test-management-ii-solutions
test-management-ii-solutions
Integrity Assurance of the accuracy and consistency of data through the life cycle
a. Determine the extent of testing required for the product risks and the
mitigation and contingency actions required for the project risks
b. Obtain the resources needed to completely cover each product risk with
tests and transfer responsibility for the project risks to the project
manager
c. Execute sufficient tests for the product risks, based on the likelihood and
impact of each product risk and execute mitigation actions for all project
risks
d. No further risk management action is required at the test planning stage
Question 7: Answer
What else should you do with those lists of product and
project risks during test planning? project title
Risk-based approach during the planning stage
Product risks
Determine the extent of testing to be carried out
Prioritise testing in an attempt to reveal critical defects as early as possible
Project risks
Identify risk items
Determine likelihood and impact for each item
Define mitigation and contingency actions for the identified risks
Question 7: Answer
You and the project stakeholders develop a list of product risks and
project risks during the planning stage of a project. What else should
you do with those lists of risks during test planning? project title
a. Determine the extent of testing required for the product risks and
the mitigation and contingency actions required for the project risks
b. Obtain the resources needed to completely cover each product risk with
tests and transfer responsibility for the project risks to the project
manager
c. Execute sufficient tests for the product risks, based on the likelihood and
impact of each product risk and execute mitigation actions for all project
risks
d. No further risk management action is required at the test planning stage
Question 8
According to the ISTQB Glossary, a product risk is related
to which of the following? project title
Contingency Testing to identify work-arounds for the defects that aren't discovered
Question 9: Answer
Failure-based testing
Idea: Can organise test effort based on failure-prone areas
project title
Identifies areas most likely to hold defects, based on complexity
Some functionality is harder to implement than other
These areas are more vulnerable to defects
Starts early in the project and conducted throughout the life cycle
New problems / challenges will always emerge
Management-directed testing
This is not a defined test strategy in the ISTQB syllabus
Question 9: Answer
Typical test strategies include:
project title
1. Risk-based testing TRUE
Testing directed to areas of greatest risk
2. Failure-based testing TRUE
Test more in failure-prone areas
3. Management-directed testing FALSE
Test first the areas indicated by the org. management
a. A bug report
b. A defect report
c. An incident report
d. A test summary report
Question 11: Answer
According to the ISTQB Glossary, what do we call a
document that describes any event that occurred during
project title
testing which requires further investigation?
Incident
Discrepancies between actual and expected test outcomes
Incident management
The process of recognising, investigating, taking actions, and disposing of incidents
Incident report
A document reporting on any event that occurred during testing
Requires further investigation
Question 11: Answer
According to the ISTQB Glossary, what do we call a
document that describes any event that occurred during
project title
testing which requires further investigation?
a. A bug report
b. A defect report
c. An incident report
d. A test summary report
Question 12
A product risks analysis is performed during the planning stage of
the test process. During the execution stage, the test manager directs
projectrisk
testers to classify each defect report by the known product title it
relates to (or by 'other').
Once a week, the test manager runs a report that shows the
percentage of defects related to each known product risks, and to
unknown risks.
What is one possible use of such a report?
a. To identify new risks to system quality
b. To locate defect clusters in product subsystems
c. To check risk coverage by tests
d. To measure exploratory testing
Question 12: Answer
What is one possible use for a report showing defects
related to known product risks and unknown risks?
project title
Objectives of an incident report
Provide developers with feedback about incidents to:
Enable identification, isolation, and corrective measures
Provide test leaders with feedback about incidents to:
Track system quality
Measure test progress
Provide ideas for test process improvement
Identify potential new risks to system quality
Question 12: Answer
A product risks analysis is performed during the planning stage of
the test process. During the execution stage, the test manager directs
projectrisk
testers to classify each defect report by the known product title it
relates to (or by 'other').
Once a week, the test manager runs a report that shows the
percentage of defects related to each known product risks, and to
unknown risks.
What is one possible use of such a report?
a. To identify new risks to system quality
b. To locate defect clusters in product subsystems
c. To check risk coverage by tests
d. To measure exploratory testing
project title
Part II: Exercises and
Open-ended questions
Exercise 1
Go to the following website and find an incident:
project title
www.adam.goucher.ca/parkcalc/
Assigned To:__________________________________________
Incident Resolution::____________________________________
Exercise 1: Incident Report
project title
The seminar slides are made by