocation
Planting Crop Area Area Harvesting
S.No Crop type date duration (%) (ha) date
1 Maize 10, Mar 125 69 55 12,julay
2 Haricot bean 15, Mar 90 16 13 12,jun
3 Coffee 01, julay 365 15 12 30,jun
4 Onion 20,Sep 120 35 28 17,jan
5 Potato 15,Sep 130 25 20 22,jan
6 Cabbage 10,Oct 165 10 8 23,mar
7 Carrot 15,Oct 100 10 8 22,Jan
8 Pepper 10,Sep 125 5 4 12,jan
Season 1 crops (wet season crops) Season 2 crop (dry season crops)
Maize Onion
Haricot bean Potato
coffee Cabbage
Carrot
Pepper
Coffee
3.2.2 Optimization
Optimization is the technique that helps to find the condition that to gives maximum
profit or minimum costs. This method has a wide range application in many
engineering problems.
The optimization technique in our case is needed to allocate the selected crops over
the total irrigable land to satisfy farmers need in other words, the technique helps to
decide what amount of area out of the total irrigable land certain should occupy so as
to give maximum benefits.
In this project, the goal is to maximize the benefit by optimally allocating the area for
each crop. Therefore, optimization refers to an economical decision. But to do the
optimization problem the given data is not sufficient and we done by the given data
on the feasibility report.
Where field conditions differ from the standard conditions, correction factors are
required to adjust ETc.The crop coefficient is used to relate the potential
evapotranspiration (ETo) to the consumptive use of the crop (ETc). It can be
presented as;
i. Initial stage –germination and early growth whether the soil surface is not
or hardly covered by the up to 10% ground cover.
ii. Development stage-runs from end of initial stage to attainment of
efficient full ground cover. Effective full cover for many crops initiation of
flowering.
iii. Mid season stage-runs from attainment of effective full ground cover to
time of start of maturing.
iv. Late season stage- runs from end of mid season stage until full maturing
or harvesting.
Steps needed to arrive at the Kc values for different growing stages are as follows
Establish planting or growing date from local information or from practices in similar
climatic zones. Determine total growing seasons and length of crop development
stages from local information or literatures. Kc for initial stage predict irrigation
and/or rainfall frequency for predetermined ETo; obtain Kc value from graph of ETo
verses assumed irrigation interval and plot Kc value or it may be selected from table
for known humidity and wind speed values. (FAO, 1994) Kc for mid season –For a
given climate (humidity and wind), select Kc value from table and plot as a straight
line. Kc for late season stage –For time of maturity (harvest within few days) select
Kc values from table as above. Assume a straight line between Kc values at the end of
mid season and at the end of growing season. Development stage- Assume a straight
line between Kc values at the end of initial stage to start of mid season stage.
Table 3-3 growing stage (days) and Kc values of the proposed crops season one
Planting Base
Crop date Initial dev Mid Late Initial Mid late period
Maize 10, Mar 20 35 40 30 0.3 1.2 0.35 125
Haricot
bean 15, Mar 20 30 30 10 0.5 1.05 0.9 90
coffee 01, julay 60 90 120 95 1 1.1 1 365
Table 3-4 growing stage (days) and Kc values of the proposed crops season two
Planting
Crop date Initial dev Mid Late Initial Mid late Base period
Onion 20,Sep 15 25 60 20 0.45 1 0.85 120
Potato 15,Sep 25 30 45 30 0.5 1.15 0.75 130
Cabbage 10,Oct 40 60 50 15 0.7 1.05 0.95 165
Carrot 15,Oct 20 30 30 20 0.7 1.05 0.96 100
Pepper 10,Sep 30 35 40 20 0.6 1.05 0.9 125
Coffee 01, julay 60 90 120 95 1 1.1 1 365
(FAO-33, 1994)
The water requirement of crops may be contributed from different sources such as
irrigation requirement, effective rainfall, soil moisture storage and ground water
contributions.
…………………..…………………….3. 2
Where, CWR = crop water requirement
IR = irrigation requirement
ER = effective rainfall
S = carry over soil moisture in the root zone
GW = ground water contribution
Factor affecting crop water requirement:
Amount of precipitation
Temperature
Day light hour
Stage of growth
Humidity
Wind velocity
Quality of water
Soil characteristic
The knowledge of the total water requirement is essential to know the
i. The total volume at water to be stored in the reservoir ( demand)
ii. The area that can be irrigated with available and usable volume or discharge
iii. To decide the economics of the project
iv. To assess and recover charge far water supplied
v. To compare the utilization and efficiency at the project
vi. To assess and recover charges for water supplied
( )
………………………………3. 3
The pen-man monteith method is done using the computer software cropWat 8
windows ver. 4.3 as follows for the available climatic data‟s.(Annex 2A)
Table 3-5 Summary of the result of effective rainfall calculated using different
methods in mm
Fixed USDA
Month Total percentage Dependable Empirical method
January 41 32.8 14.6 15.5 38.3
February 78 62.4 38.4 74.6 68.3
March 146 116.8 92.8 122.2 111.9
April 199 159.2 135.2 159.3 135.6
May 204 163.2 139.2 162.8 137.4
Jun 218 174.4 150.4 172.6 142
July 182 145.6 121.6 147.4 129
As can be seen from the Table 3.5, the highest effective rainfall was given by fixed
persentegel methods and The lowest was given by dependable method.
In general, as the rain intensity is high, more will be lost in the form of runoff and less
will reach the root zone of the crop and vice versa. Based on this, dependable method
gives conservative value of effective rain fall. Thus the one calculated by dependable
is adopted.
B. Ground water contribution (GW)
The actual contribution from the ground water table is dependent on the depth of
ground water table below the root zone and capillary characteristics of soil. For clayey
soils the rate of movement is low and distance of upward movement is high whole for
a light textured soil the rate is high and the distance of movement is low.
C. Carry over soil moisture (S)
This is the moisture retained in the root zone between cropping seasons or before the
crop is planted. The source of this moisture is either from rainfall that means
according before sowing or it may be the moisture that remained in the soil from past
irrigation
Table 3-6 Irrigation requirement
crope Etcpeak (mm/day) remark
Maize 4.7 annex 2F
Haricot bean 4.1 annex 2E
Coffee 5 annex 2D
Onion 3.68 annex 2G
Potato 4.21 annex 2H
Cabbage 4.61 annex 2I
Carrot 3.87 annex 2J
Pepper 3.83 annex 2K
It is the ratio between water directly available to the crop and that received at the field
inlet. It is expressed as
Ea= where, Ea=application efficiency
It is the ratio between water received at the field inlet and that received at the inlet of
the block of fields. It is expressed as
Eb= Where Eb = Field canal efficienc
NIR
FIR …………………………………………………………….3. 6
Ea
Where;Ea = Application efficiency.
The total amount of water applied through irrigation is termed as gross irrigation
water requirement. In other words it is net irrigation requirement plus loss in water
application and other losses. The gross irrigation requirement can be determined for
field, for a farm, for an outlet, command area or for an irrigation project, depending
on the need, by considering the appropriate lo
Where; NIR = Net irrigation requirement
Ep = project efficiency
To estimate the gross irrigation requirement of the project it is important to know the
efficiency with which the project is to operate. The project efficiency is the product of
other efficiencies such as conveyance, application and field channel efficiency. These
efficiencies are described in the following sections.
sses at various stages of the crop.
NIR
GIR ………………….……………………..…………………………3. 7
Ep
The maximum net amount of water that can be supplied per irrigation is expressed by
taking account that only part of the soil is wetted.
It is the time gap between two successive or consecutive irrigations. Irrigation should
be applied on time because delayed irrigation could cause considerable reduction in
crop yield, particularly at stages when the crop is sensitive to water stress. Irrigation
interval should take into account the soil water depletion requirement of the crops
which vary with evaporative demand, rooting depth, soil type and other factors.
T= d(gross)/ETc peak
Scheduling of irrigation application is very important for successful plant growth &
production. Water is not applied randomly at any time & in any quantity. Irrigation
scheduling indicates how much irrigation water has to be given to the crop, & how
often or when this water is given. How much & how often water has to be given
depends on the irrigation water need of the crop.
in mm/day 17.4 12.9 9.5 0.9 1.2 1 1.5 0 0 3.1 8.6 11.3
in l/s/h 0.07 0.05 0.04 0 0 0 0.01 0 0 0.01 0 0.04
Irrigated area 15 15 84 15 69 16 69 0 0 15 15 15
(% of total area)
Irr.req.for actual area 0.43 0.36 0.04 0.02 0.01 0.02 0.01 0 0 0.08 0.2 0.28
(l/s/ha)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Precipitation
deficit
1 Carrot 75 0 0 0 0 0 0 0 0 0.8 35 70.8
2 CABBAGE 108.9 82.3 35.3 0 0 0 0 0 0 3.4 20.7 51
3 Potato 66.5 0 0 0 0 0 0 0 0 7.9 66.8 81.2
4 onion 49.7 0 0 0 0 0 0 0 1.5 10.2 51.8 65.2
5 Sweet 36.5 0 0 0 0 0 0 0 2 5.9 54.6 71.1
6 coffee 116.2 86.3 57.6 5.7 0 0 0 0 0 20.9 57.6 75
Net scheme
Irr.req.
in mm/da 2.3 0.8 0.4 0 0 0 0 0 0 0.3 1.7 2.3
in mm/day 71.7 21.2 12.2 0.9 0 0 0 0 0.6 9.4 51.8 70.1
in l/s/h 0.27 0.09 0.05 0 0 0 0 0 0 0.03 0.2 0.26
Irrigated area 100 25 25 15 0 0 0 0 40 100 100 100
(% of total area
Irr.req.for actual 0.27 0.35 0.18 0.02 0 0 0 0 0.01 0.03 0.2 0.26
area
(l/s/ha)
The peak net scheme irrigation requirement has been found to be 0.43l/s/ha in wet
season and 0.35l/s/ha in dry season .there for we adopte the maximum of the two (i.e.
0.43l/s/ha) in The total irrigable land of area was fixed as 80 ha during the feasibility
study of the project.
=129l/s =0.129m3/s
The delivery schedules highly depend on the field irrigation methods and field
irrigation requirements. The objective of a water delivery and distribution system is to
deliver water adequately, efficiently and reliably to the users there by improving
production.
In all the cases the system should deliver the required water that can sustain the field
crops within the irrigation interval (T).
The distribution system selected is adjustable flow and the soil of the area is clay soil
type. In this case variable flow rates will be diverted to the tertiary unit‟s .Adjustable
flow regulator is needed for the purpose
Irrigation water may be applied to crop by loading it on the field surface, by applying
it beneath the soil surface, by spraying it under pressure or by applying it in drops.
The common methods of irrigation are surface, subsurface, sprinkler and drip.
The water supply, the type of soil, the topography of the land and the crop to be
irrigated determine the correct method of irrigation to be used. Whatever the method
of irrigation, it is necessary to design the system for the most efficient use of water by
the crop. (Micheal, 1997)
The choice of surface irrigation method has many reasons in its favor; the more
important ones are summarized below
Surface irrigation suitable for an area under study, being within the Margin of
slop for any of surface irrigation methods.
It is a proven technique currently used in Ethiopia and also in the Study area.
The proposed crop (sugarcane)to be cultivated in the project area also suitable
for surface irrigation.
Capital cost than other methods which can managed with locally available
materials, but for pressurized irrigation technique , the materials are to be
imported From the five main surface irrigation method, furrow and basin
irrigation method is proposed under gedi irrigation project.
Generally, in a surface irrigation event has four distinct hydraulic phases can be
discerned:
Advance phase: the time interval between the start of irrigation and arrival of
the advancing (wetting) front at the lower end of the field.
Furrow irrigation refers to water that is discharged into and runs down small sloping
channels (called furrows or corrugations) which are cut or pressed into the soil. The
two most common furrow irrigation systems are the straight furrow irrigation and
graded furrow irrigation. Water infiltrates from the bottom and sides of furrows
moving laterally downward to wet the soil and to move soluble salts, fertilizers and
herbicides carried in the water.
As compared to other methods, the furrow method has several distinct advantages.
Water in the furrows contacts only one-half to one-fifth of the land surface,
thereby reducing pudding, and crusting of the soil, and evaporation losses.
Earlier cultivation is possible which distinct advantage in heavy soils is.
The method reduces labor requirements in land preparation and irrigation so
economical.
Furrow can be adopted to use, without erosion, on wide range of natural sloped lands.
use of both water and energy resources for the varieties of crops and farming
practices.
One of the purposes of design of surface irrigation systems is to facilitate operational
practices so that the system can be managed and operated according to the plan and
the desired goal can be achieved.
Furrow spacing
Furrow can be spaced to fit the crops grown and the type of machines used for
planting and cultivation. Crop like potatoes, maize, cotton and sugarcane are planted
60 to 90cm apart between all furrows. Furrows should be spaced close enough to
ensure that water spreads to sides into ridge and the root zone of the crop to replenish
the soil moisture uniformly.
Table 4-1furrow infiltration and inflow rate
Maize 75 x 30
Potato 80 x 30
Tomato 150 x 20
Pepper 60 x 40
Onion 60 x 40
Furrow slope
The slope or grade of the furrow is important because it controls the speed at which
water flows down the furrow.
A minimum furrow grade of 0.05% is needed to ensure surface drainage. In our case
we adopted that the furrow slope is 0.5% the study area.
As the furrow grade increases, the range of infiltration slows down and the side
spread of water into the crop ridge decreases, so that wastage may occur at the end of
the furrow.
Furrow Length
The optimum length of the furrow is usually the longest furrow that can be safely and
efficiently be irrigated. Long furrow are an advantage inter cultivation. The length is
too long; water soaks into deep at the head of the furrow by the time the stream
reaches the lower end. This result in over-irrigation at the upper end or under-
irrigation at the lower end.
The optimum length of the furrows is usually the longest furrow that can be
efficiently irrigated. It may be as short as 45m on soils which take up water rapidly or
as much as 300m or longer on the soils with low infiltration rate. The length of the
furrow may often be limited by the size and shape of the field.
Furrow Stream
The size of the furrow stream is the one factor which can be varied after the furrow
irrigation system has been installed. The size of the stream usually varies from 0.5 to
2.5 liters per second. To obtain the most uniform irrigation, the largest stream of
water that will not cause erosion is used in each furrow at the beginning of irrigation.
Its purpose is to wet the entire length of each furrow as quickly as possible, thus
enabling the soil to absorb water evenly through the entire furrow length. The
maximum size of irrigation stream that can be used at the start of the irrigation limited
by consideration of erosion in furrows, over topping of furrows and prevention of run-
off at the down steam end.
The maximum non-erosive flow rate is estimated by the following empirical equation.
Qm = 0.6/s (Micheal, 1997)
Table 4-3Relation of maximum non erosive flow rates to critical slope of furrows
The following parameters are used for design of the furrow system.
The parameter of the intake families: soil with similar infiltration
characteristics is based on one – dimension infiltration families. The
classification is based on one –dimension infiltration furrow irrigation by taking
in to account the wetted perimeter of the furrow and the furrow spacing. This
purpose the adjusted wetted perimeter is used for design.
Reduced inflow perimeter (P2): This is the furrow perimeter corresponding to
cut –back stream.
Advanced time (Ta): The time at which the advance water front (run in stream)
reaches a particular point.
Opportunity time (To): It is the difference of between the water fronts reaches a
particular point along the furrow and the time at which the tail records from the
same point.
Recession time (Tr): The time for out flow of water to stop after inflow at the
head of the furrow has ended in recession time.
Infiltration in furrow system and calculation of required infiltration time must
be handled differently than for other types of surface system. This is because
infiltration takes place on the wetted perimeter of the furrow and the adjusted
wetted perimeter is given by the following equation.
……………………………………..4. 1
In most cases, after the flow has stabilized and gets uniform, the hydraulic gradient is
equal to the furrow slop. A roughness coefficient of 0.04 is normally used for design
of furrow irrigation system. (Cuenca, 1989)
The advanced time (Ta): for a stream of water moving down the furrow is
given by
Ta = ( )…………………………………………..4. 2
Tn = ( ) ……………………………………….4. 3
…………………………………………………....4. 6
…………………………………………..4. 7
Ed = * 100 (>50%)……………………………………………….4. 11
If the value of deep percolation and distribution efficiency is greater than the standard
specification value, cut-back condition is necessary to minimize the deep percolation
of the water .In this condition some formula is modified.
Sample calculations for onion:
Parameters needed furrow design
Soil type-clay
Intake family for the given soil type, IF = 0.15
For IF =0.15;
A = 0.711 f = 7.34
B = 0.683 g = 1.414*10-4
C=7
Furrow spacing, W = 80cm
Furrow slope, S=0.5% (0.05 to 0.5% is recommended)
Furrow length, L=250m (max. is 370m for clay of s=0.5%)
Manning‟s roughness coefficient, n=0.025
Net irrigation depth, dn=50.4mm
Design parameter
Advance time
Ta = ( )=
P=0.265*(
dn = RAM*P*D RAM=80mm
p=0.63
D=1m
Dn=80*0.63*1=50.4
Where RAM-readily available moisture from CROPWAT8window version
P - Depletion factor
D - Root depth of the sugarcane
dn - net irrigation depth
Net infiltration time
Tn = ( )
( )
Tn= ( ]
Toavg=
dg =
davg = [
Dp =
Ed = * 100 (>50%)
Q2 = = = 0.5 l/s
P2 = 0.265 + 0.227
P2= =0.265
Tn =
⁄ ⁄
Tn =
Time of cut back
Tcb = Ta =7.404min
Time of cut off
Tco = Tn + Ta
Tco=81.99+7.404=89.403min
Average infiltration time
Tavg =
Tavg=
Davg=
Davg=34.87mm
Gross application depth
dg=
Distribution efficiency, Ed =
Still it is not greater than 50% therefore we use cut back flow conditions.
Output of cutback flow model
Irrigation scheme which utilize weir a barrage or a storage reservoir necessitates the
construction of network of canals. The entire system of canals (main and branches)
distributed over the field are to be designed properly for certain realistic value of
maximum discharge, that must pass through them so as to provide sufficient irrigation
to the command area; the success of the flow irrigation depends on the perfect design
of the network of canals
The design of canals is carried out in considerations of Kennedy‟s and Lacey‟s theory
which are based on the characteristics of sediment load i.e. (silt) in canal water.
The design consideration of irrigation canals naturally varies according to the type of
soil, again the velocity of flow in the canal should be critical (i.e., none silting and
scouring).
The alignment along the ridge line or water shade line is very good as the
water shed canal can irrigate the area on both the side. Moreover, cross
drainage work may be avoided.
The alignment should be such that the maximum area may be irrigated with
minimum length of the canal.
The alignment should not pass through the water logged area because the
canal may be collapsed due to the heavy moisture in the area.
The alignment should not pass through the sandy soil as the percolation in the
loss soil will be more and the duty of the soil will be less. (NNBasak, 1999)
2. Lacey’s theory
Lacey argue that a channel showing no silting no scouring may actually not be in
regime and he classify in to three regime conditions.
a) True regime
Artificially constructed channel having a certain fixed section and a certain fixed
slope and only full filling the requirements of, Q is constant, flow uniform, silt charge
amount is constant, silt grade is constant, type and size of silt is always the same and
channel is flowing through a material which can be scoured as easily as it can be
deposited, but in practices all the above listed condition can never be satisfied.
b) Initial regime and final regime
When only the bed slope of the channel varies and its cross section or wetted
perimeter remains unaffected , even the channel is can exhibit no silting no scouring
properties called initial regime. they can be achieved only a working stability due to
the rigidity of their banks, their slope and velocities are higher and cross sections
narrower than what would have been, if the side where not rigid. And regime theory is
not applicable to them, as they are in fact not the channel in alluvium.
If there is no resistance from the sides and all the variable such as perimeter depth,
slope etc. are equally free to vary and finally gate adjusted according to Q and silt
grade then the channel is said to have achieved permanent stability called final
regime. Regime theory is applicable to such a channel in which all variable are
equally free to vary, has a tendency to assume a semi-elliptical section.
Lacey‟s calculation procedure.
V= [m/s] …………………………………………………5. 1
( ) ……………………………………5. 2
Bed slope , S= * + 5. 3
Time factor =
Time factor = =2
= 0.1185 m3/sec
′
QdR
= 0.0556 m3/sec
The design of lined and aligned canal involves different practical and economical
consideration. (Basak, 1999)
In Geddi irrigation project B/D is used to design unlined canal
Data available:
Canal capacity (FSQ) =QpR =0.1185
Manning coefficient (n) =0.029 (for Earthen ) table 6.1
bed slope of the main canal (s) =
The cross section of the main canal varies as the distance of the canal increases. This
is because the design of main canal is hold by considering the amount of water
diverted through the off taking canal upstream of each division canals
b
d
2 1 z2
0.5
z
(b/d) recom. = 1.0, for Q ≤ 0.2 m3/s
The Manning-Strickler formula can be re-written as:
Q= f. km. d8/3. S0.5………………………………………5. 4
1
3 b
5
3
Q 8 z
d d
0.5 Where: f 2
f .k m .S b
0.5
2. 1 z 2
d
Values of factor f prepared as a function of b/d and z, i.e. the shape of the
cross section is shown below.
Table 5-6 Factor f-values of the shape of the cross section (Adapted from Meijer
1989)
b/d
0 1 1.5 2 3 4 6 8 10
z
0.5 0.184 0.898 1.32 1.76 2.68 3.62 5.55 7.51 9.48
1.25 0.668 1.48 1.92 2.38 3.30 4.25 6.18 8.14 10.11
1.5 0.836 1.66 2.10 2.56 3.48 4.43 6.36 8.31 10.28
2.5 1.50 2.34 2.78 3.23 4.15 5.09 7.00 8.93 10.88
=0.5*0.5+(0.5*0.52)
= m2
P b 2 y * 1 m 2 …………………5. 6
=0.5+2*0.5*√
= 1.618m
A
Then, R = 0.232m
P
Where y is flow depth, b is bottom width, m is side slope, A is the area of flow and P
is the wetted perimeter.
Fb = 0.20 + 0.15Q1/3
FB= 0.2+0.15*0.11851/3
= 0.27m
Check whether the flow velocity is within the permissible limit on range 0.41 to 1.67
for clay soil.
V=Q/A=0.1185/0.375=0.412 m/s This implies that our canal does not cause
either silting or scouring.
Q 8 z
d d
0.5 Where: f 2
f .k m .S b
0.5
2. 1 z 2
d
Values of factor f prepared as a function of b/d and z, i.e. the shape of the
cross section is shown below.
A by my 2
=0.205*0.205+(0.5*0.2052)
= m2
P b 2 y * 1 m2
=0.205+2*0.205*√
= 0.664m
A
Then, R = 0.095m
P
Where y is flow depth, b is bottom width, m is side slope, A is the area of flow and P
is the wetted perimeter.
………………………………………………………………………………………………………….
Fb = 0.20 + 0.15Q1/3 5. 7
FB= 0.2+0.15*0.0561/3
= 0 0.257m
Check whether the flow velocity is within the permissible limit on range 0.41 to 1.67
for clay soil.
V=Q/A=0.056/0.063=0.88 m/s This implies that our canal does not cause
either silting or scouring.
FB
B
Figure 5-1 typical cross section of main canal
Table 5-7 Summary of right main canal calculation
CANALS area Qd
m s l/se m3/s d B A P R FB TD V
0.5 0.003 RMC 55.13 118.53 0.12 0.50 0.50 0.38 1.62 0.23 0.20 0.70 0.41
0.5 0.003 RMC-R1 52.81 113.54 0.11 0.24 0.24 0.08 0.77 0.11 0.20 0.44 1.35
0.5 0.003 RMC-R2 51.56 110.85 0.11 0.23 0.23 0.08 0.76 0.11 0.20 0.43 1.34
0.5 0.003 RMC-R3 48.34 103.93 0.10 0.23 0.23 0.08 0.74 0.11 0.20 0.43 1.32
0.5 0.003 RMC-R4 46.66 100.32 0.10 0.23 0.23 0.08 0.73 0.10 0.20 0.43 1.31
0.5 0.003 RMC-R5 41.97 90.24 0.09 0.22 0.22 0.07 0.70 0.10 0.20 0.42 1.27
0.5 0.003 RMC-R6 39.72 85.40 0.09 0.21 0.21 0.07 0.69 0.10 0.20 0.41 1.25
0.5 0.003 RMC-R7 32.43 69.72 0.07 0.20 0.20 0.06 0.64 0.09 0.20 0.40 1.19
0.5 0.003 RMC-R8 27.62 59.38 0.06 0.19 0.19 0.05 0.60 0.09 0.20 0.39 1.15
0.5 0.003 RMC-R9 19.47 41.86 0.04 0.16 0.16 0.04 0.53 0.08 0.20 0.36 1.05
0.5 0.003 RMCR10 10.59 22.77 0.02 0.13 0.13 0.03 0.42 0.06 0.20 0.33 0.90
0.5 0.003 RMCR11 5.01 10.77 0.01 0.10 0.10 0.01 0.32 0.05 0.20 0.30 0.75
0.5 0.003 RMCR12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.20 0.20 0.00
CANALS area Qd
M s ha l/se m3/s d B A P R FB TD V
0.5 0.015 LMC 25.86 55.60 0.06 0.21 0.21 0.06 0.66 0.10 0.20 0.41 0.88
0.5 0.015 LMC-R1 23.70 50.96 0.05 0.20 0.20 0.06 0.64 0.09 0.20 0.40 0.86
0.5 0.015 LMC-R2 19.64 42.23 0.04 0.19 0.19 0.05 0.60 0.09 0.20 0.39 0.82
0.5 0.015 LMC-R3 17.52 37.67 0.04 0.18 0.18 0.05 0.57 0.08 0.20 0.38 0.80
0.5 0.015 LMC-R4 12.67 27.24 0.03 0.16 0.16 0.04 0.51 0.07 0.20 0.36 0.74
0.5 0.015 LMC-R5 7.55 16.23 0.02 0.13 0.13 0.03 0.42 0.06 0.20 0.33 0.65
FB
Q=Cd*A*
2 gh …………………………..5. 8
4 * 0.0527
d= 0.26 0.3m
Q 0.059
V2= 1.12m / sec
A 0.0527
v 64
f 64. ( for la min ar flow ) .
DV Re
=0.00026
he=0.5(v12-v22)/2g=0.00144
ho=0.5(v32-v22)/2g=0.00144
total head loss=hf+ho+he=0.00026+0.00144+0.00144=0.0032m
Q=Cd*A*
2 gh
√
H=0.0998<0.1& V2=1.12(1<V2<2m3/s) which is recommended for culvert
H = 0.24m
R.L of crest =U/S FSL-H
= 1704.93-0.24=1704.69m
Height of crest above D/S bed, d= crest level –D/S bed level
= 1704.69-1703.67=1.019m
Top width of crest wall, √
√
The assumed top width is correct and to be provided.
Bottom width ,
Where G = 2.24m
1) Cistern
The depth of cistern;
m
RL of cistern = d/s bed level –x = 1703.67-0.29=1703.38m
2) The length of cistern, √ √ = 0.13m
Impervious floor design
Maximum seepage heads Hs =Crest level- D/S bed level
Hs=1704.69-1703.67=1.02m
Total creep length, L= cHs,
Take Bligh creep coefficient, c=9
L= 9*1.02=9.18m
Depth of U/S cut off
( ) …………………………………………5. 9
Thickness of floor=0.77m
b) Residual head at end of D/S floor
( ) m
Q=C*L*H 2
…………………………………………..5. 10
Where, Q=discharge over rectangular weir sill
(m3/s)
C=discharge coefficient, use 1.77
gate
Inlet Q
QRTC1 Q Out
let
Figure 5-3 Division box
The intake canal of turnout should be large enough and set low enough to
carry the design flow.
The minimum height of water surface of supply canal over the top of the get
opening should consider the head loss
Q=Cd*A* 2 gh ……………………………………………………………5. 11
Where, A=Cross sectional area of the pipe.
Cd=coefficient of discharge, (=0.8 for submerged flow)
H=head available, (assumed H=0.1m)
4 * 0.0037
d= 0.0691 0.1m
Q 0.0042
V= 1.135m / sec
A 0.0037
=0.0012
Water level can be set to the target value by rising and dropping the gates units the
target is set.
In Geddi command area we prefer to provide manual regulator (gates) at tertiary
canals and farm out lets. This is for the reason that to safe the economic cost of the
design and without any extra knowledge the users can operate easily by manual.
Excess rainfall lies on the ground surface infiltrates title the ground. since the mean
annual rainfall in the area (2997.8mm). .
When this rainfall exceeds the crop water requirement drainage has to be applied.
There are two types of drainage system
1. Surface drainage
2. Sub-surface drainage
Surface drainage is needed for project area to remove excess rainfall where
sub-surface drainage is not economically feasible and to collect and dispose of surface
irrigation runoff.
In our project, surface drainage system has been found to be very suitable due to its
lesser cost, easy construction and feasible management condition.
Surface drainage problem occur in nearly flat area, uneven land surface with
depression or ridges preventing natural runoff and in areas without outlet. Soils with
low infiltration rates are susceptible to surface drainage problem. Surface drainage is
intended for safe removal of excess water from the land surface through land shaping
and canal construction. Function of the system may be considered as:
-Collection systems
-conveying systems
-Outlet system
Water from the individual field is collected and is then removed through a system to
the outlet. Generally, surface drainage is required for:-
The removal of storm rainfall where the subsurface drainage is not
economically feasible.
The collection and disposal of surface irrigation runoff.
The collection and disposal of drainage in deltaic area.
designing drainage systems. Generally, the bed slope is determined from Top map of
the irrigable area.
Drainage coefficient (DC)
The drainage coefficient is the amount of water that must be removed from soil
surface in order to have sustainable agriculture. It depends on depth of irrigations,
method of irrigation, leaching requirement and soil characteristics. There are different
methods for estimating drainage coefficient. Those are:
1 %MAR method
Where: MAR= mean annual rainfall
For GEDI irrigable area, MAR =2997.8mm.
DC = 1 %* 2997.8mm
DC 29.978mm
Hudson 1983 ‟s method
In this method the following two conditions are considered
If MAR <1000 mm, DC = 10 mm/day
If MAR >1000 mm, DC = MAR/100 mm/day
Since MAR 2997.8 mm, DC = 29.978mm/day
From the above two methods the value of the drainage coefficient (Dc) for the
maximum one is taken for design of the drainage canal. DC 29.978mm/day
In this project area we design two main canals, which it gives direct to tertiary canal.
In order to prevent our command area from water logging, we design tertiary drainage
canal on each tertiary unit on the left side &e right side the command area.
The capacity of the drainage canal is determined based on the area coverage of
tertiary canals.
A =Q /√ =0.015862
Since, Qd 0.00897264 e
For trapezoidal canal
-The area of the drain section is given by
A BD mD2
-Wetted perimeter of the drain section
P B 2D 1 m 2
-R is hydraulic radius of the drainage canal
A BD mD 2
R
P B 2D 1 m 2
Where:
B - The bottom width of the drainage canal
D - The depth of water in the drainage canal
m- The side slope of the drainage canal
R -The mean hydraulic radius of drainage canal
A - The area of drainage section.
P- The wetted perimeter of the drain section
A BD mD 2 D
R
P B 2D 1 m 2 2
Then,
Since m=0.5
- By solving the above equation,
B = 1.236D
-by substituting this value in eq (2), eq (3), and eq (4)
A=BD+
=1.236D*D+
A=2.236
P=B+2D√
P=3.472D
R= ⁄ = √
R =
R=0.5D
From equation (1)
A =2.236 = √
=0.015862
By Solve the equation, D = 0.375m
Form equation (6), B =1.236D
By solving B=1.236*0.375m
B=0.464m
The hydraulic radius, R
R=0.5D
R= 0.5*0.375
=0.188m
The wetted perimeter (p)
P=3.472D
=3.472*0.375
P=1.302m
Area of cross-section, A
A=2.236
= 2.236*
A=0.341
The velocity of flow v , in the drain can be determined from Manning‟s equation
V=
V=0.186m/sec -----------------------ok the calculated 'v' in permissible 'v'
The discharge of flow (Manning)
Q =A*V=0.3
Drain
type Qdr slope n m B(m) Area( P(m) D(m) FB
(m3/sec
LDrc1 0.00074946 0.0002 0.025 0.5 0.464m 0.012 1.302m 0.0732 0.1
LDrc2 0.00094376 0.0002 0.025 0.5 0.464m 0.014 1.302m 0.0799 0.1
LDrc3 0.00046494 0.0002 0.025 0.5 0.464m 0.008 1.302m 0.0613 0.1
LDrc4 0.00073558 0.0002 0.025 0.5 0.464m 0.012 1.302m 0.0728 0.1
LDrc5 0.0016828 0.0002 0.025 0.5 0.464m 0.022 1.302m 0.0992 0.1
LDrc6 0.00090212 0.0002 0.025 0.5 0.464m 0.014 1.302m 0.0786 0.1
LDrc7 0.00087436 0.0002 0.025 0.5 0.464m 0.013 1.302m 0.0776 0.1
LDr8 0.00166546 0.0002 0.025 0.5 0.464m 0.022 1.302m 0.0989 0.1
A =Q /√ =2.236 = 0.035
Since, Qd =0.02
From this Eq, D= 0.265m
Form the above equation (6), B =1.236D
B=0.328m
The hydraulic radius, R
R=0.5D
R=0.133m
Area of cross-section, A
A=2.236
= 2.236*
A=0.157
The velocity of flow v , in the drain can be determined from Manning‟s
equation
V=
V=0.147m/sec.----------------ok the calculated 'v' in permissible 'v'
The discharge of flow (Manning)
Q= A*V = 0.157
RMDr 0.02 0.0002 0.025 0.5 0.0328 0.157 0.133 0.265 0.1
FB
Diversion head works are structures constructed across a river (head of a canal) to
facilitate a regulated and continuous diversion of water into the off-taking canal. The
obstruction is of smaller in comparison with the dam. It raises the water level locally
and supports the water against its face.
A diversion head work serves the following function
1. It raises the water level on its upstream side.
2. It regulates the supply of water in to the canal.
3. It controls the entry of silts in to the canal.
4. It creates temporary storage up stream of the weir
cross the river where canals take off a series of such pick-up weirs may be
constructed to utilize the available water
3. Intake weir: They are constructed as a part of head works. They raise the water
level by obstructing the river flow. The water is then diverted to the canal.
4. Waste Weirs: They are generally used as spill ways for reservoirs. It protects the
reservoir and the main storage dam. (NNBasak, 1999)
Under Gedi irrigation project pick up (vertical drop weir) weir is selected because of
the following reasons.
The simplicity for construction.
The relation to the function of the weir.
The skill and the experience of the workers availability.
In the present situation also vertical drop pick up weir is selected in
Gedi irrigation project.
The rating of the downstream channel section is computed using Manning‟s Equation.
The section data and roughness values used are shown in figure below. (Tefera, 2012)
1712
1708
1706
1704
1702
0 10 20 30 40 50 60 70
Distance, L(m)
The average bed slope of the river is estimated to be 0.01m/m. The estimated rating
for the above cross section at this slope is shown in figure below.
Q vs H
1.2
depth of flow water (m)
1
0.8
0.6
0.4
0.2
0
0 5 10 15 20 25 30
discharge ,Q(m^2/s)
water way
It is the width provided at the site for the river water to flow. In other word, it is the
length of the weir. Approximate water way to provide between the abutments may be
calculated from lacey‟s regime perimeter formula.
√
Where Pw – is the wetted perimeter at the site at the river, but in this case it denotes
the length of the weir between the abutments in meter and denoted by L.
√
Q – The design discharge in m3/s
√ = 25.135 but we take the actual bank width that is 15m
Discharge intensity
Regime velocity
Under the flood condition when the weir expected to attain regime condition
where R = scour depth
,
Approach velocity head = 0.083
weir
ha = velocity head.
Hd = water head above the crest of the weir
Pond level
The water level of the canal corresponding to full supply discharge is full supply level
(FSL).
FSL of the canal depends on the following factor.
Design discharge of the canal.
Head loss in the head regulator and turn out.
Topography of the area.
The FSL of the canal immediately downstream of the head regulator =1703.9
maximum seepage head for the worst condition ( WL on u/s at pond level and no
tail water ) from :
A) Top Width
II. =0.150m,
However the actual width of the base should be determined as the maximum of the
following situation.
, where
Equating the over turning and the resisting moment, we get B=0.79 by trial and error
…………………. a
…………………… b
H 3 dH 2 D3
where D = tail water depth
6 2 6
6
The resisting moments are obtained from case 1 , based on the level of water level on
the d/s side .If D is large use case 2 and if D small, use case 1. In our case D is small
and hence we adopt case 1 i.e no flow condition.
B can be determined equating Mo and Mr.
Finally, the largest B from the three cases has to be adapted.
1.006 / 10
iii. Length of upstream impervious floor ( u).
Ld (L = total creep length, B = base width.)
this implies that doesn`t need upstream floor length but we provide
a nominal floor length 3m
Therefore the total floor length
Generally nominal thickness is provided on the u/s as weight of water counter balance
uplift
On downstream: Bligh‟s theory: determine the residual pressure at any point and,
4 h
3 G 1
Khosla‟s theory: determine the pressures at the key point of the piles and linear
( h)
variation in between them more accurate.)
G 1
Thicknesses at some 4 points are determined & the thickness is reduced in steps for
ease in construction
Hs = 0.96m L = 13.96m
Thus, residual pressure at the too of the weir
Hs
L
0.96
13.3
Floor thickness at ( ) ( )
0.96
13.3
4
h / G 1 4
0.51/ 2.24 1 .
3 3
Provide a thickness of 0.6 m for the next 1m ( from 1 to 2 m from the toe)
0.96
13.3
4 hc
( )
3 G 1
0.96
13.3
4 hc
( )
3 G 1
Provide a thickness of 0.4m for next 1m (3 to 4m from toe )
Check by Khosla‟s theory
( safe)!!
√ √
Uplift pressure
U/s pile, b = 8.9m. d =0.2 m
b
D/s pile, d2 = 2 8.9 / 2 4.45, = 2.88
d2
100 ( 2)
E cos 1 40.95%
100 ( 1)
D cos 1 27.88%
a) Correction for thickness
d D D
1
b b
Effect of pile 2 on pile1: C = +19
1.57 0.052 0.052
C 19 * 0.257 %
8.9 8.9
Pressure, Pp = 0.37 +
0.909 0.37 * 4 0.61m.
8.9
h 0.61
Required thickness, t1 = = 0.51m <0.64m (safe).
G 1 2.2 1
Hydraulic jump is a phenomenon of rapidly varied flow at which the state of flow
changes from supercritical to sub critical. A hydraulic jump occurs only when the
upstream flow is supercritical (F1>1). At the hydraulic jump the energy of flow will
be lost.
Hydraulic jump on a horizontal surface
Y1 – depth before jump (pre jump depth)
Y2 - depth after jump ( post jump depth )
y1 and y2 are called conjugate depths of a hydraulic jump
To determine the water depth ,y1 the well known Bernoulli equation is used.
P+He=y1+
V1= =
Y13-2.07Y12+0.178=0
Y1 has three values
One negative root and has no any physical meaning
The other two represent the alternative depth for the same energy.the true
value is that Y1 must less than the critical depth, Yc, since the flow befor the
jump is supercritical.
By trial and error y1=0.318m
Critical depth is expressed by
q2
yc 3, yc criticalde pth
g
1.867 2
yc 3 0.575m
9.81
Therefore the actual value of y1 is 0.318m
V1= = =5.871m/s
v1 5.871
F1 = = = 3.324
gy1 9.81* 0.318
y2
y1 * 1 8F12 1
,
2
y2
0.318 * 1 8 * 3.324 2 1
1.344m
2
( y 2 y1 ) 3
Head loss, Hl ,
4 y1 y 2
(1.344 0.318)3
Hl 0.632m
4 * 0.318 *1.344
length of jump=5(y2-y1)
=5(1.344-0.318)=5.13m
Tw=1<Y2=1.344m in this case the jump will recede d/s to a point where the flow
condition allow the jump to occur. Since the river bed every hard, as per head work
geology, the rock can simply resist the expected scouring that might be caused by the
Points A B C D
Elevation of glacis 1704.31 1704.11 1703.91 1703.71
Specific energy = U/S TEL - RL 1.26 1.46 1.66 1.86
Depth (Y) 0.86 0.75 0.64 0.48
Energy of water surface 1705.17 1704.86 1704.55 1704.19
(Garge, 2003)
Know q and y1, F1 can be determined. Graphs are available between ( s for
3. Determine the horizontal distance of (x) of this point from the point p and then
evaluate the value of of different point, where y1 is the initial pre-jump depth.
4. Determine the value of of the different point from the graph for the value of F1
5. Determine the depth y for different points from value and obtained the water
surface level.
6. Join the water surface level to obtain the post joint profile
Where, y- water depth at different point, y1- initial depth
Computation
Consider four point M, N, O, &Q at distance 1m, 2m, 3m,&4m from the point P.
Fr1
Fr2 = 11.08
Table 7-2 Water surface profile after jump
S=0.21%=0.0021
Hd=He-ha=0.981
H=1.006
Yn=1
h (h+Hd) – yn=(1.006+0.981)-1=0.987
( xs 2 h) 2
y=
4h
Table 7-3 u/s water profile
x 10 50 100 150 200 250 300 350 400 450 500 550 600 650
y 0.97 0.88 0.79 0.7 0.61 0.53 0.46 0.39 0.33 0.27 0.22 0.17 0.13 0.09
Lever arm
Code Dimension Load (about the toe) Moment
Width Depth Vertical Horizontal R Positive Negative
0.5*1.01*1.01* 4.969*0.335
Pw 1.006 1.006 0.000 9.81=4.969 1/3*1.006=0.335 0.000 =1.667
1*1.01*22 22.142*1.5
W1 1.000 1.006 =22.142 0.000 1/2+1=1.500 =33.213 0.000
0.5*1*1.01* 11.071*0.667
W2 1.000 1.006 22=11.071 0.000 2/3*1=0.667 =7.381 0.000
Pu 0.000 0.000 0.000 0.000 1.333 0.000 0.000
0.5*8.243*1.01*
Ps 8.243 1.006 0.000 0.632=1.684 1/3*1.006=0.335 0.000 0.565
Sum 11.249 4.026 33.213 6.652 4.171 40.594 2.232
Ka = 1.305
= 18 KN / m3 [Moudi]
= = 18KN/m3 – 9.81KN/m3 = 8.19KN/m3
I) Check for over turning
∑
∑
= 18.19 > 1.5 … OK!
̅ =∑ ∑
= = 1.16
∑
[Moudi]
Therefore the weir is safe against over stress
Sill of the under-sluice pocket is kept at or slightly above the deepest river bed and
about 0.9 to 1.8m below the sill of the canal head regulator.
The length of the under-sluice pocket between the divide wall and the head regulator
may be taken as 1.5times the upstream length of divide wall.
However, this length is governed by discharging capacity of the under-sluices, which
should be sufficient to enable them to serve their main functions, described above.
The discharging capacity of under-sluices may be selected as follows:
i. They should be able to ensure sufficient scouring capacity for which the
discharge
capacity should at least twice the full supply discharge of the main canal at its
head.
ii. They should be able to pass the dry weather – flow and low floods during the
months excluding the rainy season .without the necessity of dropping the weir
Shutters.
iii. They should be able to dispose of 10 to 15% the high flood discharge during
several floods. (Garge, 2003)
Assume the under sluice passé about 15% of the total discharge
- Qu = under sluice discharge = 0.15*28=4.2m3/s
Water way length(assume 2m). (Basak, 1999)
qu = 4.2/2m = 2.1
L= √ √ m
R = 1.35 = 2.17m
= 1703.9-0.241 = 1703.659m
The water way for regulator is for the full supply discharge of 0.119m3/sec can pass
through it.
Discharge Q through the regulator is given by [Garge 2003]
Q= √ √
Where Cd1 = 0.577 & Cd2 = 0.8
h1- depth of D/S water level in the channel above the crest
Hv - head due to velocity
H - difference of water level U/S and D/S of the crest.
Neglecting Velocity head hv we get
Q= √ √
H = 0.55
H1=0.241
0.119 = √ √
0.119 = 1.114B
B= 0.107m adopt B= 0.1m
Provide 2 piers of 1.5m thickness each on the side (Garge 2003)
Overall waterway of the regulator = 1.5*2+0.1=3.1m
D. Head Regulator for Left Main Canal
- Full supply of off taking canal = 0.056m3
- Full supply of canal = Pond level-Modular head
= 1704.45m - 0.55m =1703.9m
- Water depth in the canal at head = 0.205m
- Safe exit gradient for canal bed material = 1/6
- Crest level of head regulator = FSL-water depth
= 1703.9-0.205 = 1703.695m
The water way for regulator is for the full supply discharge of 0.056m3/sec can pass
through it.
Discharge Q through the regulator is given by [Garge 2003]
Q= √ √
Where Cd1 = 0.577 & Cd2 = 0.8
h1- depth of D/S water level in the channel above the crest
0.056 = √ √
0.056 = 1.024B
B=0.116 m adopt B= 0.12m
Provide 2 piers of 1.5m thickness each on the side. (Garge, 2003)
Overall waterway of the regulator = 1.5*2+0.12=3.12m
Height of tunnels generally varies from 0.5 to 0.6m for Sandy River and 0.8 to 1.2m
for boulder Stage River. (Garge, 2003)
Height of tunnel (h) =crest level of head regulator-crest level of under sluice
=1703.659-1703.5=0.2m
Total clear width =
Design Procedure
Maximum discharge = 28m3
Highest flood level (HFL) =1705.488m
River bed level = 1703.5m
Water way between guide bank = 15m
The length of guide banks U/S of weir = 1.25*L (Garge 2003)
= 1.25*15=18.75m
The length of guide banks D/S of weir = 0.25*L (Garge 2003)
= 0.25*15=3.75m
The radius of the curved head (upstream portion) may be kept
=0.45*L=0.45*15=6.75m
The upstream end of guide bund may, therefore, be curved in such a way as to make
an angle of 60
a) Cross section of the guide bunds for d/s section
The HFL at wire site = 1705.488m
Assuming a free board of 0.3m,
The top level of guide bund = 1705.488 + 0.3 = 1705.788m
To be move safe and making an allowance for future statement etc; let us
Height of the bund above river bed level = 1705.788 – 1703.5 = 2.288m
Assume top width of 0.5m and side slope 1.5H:1V
b) Cross section of the guide bunds for u/s section
Height of bund over river bed = 2.288m + afflux
= 2.288m + 1m = 3.288m
Provide top width of 0.5m on side slope 1.5H:1V
c) Design of stone of pitching and apron
The sloping water side of entire guide bund as well as the sloping rear side the curved
portions are pitched with one man stone (i.e. a stone which can be lifted by one
person-weighting 40 to 50kg) or concrete block (apron)
Thickness of stone pitching on the side (t)
( )
( )
The structural analysis of guide banks should be taken for the worst condition (i.e.
during empty condition)
Force acting on the wall of guide bank
- Weight of the wall (w1,w2)
- Weight of the bank fills (w3)
- Active Rankin force (pS)
A. D/S Guide Wall
∑ ∑
Check for slidin Fs ∑
= ∑
= 7.57 > 1.5 ………ok!
∑ ∑
Check for over turning Fs ∑ ∑
= 22.24> 1.5 ………… ok!
e= ̅ = 5.432/2-2.52= 0.2
8. COST ESTIMATION
A project is economically feasible if the total benefit of the project exceeds the total
cost of the project, (i.e. benefit cost ratio of the project should be greater than one).
So economic analysis is essential for YEDI PROJECT to decide whether the project is
feasible or not. The initial investment cost is determined by carrying out quantity
surveying.
The impact of the proposed action will be identified by using the existing
environment as a control. A change in the environment is the difference in the
environment between the control, the existing environment and the new environment,
the altered condition caused by a project.
When to conduct EIA
EIA should be conducted as early as possible in the project and program to influence
planning, designing, implementation and operational management. Hence, EIA should
be conducted at all stages of development.
Flood control
Socio –Economic impact
The use of pesticides and fertilizers to increase the yield should be carried out with
care not to impair the normal condition. Farmers should be given proper extension
service on how to use chemical fertilizer and other agrochemical inputs to avoid the
misuse.
On the command area, the prominent fertilizer used are urea and DAP. Some
pesticides are also used. This will bring also an increase in the use and generation of
nutrient organic compounds and pathogens. This will result in pollution of
environment and water use problems. The discharge of drainage water polluted by
pesticides and fertilizers may have some effect on the water quality of domestic water
source if they mix.
Pollution of Water quality
Irrigation may contribute to the problem of water pollution in various ways. During
construction period, earthwork activities for construction of the proposed conveyance
canal and irrigation infrastructure are likely to yield high sediment loads.
Where as, during the operation phase, the sediment rating, down stream of the dam
will be much lower due to sediment deposing in the reservoir. All these changes may
bring changes to the water quality.
Public health
During construction period there will be increased risk of the transmission of endemic
diseases and sexually transmitted diseases including HIV/Aids, due to increased
movement and interaction between the local community and the construction force.
During the operation of the irrigation project, malaria transmission could intensify and
cause a major risk to public health.
Water logging
Through scientifically not correct, farmers think that irrigating more water will give
more yields and this excess water may percolate in to the ground water and raise the
water table. When the water table raise, salinity and water logging occurs. This will
degrade the fertile land.
Biological & ecological changes
The observation made in the project area, the cultivated land is covered with trees,
forests, bushes & shrubs. But with the increase of fertile land demand for farming &
different related needs this resource is will be endangered. This in turn will have a
remarkable negative effect on the ecological attributes. Due to the implementation of
the project in the farmer‟s area, there might be decreased grazing land, hazarded to the
wiled & domestic animals to cross large canals.
10.2 Recommendations
Project specific information such as appropriately scaled topographic maps
was not available and hence detail field level design and total cost estimation
could be roughply estmaited ..
For this particular project, the crop land allocation to maximize the benefit
by optimally allocating the area for each crop not designed. Due to the lake of
yiled data of the project but we done by the given data on the feasibility
report.
Since land leveling is a pre-requisite for any surface method of irrigation, due
consideration may also be given for land leveling job on the project area.
Special attention for proper operation and maintenance of the surface method
of irrigation as well as the surface drainage to have the efficient irrigation
system are also to protect the project area from water logging condition
REFERENCES
Abebe.D. (2011). (irrigation structure handout).
Arora. (2003). Irrigation, Water Power And Water Resources Engineering.
Arora, K. (2002). Irrigation, Water Power And Water Resources Engineering, Standard
Publishers. NAIA Saraf,Delhi.
Basak, N. (1999). Irrigation Engineering.
Chow, C. t. (1983). applied hydrology.
Cuenca. (1989). Irrigation Theory and Practice. universty of Arizona USA.
DELFT. (1992). principle of hydrology.
FAO. (1994). Guide Lines for computing crop water requirement, Irrigation And Drainage
Project Paper 33.
FAO. (1994). Guide Lines for computing crop water requirement, Irrigation And Drainage
Project Paper 56.
FAO. (1994). Guide Lines for computing crop water requirement, Irrigation And Drainage
Project Paper 33. FAO.
Garge, S. (2003). ,Irrigation Engineering And Hydraulic Structures.
Micheal, A. (1997). Irrigation theary and practice .
NNBasak. (1999). Irrigetion Engineering.
Sahasrabudhe, J. (1994). Irrigation Engineering and Hydraulic Structures.
subramanya. (1994). engineering hydrology,2nd edition.
Tefera, B. (2012). Gedi Small Scale Irrigation Project Feasibility Report.
Page 118
Annex 1 HYDROLOGY
A) Table of kn value for different sample size (Chow, 1983)
sample size n Kn sample size n Kn
10 2.036 37 2.65
11 2.088 38 2.661
12 2.134 39 2.671
13 2.175 40 2.682
14 2.213 41 2.692
15 2.247 42 2.7
16 2.279 43 2.71
17 2.309 44 2.719
18 2.335 45 2.727
19 2.361 46 2.736
20 2.385 47 2.744
21 2.408 48 2.753
22 2.429 49 2.76
23 2.448 50 2.768
24 2.467 55 2.804
25 2.486 60 2.837
26 2.502 65 2.866
27 2.519 70 2.893
28 2.534 75 2.917
29 2.549 80 2.94
30 2.563 85 2.961
31 2.577 90 2.981
32 2.591 95 3
33 2.604 100 3.017
34 2.616 110 3.049
35 2.628 120 3.078
36 2.639 130 3.104
140 3.129
Page 119
B) Table of Reduced mean in Gumbel’s extreme value distribution, N= sample size
Page 120
D) Table of Kz=F(Cs,T) for use in Log-Pearson Type III Distribution
Page 121
E. Intensity-Duration curve for various recurrence intervals (Adopted from ERA
manual 2003)
Page 122
E) Table Runoff coefficients for Rational formula
Page 123
F) Table Coefficients for SCS peak Discharge Method
Page 124
G) Table of Ia/P for selected rainfall depths and Curve Numbers
Page 125
ANNEX 2 CROPWAT
Common Data
A) MONTHLY ETO PENMAN-MONTEITH DATA
(File: D:\crop\BONGA.pen)
Country: Location 51 Station: BONGA
Altitude: 1725 m. Latitude: 7.21 °N Longitude: 36.28 °E
Month Min Temp Max Temp Humidity Wind Sun Rad ETo
°C °C % km/day hours MJ/m?/day mm/day
January 10 29 59 95 7.1 18.4 3.85
February 11 29.7 62 104 6.4 18.4 4.03
March 11.9 29.2 67 181 6.3 19.1 4.5
April 12.7 28.1 71 130 6.6 19.6 4.2
May 12.6 27.4 75 112 6.2 18.4 3.83
June 12.4 25.9 76 104 5.3 16.7 3.43
July 12.4 24.3 74 95 3.7 14.5 3.03
August 12.4 24.6 72 104 4.1 15.4 3.22
September 11.7 25.8 75 86 5.1 17.2 3.43
October 11 27.8 79 95 6.7 19 3.74
November 10.3 28.1 69 78 7.1 18.7 3.65
December 10.3 28.4 66 69 7.4 18.5 3.56
Average 11.6 27.4 70 104 6 17.8 3.71
B) SOIL DATA
(File: C:\ProgramData\CROPWAT\data\soils\BLACK CLAY SOIL.SOI)
Soil name: BLACK CLAY SOIL
General soil data:
Total available soil moisture (FC - WP) 200.0 mm/meter
Maximum rain infiltration rate 30 mm/day
Maximum rooting depth 180 centimeters
Initial soil moisture depletion (as % TA 50%
Initial available soil moisture 100.0 mm/meter
C) DRY CROP DATA
crop
Stage initial develop mid late total
Length (days) 60 90 120 95 365
coffee Kc Values 1 1.1 1
Rooting depth (m) 1.8 1.8 1.8
Critical depletion 0.5 0.5 0.5
Yield response f. 1 1 1 1 1
Cropheight (m)
Length (days) 20 35 40 30 125
Kc Values 0.3 1.2 0.35
Maize Rooting depth (m) 0.3 1 1
Critical depletion 0.55 0.55 0.8
Yield response f. 0.4 0.4 1.3 0.5 1.25
Cropheight (m) 2
Length (days) ` 30 30 10 90
haricot bean Kc Values 0.5 1.05 0.9
Rooting depth (m) 0.3 0.7 0.7
Critical depletion 0.45 0.45 0.6
Yield response f. 0.2 1.1 0.75 0.4 1.15
Cropheight (m) 0.4
Length (days) 15 25 60 20 120
Kc Values 0.45 1 0.85
Onion Rooting depth (m) 0.6 0.6 0.6
Critical depletion 0.25 0.25 0.25
Yield response f. 0.45 0.45 0.8 0.3 1.1
Cropheight (m)
Length (days) 25 30 45 30 130
Kc Values 0.5 1.15 0.75
potato Rooting depth (m) 0.3 0.6 0.6
Critical depletion 0.25 0.3 0.5
Yield response f. 0.45 0.8 0.8 0.3 1.1
Cropheight (m) 0.6
Length (days) 40 60 50 15 165
Kc Values 0.7 1.05 0.95
Cabbage Rooting depth (m) 0.25 0.5 0.5
Critical depletion 0.45 0.45 0.45
Yield response f. 0.2 0.4 0.45 0.6 0.95
Cropheight (m) 0.4
Length (days) 20 30 30 20 100
Kc Values 0.7 1.05 0.95
Carrot Rooting depth (m) 0.3 0.6 0.6
Critical depletion 0.25 0.3 0.5
Yield response f. 0.45 0.8 0.8 0.3 1.1
Cropheight (m)
Length (days) 30 35 40 20 125
Kc Values 0.6 1.05 0.9
pepper Rooting depth (m) 0.25 0.8 0.8
Critical depletion 0.2 0.3 0.5
Yield response f. 1.4 0.6 1.2 0.6 1.1
Cropheight (m) 0.7
D) CROP WATER REQUIREMENTS
ETo station: BONGA Crop: coffee
Rain station: BONGA Planting date: 01/08
Date Day Stage Rain Ks Eta Depl Net IrrDeficit Loss Gr.Irr Flow d(net) T (Interval)
mm fract. % % mm mm mm mm l/s/ha mm l/s/ha mm day
1-Aug 1 Init 0 1 100 51 183 0 0 458 53 274.74 56
11-Feb 195 Mid 0 1 100 51 183 0 0 457 0.27 274.08 55
31-Jul End End 0 1 0 3
Date Day Stage Rain Ks Eta Depl Net IrrDeficit Loss Gr.Irr Flow d(net) T (Interval)
mm fract. % % mm mm mm mm l/s/ha mm l/s/ha mm day
15-Mar 1 Init 0 0.9 91 53 33 0 0 82.1 9.51 49.26 12
12-Jun End End 0 1 100 12
N) Table format: Irrigation schedule MAIZE (Grain)
Date Day Stage Rain Ks Eta Depl Net IrrDeficit Loss Gr.Irr Flow d(net) T (Interval)
mm fract. % % mm mm mm mm l/s/ha mm l/s/ha mm day
12-Mar 3 Init 0 1 100 56 38 0 0 94.7 3.65 56.82 12
12-Jul End End 16 1 100 4
T
Date Day Stage Rain Ks Eta Depl Net IrrDeficit Loss Gr.Irr Flow d(net) (Interval)
mm fract. % % mm mm mm mm l/s/ha mm l/s/ha mm day
20-Sep 1 Init 0 0.67 67 51 61 0 0 152.6 17.66 91.56 25
2-Dec 74 Mid 0 1 100 27 31.9 0 0 79.7 0.13 47.82 13
30-Dec 102 End 0 1 100 25 30.3 0 0 75.8 0.31 45.48 12
14-Jan 117 End 0 1 100 26 31.1 0 0 77.7 0.6 46.62 13
17-Jan End End 31.6 1 100 2
T
Date Day Stage Rain Ks Eta Depl Net IrrDeficit Loss Gr.Irr Flow d(net) (Interval)
mm fract. % % mm mm mm mm l/s/ha mm l/s/ha mm day
15-Sep 1 Init 0 0.67 67 52 31.7 0 0 79.2 9.17 47.52 11
22-Nov 69 Mid 0 1 100 30 36 0 0 90.1 0.15 54.06 13
16-Dec 93 Mid 0 1 100 30 36.3 0 0 90.7 0.44 54.42 13
6-Jan 114 End 0 1 100 41 49.7 0 0 124.2 0.68 74.52 18
22-Jan End End 0 1 100 34
T
Date Day Stage Rain Ks Eta Depl Net IrrDeficit Loss Gr.Irr Flow d(net) (Interval)
mm fract. % % mm mm mm mm l/s/ha mm l/s/ha mm day
10-Oct 1 Init 0 0.91 91 55 27.6 0 0 68.9 7.98 41.34 9
10-Jan 93 Dev 0 1 100 47 45.7 0 0 114.2 0.14 68.52 15
26-Jan 109 Mid 0 1 100 48 48.1 0 0 120.3 0.87 72.18 16
11-Feb 125 Mid 0 1 100 46 46.4 0 0 116 0.84 69.6 15
23-Mar End End 0 1 100 7
R) Table format: Irrigation schedule Carrot
T
Date Day Stage Rain Ks Eta Depl Net IrrDeficit Loss Gr.Irr Flow d(net) (Interval)
mm fract. % % mm mm mm mm l/s/ha mm l/s/ha mm day
15-Oct 1 Init 0 0.67 67 53 32.4 0 0 80.9 9.36 48.54 13
26-Dec 73 Mid 0 1 100 32 38.4 0 0 96 0.15 57.6 15
12-Jan 90 End 0 1 100 41 49.2 0 0 123 0.84 73.8 19
12-Jan End End 4.9 1 100 24
T
Date Day Stage Rain Ks Eta Depl Net IrrDeficit Loss Gr.Irr Flow d(net) (Interval)
mm fract. % % mm mm mm mm l/s/ha mm l/s/ha mm day
10-Sep 1 Init 0 0.62 62 52 27.1 0 0 67.8 7.85 40.68 11
12-Jan End End 0 1 100 49
Annex 3
A) Take of sheet
S/ N Un Leng Wind Depth or Ar Quant
N Description o it th th Height ea ity
Weir Body , cut off and
1 D/S Apron
1.
1 U/S cut off
Excavation of Hard rock 1 m3 3 15 0.4 18.0
Lean concrete 1 m3 3 15 0.05 2.3
1.
2 D/S cut off
Excavation of Hard rock 1 m3 5 15 1.5 112.5
Lean concrete 1 m3 5 15 0.05 3.8
1.
3 D/S Apron
Excavation of Hard rock 1 m3 5 15 1.5 112.5
1.
4 Weir Body
Excavation of Hard rock 1 m3 2 15.00 0.58 17.4
3
Lean concrete 1 m 9 15.00 0.05 6.8
3.9
Reinforced concrete 1 m3 15 1 58.7
1.5
Masonry 1 m3 15 9 23.850
m^
Form work 1 2 3.9
2 Divide Wall
Excavation for hard rock 2 m3 0.116 0.2 0.5 0.023
Masonry 2 m3 0.116 0.2 1.036 0.024
3 Under Sluice
Excavation for hard rock 2 m3 1.43 0.5 0.4 0.6
3
Lean concrete 2 m 1.43 0.5 0.05 0.1
6 Upstream Guide Wall
Excavation for hard rock 2 m3 5.49 0.5 3.59 19.7
3
Lean concrete 2 m 5.49 0.5 0.05 0.3
Masonry 2 m3 5.49 0.5 3.59 19.7
7 D/S Stream Guide Wall
Excavation for hard rock 2 m3 3.932 0.5 2.6 10.2
Lean concrete 2 m3 3.932 2.4 0.05 0.9
3
Masonry 2 m 3.932 0.5 2.6 10.2
3
Total masory m 53.8