Project Cost Control & Reporting Procedure_PSE
Project Cost Control & Reporting Procedure_PSE
ORIGINATOR COMPANY
DOCUMENT TITLE
Table of Contents
1.0 PURPOSE........................................................................................................................... 3
2.0 SCOPE................................................................................................................................ 3
3.0 LIST OF REFERENCES.....................................................................................................3
4.0 DEFINITIONS / ABREVIATIONS........................................................................................3
5.0 RESPONSIBILITIES & FLOW OF INFORMATION.............................................................4
6.0 PROCEDURE..................................................................................................................... 5
6.1 Project Cost Control & Reporting........................................................................................5
6.1.1 Control Budget / Current Contract Price.............................................................................6
6.1.2 Physical Progress............................................................................................................... 6
6.1.3 Value of Work Done............................................................................................................6
6.1.4 Estimation to Complete.......................................................................................................7
6.1.5 Pending Items..................................................................................................................... 7
6.1.6 Forecast Contract Price......................................................................................................7
6.1.7 Invoices as per Payment Milestone....................................................................................8
7.0 COST BREAKDOWN STRUCTURE / COST REPORT FORMAT......................................8
8.0 MONTHLY COST REPORT MEETINGS............................................................................8
9.0 ATTACHMENTS................................................................................................................. 8
Project Cost Control & Reporting
Procedure PAGE 3 of 9
6.1.1
1.0 PURPOSE
The purpose of this procedure is to capture specific cost controls which contribute to the overall
Project reporting.
2.0 SCOPE
This procedure defines the cost monitoring, controlling and reporting process performed during
the Project period, to ensure that the evolution of actual costs during the execution is taking
place within the established control budget. Actual costs are monitored in relation to approved
control budget and time schedule. Thus, at the earliest possible stage, potential adverse
developments affecting the forecasted CAPEX can be identified and, if possible, corrective
actions initiated.
PM Project Manager
Scheduling - in order to get the physical progress ratios for the WBS items
Procurement - in order to apply the payments and dates specific for each package
Engineering – in order to use the specific information in terms of costs regarding the
construction and commissioning phase.
The Project Services functions are responsible for providing actual Project cost controls and
ensuring support to the PM as necessary to manage effective completion of the project
deliverables.
The PSM is responsible for the application of the appropriate project cost control processes to
ensure the Project quality objectives are achieved and presented to the PM for review and pass
to the Client.
The PM shall be responsible for the cost documentation and shall train and delegate the work to
his staff accordingly. Moreover, the PM is responsible to ensure that all Project cost controls and
Project Cost Control & Reporting
Procedure PAGE 5 of 9
requirements are Client Project developed appropriately and meet the Client /
Project Manager expectations.
Project Manager
Projct Services
Reporting
Cost
Controlling
6.0 PROCEDURE
The Work Breakdown Structure (WBS) of the Project is the basis for the scope and splitting of
the work, budgeting / cost controlling, scheduling / progress controlling and the Project
organization.
The Project Cost Report is performed monthly throughout the Project period duration, beginning
as soon as the Project costs are incurred.
The physical progress is the percentage achieved by each item of the WBS / CBS over the
Project duration. Planned and actual physical progress is calculated within the registers specific
for each phase of the Project, namely:
Master Document Register (MDR) for the Project Management and the Engineering
phase
From these sources the calculated percentages of planned and actual physical progress at an
aggregate level will be manually transferred into the Cost Report.
The Value of Work Done can be defined as the amount of work actually achieved to date
(earned value) in monetary terms. The VoWD cumulative is equivalent to the actual costs
incurred up to the cut-off date. The Value of Work Done for the Project will be calculated by
multiplying the Original Contract Price / Current Contract Price by the physical progress
achieved by each item of the WBS / CBS. This will be controlled against respective CTRs and
will provide an overall achieved completion which is directly comparable to the planned one. The
physical relative progress for each deliverable contained in the specific phases of the Project is
obtained by multiplying the absolute progress value of each deliverable corresponding to each
control point with the weighting factor. Deviations from planned baseline will form discussions at
the monthly meetings and any corrective actions to address areas of concern will be
considered.
The Estimation to Complete is the value obtained by the difference between the Original
Contract Price / Current Contract Price and the cumulative Value of Work Done.
value to completion. Forecasting will incorporate also approved changes in order to determine
the most realistic end value.
Thus, the Forecast Price will be the result of the sum between the VoWD as of the cut-off date,
the value of the remaining works to be done as per the schedule, meaning the Estimation to
Complete and the Pending Items.
The amounts of the services rendered will be invoiced on the aggregate project level as per the
Payment Milestones. However, the invoice shall have attached details of the items invoiced.
Periodic and cumulative total amounts of the invoices will be displayed in the Cost Report
analyzed by amounts paid and unpaid as per cut-off date.
The Cost Report format is detailed under Appendix 1 attached to this procedure.
Based on the preliminary Project Cost Report, Monthly Cost Report Meetings will be held. The
results will be considered in the final Project Cost Report.
9.0 ATTACHMENTS
Project Cost Control & Reporting
Procedure PAGE 9 of 9