OP First Assignment
OP First Assignment
Index: 202103010
What is a network?
A network is a collection of people and / or things that are connected to each
other by some kind of relationship. Many kinds of entities can be part of a
network: people, projects, documents, events, organisations, cities,
countries, etc. And there are many kinds of relationships that can link such
entities, involving transmission or exchange of information, money, goods,
affection, influence, infection, etc.
By listing all your tasks in the table, you get a clear overview of all the steps,
which you can subsequently expand by adding information on sequence and
the time necessary to complete each activity.
While it is easy to predict the order of some activities, other tasks may
require more in-depth analysis, which will help you determine their order
more easily.
Once you have established the sequence of activities, you can represent
both serial and parallel activities in the diagram. Each event and milestone
should represent a node in the network, and you can use arrows to show
relationships between activities.
What distinguishes PERT from other techniques is its ability to deal with
uncertainty in activity completion time. There are three-time estimates this
model typically uses for each activity:
• Optimistic time – the shortest time in which the activity can be completed
• The most likely time – the completion time that has the highest probability
• Pessimistic time – the longest time in which the activity can be completed
After you have identified the time estimates, you can calculate the expected
time for each activity by using the following weighted average:
For example, imagine you are building a cottage. Drilling and planting the
posts have an optimistic duration of 7 hours, an expected duration of 10
hours, and a pessimistic duration of 12 hours. The optimistic duration is
counted once, the most likely time is counted four times, and the pessimistic
time is counted once. The entire sum is then divided by 6, and the weighted
average is 9,83. You perform this calculation for each event and then share it
by inserting it into the duration data column.
By adding the times for the activities and determining the longest path, you
create a critical path. The critical path involves the total amount of time
necessary to complete the project. The total project time doesn’t change if
activities outside the critical path speed up or slow down.
PERT Chart in Project Management
PERT helps project managers identify responsible departments, delegate
roles to their team workers, and track results. Gathering information from
multiple sources allows you to coordinate project activities and leverage
communication between departments easily. Through efficient planning and
decision-making, you encourage your team to truly invest their time and
energy into delivering the best results.
Start by listing all the functions or activities that need to be completed for
the project’s successful conclusion, also known as a work breakdown
structure. When created thoroughly, the work breakdown structure is a
roadmap that guides a team when completing projects .
Next, identify the order in which the tasks need to be performed. Some tasks
may depend on the completion of others before they can begin, while others
may be carried out concurrently. This step is crucial in understanding the
dependencies and relationships between tasks.
Assign a time estimate to each task. This should be the total time required to
complete each task from start to finish. Make sure to account for any
potential delays or issues that may arise by incorporating buffers or
contingency time into your estimates.
Two techniques that can help project managers accurately determine each
task’s duration are the forward and backward pass techniques:
Forward pass: Starting from the beginning of the project and moving forward
through the critical path diagram, calculate the earliest start time and finish
time for each activity. This helps determine the earliest possible project
completion date for the entire project.
Backward pass: Work your way backward from the project’s end date through
the CPM chart, calculating the latest start time and finish time for each
activity. This helps identify the latest possible project completion date for the
project and determines the amount of scheduling flexibility or slack time
available for each activity.
Using the information from the previous steps, draw a network diagram. This
visual representation should depict all the tasks, their sequence, and their
dependencies. Each task is represented as a node on the diagram, and the
arrows between nodes represent the task dependencies.
The critical path is the longest path from the start to the end of the project,
passing through all the essential tasks to the project’s completion. In other
words, the longest sequence of tasks determines the minimum time needed
to complete the project. On your network diagram, this is your critical path,
the longest duration from the initial to the final task.
The total float or slack is how long you can delay a task without postponing
the project’s completion. Tasks on the critical path will have zero float,
meaning they can’t be delayed without impacting the project timeline.
However, non-crucial tasks may have some float, allowing for some flexibility
in scheduling.
Within the overall float calculation is also free float, which is the amount of
time an activity can be delayed without delaying the start of its successor
activity.
Once the project is underway, closely monitoring the tasks on the critical
path is essential. Any delays in these tasks will directly impact the project
timeline. Regularly update and review the critical path to help identify
potential issues early and keep the project on track.