CEng 4231 chapter 4
CEng 4231 chapter 4
4.1 Introduction
Project Cost estimation is the process of valuing on monetary expression, including the cost of
all possible entrants necessary for the planning, implementing and monitoring stages of the
proposed project under consideration. Cost estimation is the determination of the probable cost
of a project.
An estimate serves a number of different functions, depending on the stage of the project, as
shown below:
• Schematic Design (Conceptual design): Sketches are prepared. Major elements are defined;
Use a preliminary method to estimate cost. Cost of each element is established (cost plan).
42
• Construction Phase: Estimates are prepared for cost for cost Control and for change order
evaluations.
• Costs include:
• Land
• Financing cost
• Consultations/Studies
• Engineering
• Project Management
• Construction
• Operation & Maintenance
• The Conceptual Estimate found during feasibility becomes the initial project budget
• Subsequent design development should remain within the limit of this budget
• For that purpose, several preliminary estimates are performed as more details become
available through the design.
• Preliminary estimates assign cost to various assemblies (elements) of the project (Cost
Plan). {substructure, superstructure, interior partitions & doors, exterior cladding ..etc.}
• Preliminary estimates allow for Value Analysis – Compare value of an element with its
cost Consider Alternatives Select desired option.
Over all the main purpose of cost estimation can be summarized as follow:
43
• determine actual cost per unit of item
• Correct information of the market price of the materials at the time of need to be
used as a basic price
The following knowledge, managerial talents, and degree of construction experience make a
good estimator.
• Ability to read and understand contract documents, with special skills in reading
construction drawings for all specialties and related specifications.
• Ability to accurately take off the quantities of construction work for which he or she is
preparing the detail estimate.
44
• Ability to visualize the future building from drawings, which usually requires some
years of construction site experience.
The following knowledge, managerial talents, and degree of construction experience make a
good estimator.
• Familiarity with estimating software in depth and with available building cost
databases.
• Ability to work under pressure and to meet all bid requirements and deadlines
• Construction scheduling
• Bidding environment
• Proper management
45
NB: Cost due to construction is given special attention here; it includes cost due to material, cost
due to labor, cost due to equipment, overhead costs and contractor’s profit. In order to facilitate
estimation of cost due to material, it is important to know the quantities of various elements
involved in construction of various parts of the building work i.e. material break down is
essential. Construction cost includes
Material Break Down -In order to facilitate estimation of cost due to material, it is important to
know the quantities of various elements involved in construction of various parts of the building
work
Example: Material Break Down for 1m3 C-25 concrete (1:2:3 mix)
Note: -1.5 to 1.6 times dry volume of the materials is required to get 1m3 of compact dense fresh
concrete mix.
46
4.5 Purposes of Cost Estimation
➢ Correct information of the market price of the materials at the time of need to be
used as a basic price
• Correct information of the rates of various categories of skilled and unskilled laborers
as wage rates to be used for daily work rate.
Eg. mixer= 500 birr/day; loader= 450 birr/hr; vibrator= 100 birr/day
47
4.6.1 Preliminary /approximate costing
This type of cost estimation is required to know the financial position of the client before costly
detailed designs are carried out.
Such estimates are based on practical knowledge and cost of similar previous works.
Examples of approximate cost estimations are as follows: cost per functional unit, Plinth area
method -cost per m2, Cubical Content method –cost per m3.
Hospital =cost per bed, Dormitory = cost per student, Cinema or theatre = cost per seat,
residential buildings =cost per area, road works = cost per kilometer length, culverts or bridges =
cost per meter span, water supply sewerage projects = cost per head of population.
Based on PLINTH AREA -roof area or external dimensions at the plinth level (Courtyard &
open area shall not be included)
The rate per meter square is deduced from the cost of similar building projects in the locality.
Based on cubical contents of various buildings, i.e. Plinth area of the building x height x cubic
content rate.
Height should be taken from the top of flat roof (or halfway of the sloped roof) to the top of
concrete in foundation.
This is the most reliable and accurate type of estimate. The quantities of items are carefully
prepared from the drawings and the total cost worked out from up to date market rates.
48
A detail cost estimate thus requires:
• Direct costs, which include the direct cost of materials, labor as well as equipment and
• Indirect costs, which include but not limited to head office and site overhead costs.
Direct construction costs are all costs that can be specifically booked with an activity in a
project. The direct costs mainly include material, labor, equipment and subcontract costs
• Direct material costs – These costs referring to the cost of materials, consumables
and components used for executing an activity including the allowances for scrap and
wastages.
• Direct labor costs – All costs related to the workers working on a specific activity
such as carpenters, masons, erectors, painters, plumbers and so on.
• Direct equipment costs – These costs referring to the costs of machineries and plants
used in executing a specific activity.
• Subcontract costs – In case some specific activities are subcontracted, the subcontract
price will be considered as the direct cost of the activities to be executed by the
subcontractor.
Indirect construction costs are all costs, which cannot be directly booked under a specific activity
in a construction project but required to keep the whole project operational.
49
These costs are also called overhead costs, which mainly include the head office and site
overhead costs.
Head office overhead costs are all costs required to run the whole operation of the construction
company, which usually administers different projects at a time.
These costs are not usually associated with specific project but rather shared proportionally by all
projects under the company
• Senior management costs and Indirect labor costs – salaries and benefit package for
senior Management, technical, administrative, marketing, finance and supply staffs.
• Bidding Expenses
• Expertise service costs – external auditors, lawyers, management consultants and external
trainings.
• Office running expenses – expenses such as telephones, fax, internet services, stationery,
mail services and so many others.
• Transportation and travel expenses - costs related to transportation, per diem and living
expenses.
Site overhead costs are all costs required to run the whole operation of a specific construction
project at site level.
50
• Site management costs and Indirect labor costs – salaries and benefit packages of the site
management members, general foremen, site engineers, office engineers, administrative
and finance staffs, data collectors in the project site.
• Site offices
• Office running expenses - expenses such as telephones, fax, internet service, mail service
and stationery for the site office
C. Risk Allowance
Usually contractors incorporate risk allowances in their tender prices to compensate the negative
impacts of different risks such as contractual, technical, political and economic risks.
construction projects are executed by contractors whereby these contractors will commit to
invest their capital to get maximum possible profit from the contracts to be performed.
A profit margin entirely depends on the market competitiveness and company strategies.
Rate Analysis is the process of fixing cost per unit of measurement for the different item of
works.
Total cost per unit of work (TC): Direct cost (DC) + Indirect cost (IC)
51
DC includes cost due to material (MC), cost due to labor (LC), cost due to equipment (EC), IC
covers overhead costs, and contractors profit.
Example: -Calculate the Unit price for C -25 concrete per m3 of work (formwork and
reinforcement rated separately). Assume 15% overhead and 20 % profit.
Solution: -
IC = (15% + 20%) of DC = 35 % of DC
Direct Cost (DC) = Material Cost (MC) + Labour Cost(LC) + Equipment Cost (EC)
52
Material cost (MC)
53
Equipment Cost (EC)
Assuming a mixer with a daily rental rate of 500Birr/hr and a vibrator with a daily rental rate of
100 birr/hr and equipment productivity of 0.5 m3 per hour:
DC = MC + LC +EC
≅ 2400 Birr/m3
Example: If the quantity of C25 concrete was found to be 110 m3 from the takeoff; the total cost
of concrete would be
54
REFERENCE
1. Estimating and Tendering for Construction Work, Martin Book, 3rd Edition, 2004.
2. Civil Engineering, Estimating and Costing (Including Quantity Surveying Valuation and
Contracting), V.N. Vazirani & S.P. Chandola, 4th Edition, Khana Publisher.
3. Contract, Specification and Quantity Survey, Lecture notes by Nasir Bedewi, School of
Civil Engineering, FOT, AAU.
55