METHOD STATEMENT - Laydown activity
METHOD STATEMENT - Laydown activity
Project
HATCHERY STRUCTURAL RETROFIT WORKS
14-Outer Region, NOEM, Kingdom of Saudi Arabia
PMC: CONCESSIONNAIRE:
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant Doc nº: WT2201-NAB-CW-MST-A00-0003
MST for Installation of 3-
D Printed Precast Rev 00
Concrete Segments for
Site Laydown Page 2 of 11
Nafees Muhammad
METHOD STATEMENT FOR HAND GRINDING
01 02.02.2025 Ahmad Ibrahim
WORKS
Submission Details
Page 2 of 11
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant Doc nº: WT2201-NAB-CW-MST-A00-0003
MST for Installation of 3-
D Printed Precast Rev 00
Concrete Segments for
Site Laydown Page 3 of 11
Table of Contents
1 Introduction ......................................................................................... 4
2 Scope of Work ...................................................................................... 4
3 References........................................................................................... 4
4 Abbreviations: ...................................................................................... 5
5 Roles and Responsibilities....................................................................... 6
6 Tools and equipment ............................................................................. 8
7 Manpower............................................................................................ 9
8 Procedure: ........................................................................................... 9
9 QUALITY CONTROL ..............................................................................10
10 Health Safety and Environment ..............................................................10
11 Attachments .......................................................................................11
Page 3 of 11
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant Doc nº: WT2201-NAB-CW-MST-A00-0003
MST for Installation of 3-
D Printed Precast Rev 00
Concrete Segments for
Site Laydown Page 4 of 11
1 Introduction
The purpose of this Method Statement is to identify the methods, procedures,
resources, plant, equipment, quality control and HSE measures to be planned, prepared
and implemented for the Scope of work to be carried out for ‘LAYDOWN WORK’ activity
at Zuluf Water Treatment Plant.
2 Scope of Work
The purpose of this method statement is to describe the detailed procedure for the safe and
efficient methodology to be applied for installation of 3-D printed concrete segments for site
offices.
• Site Cleaning and Preparation
• Levelling, Grading and Compaction
• Installation of Fence.
• Installation of 3-D printed concrete segments for site offices.
3 References
Page 4 of 11
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant
MST for Installation
Doc nº: WT2201-NAB-CW-MST-A00-0003
of 3-D Printed
Concrete Segments Rev 00
for Site Laydown
Page 5 of 11
4 Abbreviations:
• EPC CONTRACTOR - FISIA ITALIMPIANTI S.p.A (FIT)
• CONSORTIUM - ALMAR WATER SOLUTIONS- AL JOMAIH ENERGY AND WATER
• Main Contractor - COMPANY (AWS WATER PURIFICATION COMPANY)
• FINAL CLIENT - SAUDI ARAMCO
• NAB - National Building General Contracting Co. (SUBCON/ SUPPLIER)
• GM - General Manager-NAB
• SQM - Site Quality Manager
• SPM - Sr. Project Manager
• PM - Project Manager
• SM - Site Manager
• CM - Construction Manager
• SCM - Sr. Construction Manager
• SE - Site Engineer
• QAQCE - QA/QC Engineer
• QCI - QC Inspector
• IFC - Issued for Construction
• NOI - Notification of inspection
• ITP - Inspection and Test Plan
• MSA - Material Submission Approval
• HSSE - Health, Safety, Security and Environment
• TBT - Tool Box Talk
• MSDS - Material Safety Data Sheet
• CSSP - Contractor Site Safety Program
• CEMP - Construction Environmental Manual Plan
• PPE - Personal Protective Equipment
• ANSI - American National Standard Institute
• OSHA - Occupational Safety and Health Administration
• ISO - International Organization for Standardization
• SASO - Saudi Standards, Metrology and Quality Organization
• SBC - Saudi Building Code
• CSM - Construction Safety Manual
• ASTM - American Society for Testing and Materials
• ACI - American Concrete Institute.
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant
MST for Installation
Doc nº: WT2201-NAB-CW-MST-A00-0003
of 3-D Printed
Concrete Segments Rev 00
for Site Laydown
Page 6 of 11
Page 6 of 11
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant
MST for Installation
Doc nº: WT2201-NAB-CW-MST-A00-0003
of 3-D Printed
Concrete Segments Rev 00
for Site Laydown
Page 7 of 11
• QC inspector will confirm the storage and place of the material on site as per project
requirements.
• Ensure MEP clearance & signed off by concerned site engineer (if any) prior to proceed
with installation.
• Prior to final inspection request for consultant, check and ensure required work is
completed.
• He will keep records of all inspections and testing related to the activities.
Page 7 of 11
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant
MST for Installation
Doc nº: WT2201-NAB-CW-MST-A00-0003
of 3-D Printed
Concrete Segments Rev 00
for Site Laydown
Page 8 of 11
• Assign a competent guide to assist drivers delivering materials to the site and lay down
areas;
• Ensure that NO work requiring permit approval is permitted, unless proper permit
approval is obtained.
• Raising the IR/MIR according to nature of job or specific site requirements
Page 8 of 11
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant
MST for Installation
Doc nº: WT2201-NAB-CW-MST-A00-0003
of 3-D Printed
Concrete Segments Rev 00
for Site Laydown
Page 9 of 11
• Total Station
• Hammer
7 Manpower
• Construction Manager
• HSE Officer
• QC Engineer/Inspector
• Civil Engineer/Supervisor
• Surveyor
• Foreman
• Lab Technician
• Loader operator
• Dumper operators
• Grader Operator
• Roller operator
• Labor
8 Procedure:
8.1 Pre-Installation Checks and Site Preparation
• Review and approval of shop drawings and structural details. Permit to work shall be
obtained from FISIA Construction Department prior to start the excavation work. Before
starting of excavation work, dimension shall be marked on the ground
• Clear the site within the laydown boundary on flat and/or undulating ground surfaces.
• Verification of foundation levels and alignment points.
• Inspection of delivered precast elements for damages or defects
• Ensuring access and lifting space for installation
• Confirming availability of all required materials, tools, and equipment
Page 9 of 11
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant
MST for Installation
Doc nº: WT2201-NAB-CW-MST-A00-0003
of 3-D Printed
Concrete Segments Rev 00
for Site Laydown
Page 10 of 11
• The proposed fence line is to be staked out at intervals. Locations of gates, corners to
be identified and marked at site.
• A string shall be stretched and taut between these stakes.
• Measurement tape shall be laid along the string line.
• Markings to be made every required meters apart. This shall be the point for making
post holes.
• Incoming fencing material shall be inspected prior to installation at site
9 QUALITY CONTROL
• Inspection: Conduct thorough inspections at each stage (Pre-installation, fence
installation, during installation and post installation) of the process to ensure
compliance with supplier’s specifications and identify any defects or areas requiring
rework.
Page 10 of 11
CLIENT PROJECT COMPANY EPC CONTRACTOR Zuluf Water Proj. nº: WT2201
Treatment Plant
MST for Installation
Doc nº: WT2201-NAB-CW-MST-A00-0003
of 3-D Printed
Concrete Segments Rev 00
for Site Laydown
Page 11 of 11
11 Attachments
• JSA
• LAYDOWN AREA PLAN/DRAWING
Page 11 of 11