construction-cost-estimating-guide
construction-cost-estimating-guide
Introduction
This Reference Guide provides instruction for the creation and management of construction cost estimates for roadway
and bridge projects. This guide provides a framework of recognized and accepted processes and tools that each TxDOT
district can adapt and use as appropriate for their situation.
Contingency
Unknowns
Allowances
Unquantifiable
Areas of Work
Allowances
Quantifiable
Base Estimate
Knowns
Known
Quantities and Pricing
Risk and Contingency:
Cost estimation considers uncertainties and related risks early and often in the project
development process. Management uses identified risks and uncertainties to structure Contingency is meant
procedures that mitigate, eliminate, or account for the possible variation in the to protect the project
outcomes. against cost increases
• Contingency is needed in an estimate to account for the second type of that may arise when
known unknowns. risks become reality,
• Risk management practices and tools can assist in the calculation of not to cover overruns,
inflation, or allow for
appropriate contingencies to account for these costs.
scope creep.
By their very nature, risks have a probability of occurring and if they do occur, will
impact the project in a positive or negative way. A Project Contingency is used to
capture the cost impacts associated with risks.
Contingency funds are incorporated into a cost estimate to account for the risks
associated with the project.
Standard Deviation σ: A quantity calculated to indicate the extent of deviation from the mean.
(𝑃𝑃 − 𝑂𝑂)
σ=
6
Optimistic (O): Best-case scenario of activity durations/quantities/costs
Pessimistic (P): Worst-case scenario of activity durations/quantities/costs
C onfidence Level: The probability that the value for the activity falls within a specified range of values.
99.73
95.45
68.27
135
165
195
45
15
75
10
A tool to assist with the calulations and determination of the estimate confidence level is available at the following link:
https://txdot.sharepoint.com/:x:/r/sites/office-epmo/intranet/_layouts/15/Doc.aspx?sourcedoc=%7B802E7503-E4A7-4E44-9D37-
D940CD7DEC5B%7D&file=Risk-Based%20Cost%20Estimation.xlsx&action=default&mobileredirect=true
The following image is a snap shot of the tool that will assit with the three point estimating and determining the base estimate.
In this tool the known and identified items will be be entered at each phase of the project’s development. There are tabs for the
each stage to document the estimate.
Note: Considerations in determining the bid prices : geographic location, quantity of item, item availability, type of qty pricing
such as lump sum.
Appendix B : Determining Allowances:
Allowances are for the known items that you have that are not yet quantifiable. For example, it is known that a project will need
some traffic items ( pavement markers, signs, lighting); however those items are not just yet quantified. We will apply the same
concept of the most likely, optimistic outcome, and pessimistic outcome as we did in the Three Point for the Base Estimate.
The same tool that is used to determine the Base Estimate also has a section for determining the allowances as well. Below is a
snap shot of the tool being utlilzed to determine the allowancs for a project.
Figure 2, Risk Based Contigency Register, identifies the risk associated with the project that will have an impact to the
construction cost. Determine the probability of each Event Driven risk in the risk register. This accounts for the probability and
impact of that risk. The cost associated with the risk is then used to determine the contingency on a project. Like the Three
Point Estimating, we will look at the :
Most Likely (M) Outcome
Optimistic (O): Best Outcome
Pessimistic (P): Worst Outcome
The following spreadsheet tool can be used to determine the expected value of the risk. This tool is deivided out to assist with
developing the Risk Based Contingency for the different stages of project development.
The Link to Risked Based Contigency Tool: https://txdot.sharepoint.com/:x:/r/sites/office-
epmo/intranet/_layouts/15/Doc.aspx?sourcedoc=%7B802E7503-E4A7-4E44-9D37-D940CD7DEC5B%7D&file=Risk-
Based%20Cost%20Estimation.xlsx&action=default&mobileredirect=true