SD_RCL_CD_final
SD_RCL_CD_final
Version control :
Name Role
This Scope has been developed by documenting all input gathered from the business team by
scheduling meetings and workshops with the Business Process owners and Core team users
from RCL CD as well as from cross modular meetings. This document shows the business
requirements for Project’s commercial activities such tendering, project billing etc. in detail,
and serves as the basis for organization, configuration and development activities.
The Division also includes a Building and Civil Engineering Section which is responsible for
turnkey construction projects. It also provides general support services to electromechanical
operation and maintenance works, including building work, carpentry, plumbing, L V electrical
systems, gardening, pest control, janitorial and cleaning services, and purchasing services.
From its prime operational centres in Al Khobar, Jubail and Riyadh, the Rezayat Construction,
Maintenance and Engineering Division is able to provide
construction/maintenance/engineering services throughout the Kingdom and can respond
effectively to emergency situations, rapidly deploying experienced engineering and support
personnel to site.
The Purpose of this Scope, which is the main deliverable of a Requirement gathering Phase, is
to serve as conceptual master plan for the implementation of Sales and Distribution module of
SAP in RCL CD.
This Scope has been developed by documenting all inputs gathered from the core team by
scheduling meetings and workshops. The document shows the business requirements in
detail, and serves as the basis for organization, configuration and development in SAP.
Business Process
Expectations/ Improvements
Reporting/Information requirements
During the workshops, the business team was acquainted with the capabilities and
functionality of the SAP solution.
Confirm the understanding of the business process and scenario, which would form the
basis for system specifications
List requirements which cannot be addressed by the system
Form the basis for all subsequent activities to be conducted during the project
This document covers only an Overview of the to-be processes. The exact data on master data
fields, their statuses, order types – if not identified in scope, number ranges if not identified -
used in individual transactions shall be determined during the Realization phase
RCL NCC
RCL-CD RCL MD
This module is integrated with Project System (PS), Financial accounting (FI), Controlling (CO)
and Material Management (MM).
In RCL CD SD will be used to map the following processes for Project Sales
a) Prequalification
b) Inquiry Logging
c) Estimation and quotation preparation
d) Sales order processing
e) Project Billing
Bill of services will be used to map estimation process and quotation preparation process.
Once the contract is awarded the same Bill of Service will be used to map unit rate contract
process and also to map progressive billing based on the BOQ quantities.
Sales and Distribution is a component within the SAP that enables the Sales Process within
SAP System. In sales and distribution module, organization entities are important as it is a
platform for creation of master data, transaction data, SD reporting. The standard application
is set to control accessibility at sales organization, division level etc i.e. user assigned to one
organization structure will not be able to access data of another if the relevant rights are not
granted.
Controlling Area
REZ1
REZAYAT GROUP
Company Code
1041
RCL CD
The Organization Elements applicable for Sales and Distribution Module are:
1. Sales Organization
2. Distribution Channel
These organization elements are required in Sales and distribution to understand the
organization / division that is rendering the products or services to the customer. To capture
the revenue to be received at the company level, sales organization and division plays a vital
role.
SALES ORGANIZATION
1041 RCL CD
DISTRIBUTION CHANNEL
01 GOVERNMENT
02 QUASI GOVERMENT
03 PRIVATE COMPANY
04 INDIVIDUAL (Private No CR)
05 AFFILIATES / INTERCOMPANY
DIVISION
SALES OFFICE
Customer Master
Each sales organization is assigned exactly one company code. This way, the system derives
the company code for each accounting transaction originating from Sales. Below mentioned
Sales organization shall be created for RCL CD. The sales organization must be specified in all
sales documents. Following sales organizations will be defined in the SAP system:
The following distribution channels have been proposed for RCL CD, and those will be linked to
the following Sales Organization:
2.1.3 Division
This entity normally groups together saleable materials and services for the purpose of
responsibility and analysis.
The division is used for control and analysis purpose and can be assigned to multiple sales
organizations. The divisions will be assigned to the Sales Organizations engaged in relevant
business.
The following Divisions shall be defined for RCL CD:
RCL CD SD SCOPE Page 12
Sales
Division Name of the Division
Organization
1041
57 Maintenance Services
1041
58 Garage Services
1041
59 Short Term Projects
1041
60 Industrial Projects
1041
61 Building Maintenance Services
Commercial & Residential 1041
65
Projects
1041
66 Housing Maintenance Services
Janitorial & Chauffeuring 1041
67
Services
Sales Sales
Name of the Sales Office
Office Organization
1041 RCL CD – JUBAIL 1041
2041 RCL CD – YANBU 1041
3041 RCL ICC – KHOBAR 1041
The Sales Group will not be used by RCL CD as it is not required to map individuals who is
responsible for the sales.
2.2 Plant
An organizational unit serving to subdivide an enterprise according to production, procurement, maintenance, and
materials planning aspects. It is a place where either material is produced or goods and services are provided.
RCL CD SD SCOPE Page 13
Further details are covered under MM Module Blue Print.
Shipping Point is the key organization unit for delivering from sales and distribution module.
Any delivery from the respective plants to other companies will be through the Shipping point
defined for the plant.
The following shipping point will be created in the system for RCL CD as a technical
requirement, as the shipping point is mainly applicable for trading business.
Master data is the data about customers, products and services that remains constant over a
period of time. This data is carefully maintained by a responsible person in the organization
and forms the basis of all transactions.
Master data forms the basis of sales and distribution processing. Precisely maintained and
classified master data considerably simplifies and accelerates the operative processing in
daily business. A large amount of data is copied from the master records during business
transaction processing. The sales related masters to be maintained for Rezayat Project Sales
are:
• Customers
• Service Materials
• Bill of Services
• Costing Templates
The following system settings also will be maintained for Rezayat Project Sales:-
3.1 Customers
The system would regard any business partner or consumer in the Sales Cycle as a Customer.
Customer master is the central entity for Customer Order Management Cycle in the system.
Customer in SAP can denote different kinds of customers. The extent of information captured
for each type of customer would vary as per requirements.
In SAP, a customer would be identified with the help of a unique customer code and captures
all information about the customer. The customer master would capture information at various
levels like name and address, payment terms, banking details, accounting data (such as the
GL account to be utilized for the customers transactions), the sales office responsible for the
customer, terms of delivery, customer classification parameters etc. It is
All the business related information on customers is stored in the customer master. The
customer has the following views:
General Data: Data related to name, address, telephones, contact persons, industry details,
etc., which remain constant for a customer across organization elements in SAP.
Company Code Data: Data used in FI, such as the reconciliation account number, sort key,
etc., which remains constant for a company code. Ownership of this data is mainly with the
Accounting function.
Sales Area Data: Data used in SD, such as the indicator for pricing procedure, tax
classification, account assignment group, partner determination, statistical update group (for
updating Information System). For each customer, this data is to be maintained separately for
each sales area. However, each customer will be maintained in for the sales organization /
Distribution channel / Division. This will minimize the master data maintenance effort. At
transaction level the user will choose the correct sales area for the document.
Number Range
Field Selection- Fields present for data entry in the customer master
The following account groups for customers will be maintained in the system for Rezayat
Project Sales
Z001: Customers, with whom Rezayat has ongoing business or first time business. For
this account type, all three segments of the master (General, Accounting and Sales
Area) will be maintained.
Z002: Prospects, from whom Rezayat is soliciting business, but no transaction has
taken place. It possible to record an inquiry from a prospect and send quotations. No
Company Code (accounting) data will be maintained for this account. It is necessary to
change the account group and maintain the Company Code data for the account
before recording any order from that customer.
The account groups will share a common, internally generated number range across the entire
organization.
The component Partner Determination in Sales and Distribution enables to display the
partners involved in the business transaction, their functions and their business relationships
in the SAP system. When creating or processing sales documents, the system can determine
the partners automatically. Partner functions are classified using partner types. Partner types
enable general scheduling of partner functions in creditors, customers, personnel and contact
persons.
The following partner functions shall be used in case of Rezayat Project Sales:
It is advisable to maintain these relationships in the customer master itself so that the data is
automatically available in sales documents. The default partner determination can be
overwritten at transaction stage.
Cash management
Dunning procedures
Payment transactions
In most business transactions, the system defaults the key specified in the master record of
the customer in question. Regardless of whether or not a key is defaulted from the master
record, you can manually enter a key during document entry.
Additional Payment terms for Sales order will be created before go live as per the sales orders
to be taken into SAP
Material master data is critical for doing the sales transaction. Sales are booked either for sale
of product or for the sale of the services, for which in SAP a material is required.
Further details of Material Master have been covered under MM Module Blue Print.
RCL CD will create Model service Specification to map customer bill of quantities in the
system. Present Quotation number will be used to create the model service specifications. The
outline will represent the structure of customer’s BOQ and all the required service lines will be
copied from the customer BOQ. The Model service specification created will be used as Bill of
Services in the sales document and also for estimation.
Bills of services play an important and central role for numerous business processes in the
engineering and construction industry. On the debit side, BOS are fully integrated in the sales
and distribution (SD) process. The customer BOS forms the basis for describing the services to
be performed in sales documents. Cost planning, sales price determination, and billing are
The BOS structure allows you to describe services completely. A service line describes an
individual service. You can structure a BOS by using an outline layout structured according to
construction stages. You have several options for creating and editing a customer BOS. When
creating bills of services with extensive specifications, you do not need to repeatedly enter the
services on a manual basis. Instead, you can easily copy them from existing service master
data, using the reference technique and the selection function.
Easy Cost Planning enables you to quickly calculate planned costs in the SAP System. You
establish a representation of the structure of planning objects in the system. These can then
be used as planning forms by all cost planners. Easy Cost Planning is therefore particularly
efficient when more than one person in your organization plans costs, or when you frequently
plan costs in a similar way.
You create a costing model that contains the cost factors of a planning object and that
represents the planner’s point of view. You can structure the planning object. It is also
possible to divide up related cost factors into separate costing models. You then merge these
costing models into one large costing model at the end. This helps even large planning objects
remain manageable, and enables you to reuse the smaller costing models.
The planner uses the costing model as a planning form. The use of this planning form ensures
that all of the relevant cost factors are included, helping you to avoid errors.
The planning object can be structured whichever way the planner chooses, and the
substructures that the user defines can be costed separately.
You can define the entry screen in accordance with your individual requirements for each
planning form. It is automatically generated in HTML format, and you can modify it in various
ways. You can also insert information in the form of explanatory text. The entry screen
includes a field where planners can enter comments for themselves or for other users who
need to analyze the cost estimate. These comments are saved together with the entries for
the cost estimate.
RCL CD will prepare costing templates to do costing for service line items.
3.6 Pricing
The term pricing is used broadly to describe the calculation of prices and costs. Conditions
represent a set of circumstances that apply when a price is calculated. The condition
technique refers to the method by which the system determines prices from information
stored in condition records. In Sales and Distribution, the various elements used in the
condition technique are set up and controlled in Customizing. During sales order processing,
ZPR0 Price
The following Rejection Reason will be created in the system for closing the Inquiry
Documents.
I1 OUT OF SCOPE
I4 Unacceptable Client.
A status is an indicator that fulfills two functions. First, it informs you that a particular status
has been reached. Second, it influences the business transactions you can perform for a
particular status. A status can allow a business transaction; allow a business transaction but
issue a warning message; or prohibit a business transaction altogether. If a warning message
is issued it is up to the user whether the business transaction is carried out or not.
Statuses can be used to control and communicate. Statuses can be used in reporting.
Statuses can be used as selection criteria. Statuses can communicate the state of an object.
Two User Status profile will be created for REZAYAT GROUP for assigning to Inquiry Document.
One User Status Profile on Inquiry Header level for communicating the current status of the
Inquiry Document. The second User Status profile on Inquiry Item Level for controlling to
record the review and approval process.
Header Status
Status Description
CRTD Created
Item Status
CRTD Created
APRV Approved
RJCT Rejected
The following Rejection Reason will be created in the system for closing the Quotation
Documents.
Q3 PROJECT ON HOLD
A status is an indicator that fulfills two functions. First, it informs you that a particular status has been reached.
Second, it influences the business transactions you can perform for a particular status. A status can allow a business
transaction; allow a business transaction but
Statuses can be used to control and communicate. Statuses can be used in reporting.
Statuses can be used as selection criteria. Statuses can communicate the state of an object.
Two User Status profile will be created for REZAYAT GROUP for assigning to Quotation
Document. One User Status Profile on Quotation Header level for communicating the current
status of the Quotation Document. The second User Status profile on Quotation Item Level for
controlling to record the review and approval process.
Header Status
Status Description
CRTD Created
SBMT Submitted
OHLD On Hold
Item Status
Status Description
CRTD Created
APRV Approved
RJCT Rejected
User status for approval need to be created more depends on the approval matrix to record
the review and approval by different authority.
Sales & Distribution (SD) is the authorized legal arm of the company to do transaction with the
Customer. In RCL CD, Sales& Distribution can be divided into Pre sales activity, Sales Orders,
and Billing.
Sales & Distribution Module of SAP communicates with other modules in the SAP System to
ensure a constant flow of information. Sales processes will be integrated with Financial
Accounting (FI), Controlling (CO), Materials Management (MM) and Project System (PS).
RCL CD handles many projects. In order to capture the revenue for the project executed and
for collections related to projects SAP Sales and distribution module is used. Sales and
distribution module is helpful for order management and finance interface. It is also required
to update the receivables from client and for outstanding collection. It can be integrated with
PS module to update the planned and actual revenue for project work effectively.
Sales and distribution processes for RCL CD are broadly classified as follows:-
A record for each Customer is required to be created for smooth business function. The
details of the Customer need to be recorded while creating a new Customer.
All the details regarding the Customer address, telephone number etc need to be
recorded for ready reference.
The service material needs to be created which are to be maintained in the sales
documents.
Service Master needs to be created to prepare customer BOQ Line items
Bill of Services will be created to maintain customer BOQ in the system
Costing Template for Estimation
RCL CD Project uses Sales and distribution module to handle project related pre-sales
and sales activities. In order to record these processes in SAP master data needs to be
maintained prior to executing the transactions.
Master Data Team will create the Customer Master data in the system based on the
input received from concerned department.
The flow chart also shows the roles and responsibility related to customer master
creation and change.
All finance related Customer Account details like reconciliation account, payment terms
will be integrated with finance. For every account group one reconciliation account will
be maintained.
Service master will be created after verifying the BOQ line items for those masters
which are missing
Master data team creates the master data and it will be verified by the master data
verification team or the team who is going to use the master data.
Model service specification will be created to represent the client BOQ in the system
by structuring the service masters as BOQ line items.
Model Service Specification created also will be verified before using it in the sales
documents.
4.1.4 Pre-Requisite
Customer Account Group, Reconciliation account, sort key etc.
Service Group, Unit of Measurement, Service Category, Valuation Class for Services.
Consultant will complete the configuration in system to use all the functionality
mentioned in the document.
Custom Table Required to maintain Material cost per quotation to fetch material
value in valuation variant.
The following processes covers under Tendering Process in RCL Construction Division:-
1 Pre-Qualification
2 Inquiry Logging
3 Quotation Processing
4.2.1 Pre-Qualification
Pre-qualification is a process whereby a Customer takes information from RCL Construction
Divisions and makes a tentative assessment. Prequalification is a process by itself, where in
client says there is a prospect of tender and ask for a kind of job done. RCL cnstruction
division shall prove for qualification by submitting necessary documents. Upon reviewing
these documents by the client and prequalification reward, the client will send the inquiry.
The overall Pre-qualification process will happen as shown in the flow Chart attached in the
Addendum.
The inquiry logging process will happen as shown in the flow Chart attached in the
Addendum.
The inquiry from customers will be received either through fax or email.
Once the inquiry is received estimation will create inquiry document in the system.
While creating the inquiry the tender number mentioned in inquiry will be
maintained as the PO number in the inquiry document and the PO date field will be
used to indicate the inquiry received date.
Estimation will analyze the inquiry then will discuss with higher management to take
quote no quote decision.
If the higher management decision is to no quote then estimation will close the inquiry
document by maintaining inquiry rejection reason for future analysis.
If the higher management decision is to quote for the inquiry then estimation will
arrange to purchase the bid document.
4.2.4 Pre-Requisite
Customer Master, Material Master, Bill Of Services
Consultant will complete the configuration in system to use all the functionality
mentioned in the document.
Some of the processes shown as sequence in the flow chart may be executed parallel
with other processes.
Some of the processes shown in the flow diagram might repeat multiple times depend
on the nature of the project.
The process flow for Lump Sum contract with milestone billing will happen as shown in the
flow chart attached in the Addendum.
A project is created with a billing work breakdown structure (WBS) element. Network
and activities are also created. Define milestones for the billing plan which includes
the percentage value for billing amount of the contract value.
A Customer order (Sales Order) is created with a material item that contains a service
specification. If the contract is a result of a tendering the customer order will be
created with reference to a customer quotation. Latest negotiation will be considered
in the customer order.
The customer order item is linked to the project (billing WBS element) by the account
assignment of the customer order item. Hence the billing WBS element will be debited
with all revenues and down payments created due to the settlement (billing) of the
customer order. Defined milestones of the project are taken over to the billing plan of
the customer order item.
After a part of the construction project has been completed the work can be
documented by confirming a network activity with an attached billing milestone. Due
to the confirmation of the network activity the milestone is reached and the block in
the assigned billing plan item is removed.
In Lump Sum contract with Progressive Billing where Client and Rezayat has agreed on a lump
sum for the execution of the contract on a billing plan with dates usually depending on the
progress of the work in every month.
The process flow for Lump Sum contract with progressive billing will happen as shown in the
flow chart attached in the Addendum.
A project is created with a billing work breakdown structure (WBS) element. Network
and activities are also created.
A Customer order (Sales Order) is created with a material item that contains a service
specification. If the contract is a result of a tendering the customer order will be
created with reference to a customer quotation. Latest negotiation will be considered
in the customer order.
In the sales Order progressive billing plan will be maintained based on the planned
percentage of completion of the project on a monthly basis.
After a part of the project execution has been completed the progress of the completed
/ client approved percentage will be informed from the site.
The percentage of completion will be adjusted in the sales order if it varies from the
planned progress percentage. While adjusting the planned percentage of progress final
invoicing amount will be automatically adjusted in the sales order billing plan.
The billing block in the sales order billing plan item will be manually removed.
The financial accounting transactions post the outgoing and incoming payments. The
posting can be done automatically or manually, depending on the transaction.
In a unit rate contract, the work to be performed is broken into various parts, usually by BOQ,
and a fixed price is established for each unit of work. A minimum quantity of each work will be
mentioned in the contract where as the payment will be made based on the quantity take off
conducted during every month.
The process flow for unit rate contract with re-meaurable billing will happen as shown in the
flow chart attached in the Addendum.
A project is created with a billing work breakdown structure (WBS) element. Network
and activities are also created.
A Customer Order is created with a material item that contains a service specification
(Bill Of Services). If the contract is a result of a tendering the customer order will be
created with reference to a customer quotation. Latest negotiation will be considered
in the customer order.
The customer order item is linked to the project (billing WBS element) by the account
assignment of the customer order item. Hence the billing WBS element will be debited
with all revenues and down payments created de to the settlement (billing) of the
customer order.
The services that have been performed, planned and unplanned – are entered in the
service entry sheet (Quantity take-off based on the site measurement). After checking
the service entry sheet remove the billing block based on the client approved quantity.
The service entry sheet constitutes the basis for the billing process.
A service entry sheet is created then the down payment request or invoice is
generated. Once the billing documents have been created, they are transferred to
Financial Accounting automatically, and the corresponding FI documents are
generated.
The financial accounting transactions post the outgoing and incoming payments. The
posting can be done automatically or manually, depending on the transaction.
Orders of this kind are billed according to the resources consumed in executing them. In
resource-related billing, individual materials, internal company services and costs are passed
on to the customer. Billing requests during resource-related billing serve as the basis for
creating billing documents. You can create billing requests for customer orders, customer
projects and service orders. Items are created in the billing request on the basis of information
on the resources to be billed.
RCL CD will use resource related billing to address their maintenance service contract billing.
Contract
Start End
Details
Cost Budget
Controller
Carry-out
Create Service Book Material Book Equipment
Service Book Labor Costs
Order Costs Costs
Activities
Receive
Customer
Payment
All the labor costs, material cost and equipment costs will be booked on the service
order.
Define which billing data is to be supplied and/or postponed. The system reads the
expenses (hours, travel expenses or third-party invoices) for the service order, and
uses the dynamic item processor to summarize these according to any criteria you
define here.
The system determines a corresponding material, which has the character of a service
to be billed, for each dynamic item. The system uses these materials to create a billing
request (which is a sales document that is similar to the sales order), in which it also
performs pricing. The system will accept entries you make manually during pricing.
The system uses fixed price billing to convert the billing request to a billing document
(the actual invoice document).
Create billing document with reference to the billing request. Once the billing
documents have been created, they are transferred to Financial Accounting
automatically, and the corresponding FI documents are generated.
Further details of Customer Service processing are covered under CS Module Scope.
4.3.5 Pre-Requisite
Customer Master, Material Master, Bill Of Services
Some of the Processes shown in the flow diagram may not be applicable for all the
project divisions’ especially small projects.
Some of the processes shown in the flow diagram might repeat multiple times depend
on the nature of the project.
Custom report to compare customer supplied material with billed BOQ items.
Period-end closing is the framework for carrying out period-related commercial transactions.
Period end closing is done to ensure that all the data belonging to a period is determined and
that data is available for enterprise controlling purposes. Result Analysis and Settlement
belongs to Project period end closing.
Legend:
C(z) Work in progress C(r) Reserves for unrealized costs
R(z) Inventory, from which R(r) Revenue surplus (revenue can be generated)
R(p) Planned revenues C(p) Planned costs
R(a) Actual revenues C(a) Actual costs
R(c) Revenues affecting result C(c) Costs affecting result
POC Percentage of completion
In REZAYAT Result Analysis will be calculated based on the Cost based POC method.
After calculating Result Analysis Project will be settled to Profitability segment so that
profitability analysis for the project (with production order) can be analyzed in Controlling.
During settlement, actual posting of calculated WIP/reserves for unrealized cost happens as
per the posting rule. When WIP carrying object is Technically Completed (TECO), entries to
WIP P/L & Balance Sheet account are reversed.
Project Period End activities are covered under CO (Controlling) Module Scope.
Please refer CO Blue Print Point 4.4 for further details.
It is proposed to use standard reporting in SAP. If any specific requirement arises during
realization will be considered later. Some of the Standard SAP report details given below.
Service Master
Symbol Description
Unit Process:
Unit Business Identifies a task executed in SAP that is covered in a step-by-step
process
manner in the scenario.
Manual Process:
Manual Process Covers a task that is manually done
End Process:
End Process Represents end of process.
Documents
Hardcopy / Document:
Identifies a printed document, report, or form
Project Commercial - PC
Sales and Distribution - SD
Sales Master Data - MD PC_SD_001
Customer Management - CM
01Create Customer Master PC_SD_MD_CM_01
02Maintain Customer Master PC_SD_MD_CM_02
03Blocking Customer Master PC_SD_MD_CM_03
04Extend Customer Master PC_SD_MD_CM_04
Bill of Quantities - BQ
01Create Service Master PC_SD_MD_BQ_01
02Maintain Service Master PC_SD_MD_BQ_02
03Create Model Service Specification PC_SD_MD_BQ_03
04Maintain Model Service Specification PC_SD_MD_BQ_04
Costing Template - CT
01Create Costing Template for Easy Cost Planning PC_SD_MD_CT_01
02Maintain Derivation Rules for Easy Cost Planning PC_SD_MD_CT_02
Tendering Process - TP PC_SD_002
Pre-Qualification - PQ
01Create Pre-Qualification Document PC_SD_TP_PQ_01
02Maintain Pre-Qulaification Document PC_SD_TP_PQ_02
03Close Pre-Qualification Document PC_SD_TP_PQ_03
04Maintain PQ Submittal in DMS PC_SD_TP_PQ_04
Inquiry Logging -
IN
01Create Inquiry PC_SD_TP_IN_01
02Maintain Inquiry PC_SD_TP_IN_02
03Update Bill of Services in the Inquiry PC_SD_TP_IN_03
04Close Inquiry PC_SD_TP_IN_04
05Maintain Inquiry Submittal in DMS PC_SD_TP_IN_05
Quotation Processing - QT
01 Create Quotation PC_SD_TP_QT_01
02 Maintain Bill of Serivce in the Quotation PC_SD_TP_QT_02
03 Easy Cost Planning on Service Line Items PC_SD_TP_QT_03
04 Maintain Conditions PC_SD_TP_QT_04
05 Maintain Quotation Submittal in DMS PC_SD_TP_QT_05
06 Quotation Revision PC_SD_TP_QT_06
Contract Award - CA PC_SD_003
Sales Order - SO
01 Create Sales Order PC_SD_TP_SO_01
02 Maintain Bill of Services in Sales Order PC_SD_TP_SO_02
03 Update Sales Order Line Items as per contract PC_SD_TP_SO_03
04 Maintain Billing Plan in Sales Order PC_SD_TP_SO_04
Quantity Take-Off - TO
01Create Service Entry Sheet PC_SD_TP_TO_01
02Maintain Service Entry Sheet PC_SD_TP_TO_02
Billing - BL
01 Create Down Payment Request PC_SD_TP_BL_01
02 Create Invoices PC_SD_TP_BL_02
Maintain Down Payment & Retention Details in
03 Invoices PC_SD_TP_BL_03
04 Maintain Payment Certificate Received in DMS PC_SD_TP_BL_04
Start YES
Inquiry Process/Invitation to bid Pre- Customer NO Customer Maintain PQ missing Details are OK
YES Financial
qualification Process master Exists details Details are OK
NO NO
Submit Review PQ
Create PQ submission PQD OK
Document in Prequalification Add missing Document
Inform to
Close PQ
Document
YES
Customer Sends Review the inquiry
Customers
Analyze
Create Inquiry the scope OK to Bid Yes OK to Bid Yes OK to Bid Yes OK to Bid
required
documents NO
for Bid
Accounts to
arrange Bid
Document Reject No
Quotation Process
Receive Bid Upload Bid
Preliminary Preliminary review Preliminary review Preliminary review Preliminary review
Documents Documents in
from review of Bid DMS of Bid Documents of Bid Documents NO of Bid Documents NO YES of Bid Documents
Customer Documents
Send NO YES
Info received
Send Prepare No about Bid
Preliminary Review
Design /
GGM
Clarifications
Check Activity
Types
Prepare Excel
Sheet for BOQ Prepare
Upload in the Optimized
No Create
Creation BOS
YES
YES YES
NO Details are OK
Revise Revise the
Revise Costing Technical Optimized
YES
Pricing in the Quotation Pricing Quotation Pricing Quotation Pricing Quotation Pricing Quotation Pricing
Billing Quotation
Pricing in the NO YES
Bid Bond Approve Bid Approve Bid Approve Bid Approve Bid Approve Bid Approve Bid
Request Send Bid Bond Bond Request Bond Request Bond Request Bond Request Bond Request Bond Request
Request for
Manager’s
approval
Close the
Quotation NO
Document
Management
YES
Approval
LS Contract
Prepare
Performance
Consultant
Is the Contract
Relevant for
Retention
Send Approved
Measurement for
Billing
YES
Create Retention NO
Agreement
NO
Remove Billing
Generate Billing
Document
the Billing
Document
to the Client
RCL CD SD SCOPE Page 51