0% found this document useful (0 votes)
4 views11 pages

079254C 0000 JSC 1393 014 - 0 - Signed

This document outlines the job specification for piping inspection at the Assiut Hydrocracking Complex, detailing the responsibilities of the subcontractor, the scope of work, and the necessary preliminary activities. It emphasizes the importance of adhering to engineering documentation, conducting thorough inspections, and ensuring safety measures are in place during the inspection process. The document includes a checklist for various piping components and inspection procedures to ensure compliance with project standards.

Uploaded by

Maher Fouda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views11 pages

079254C 0000 JSC 1393 014 - 0 - Signed

This document outlines the job specification for piping inspection at the Assiut Hydrocracking Complex, detailing the responsibilities of the subcontractor, the scope of work, and the necessary preliminary activities. It emphasizes the importance of adhering to engineering documentation, conducting thorough inspections, and ensuring safety measures are in place during the inspection process. The document includes a checklist for various piping components and inspection procedures to ensure compliance with project standards.

Uploaded by

Maher Fouda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Project N° Unit Document Code Serial N° Rev.

Page
079254C 0000 JSC 1393 014 0 1/11

ASSIUT HYDROCRACKING COMPLEX


ANOPC
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

JOB SPECIFICATION FOR

PIPING INSPECTION

(ex 079254C-0000-MS-1393-014)
it is specifically furnished or outside the extent of the agreed upon right of use.

Martina Pinto
2021.02.10 12:02:08 Nicola Perugini
Nicola Perugini
2021.02.10
Corrado Digitally signed by
Corrado Pigna
+01'00' 2021.02.10 12:37:37 +01'00' 12:37:55 +01'00'
Pigna Date: 2021.02.10
14:16:44 +01'00'

0 10/02/2021 ISSUED FOR EXECUTION M. PINTO N. PERUGINI N.PERUGINI / C. PIGNA

B 22/10/2019 ISSUED FOR EARLY WORKS A. RUZZETTI N. PERUGINI N.PERUGINI / C. PIGNA

A 27/08/2019 ISSUED FOR REVIEW A. RUZZETTI N. PERUGINI N.PERUGINI / C. PIGNA

REV. DATE STATUS WRITTEN BY CHECKED BY APPROV./AUTHOR. BY


(name & visa) (name & visa) (name & visa)
DOCUMENT REVISIONS

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 2/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

INDEX

1. PURPOSE 3
2. SCOPE 3
3. REFERENCE DOCUMENTS 3
4. RESPONSIBILITIES 3
5. PRELIMINARY ACTIVITIES 4
5.1. Documentation 4
5.2. Inspection Scheduling 4
5.3. Site preparation 5
6. PIPING INSPECTIONS CHECKLIST 6
7. REPORTS 10
8. HSE PRECAUTIONS 10
9. ATTACHMENTS 11
9.1. Att. 1 – Typical Job Hazard Analysis for Works in Confined Spaces 11
9.2. Att. 2 – Typical Job Hazard Analysis for Piping Inspection 11
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 3/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

1. PURPOSE
Purpose of the present job specification is to provide the minimum requirements, to be
integrated with manufacturer’s instructions, that Subcontractor shall apply to carry-out all
checks on piping systems during construction and precommissioning.

2. SCOPE
This job specification applies to the execution of piping inspection activities on the project
079254C.

3. REFERENCE DOCUMENTS
079254C-0000-QCP-1300-051 Precommissioning Quality Control Plan – Piping

079254C-0000-PP-901 Precommissioning, Commissioning, Start-up


Execution Plan

4. RESPONSIBILITIES
Subcontractor is responsible to monitor all the activities, maintain track and document all
records.

Subcontractor is responsible to eliminate or mitigate any risk related to the execution of


such activity.

In case the specific piping inspection procedure is prepared by Others (Company,


Contractor, Vendor, etc.), Subcontractor remains responsible for any safety matter
related to the implementation of such procedure being the piping inspection in his scope
of work.

Subcontractor is responsible in any case of the safety of the personnel directly working
on the piping inspection and the personnel working/present in the same area affected by
the execution of the activity.

Subcontractor is responsible to follow the job specification in developing a specific


it is specifically furnished or outside the extent of the agreed upon right of use.

procedure for each circuit. Moreover, Subcontractor is responsible to instruct its workers
and to monitor/supervise them during the execution of piping inspection activities. Before
starting the activity, Subcontractor shall have a Tool Box meeting. Company can attend
such tool box meeting at any time.

Subcontractor is responsible to:


• verify that piping systems have been erected according to the latest applicable
P&IDs and specifications;
• verify safe operability and maintainability of each plant item/equipment.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 4/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Subcontractor is responsible to execute P&ID’s check. This inspection applies to piping


physical check-out; it is not covering welding checks. Subcontractor is responsible to
check and submit approved welding documentation (including material traceability) on
piping and piping supports prior to the final system/subsystem joint walkdown.

Subcontractor shall execute piping conformity check against ISO drawings before piping
pressure test execution. This conformity check is not of the present job specification.

5. PRELIMINARY ACTIVITIES

5.1. Documentation
Subcontractor shall check piping versus the up-to-date engineering documentation.
A dedicated piping inspection folder shall be prepared by Subcontractor prior each sub-
system/system inspection including the followings:
• Latest revision (red-marked) of sub-system/system marked up P&IDs;
• Latest revision of sub-system/system component list;
• Last status of sub-system/system Construction punch list;
• Punch list form;
• Vendor P&ID (if any).

Any deviation from specifications and drawings shall be recorded by Subcontractor as


punch items for resolution. Where deviations from drawings are agreed to be maintained
by all involved parties, Subcontractor shall promptly communicate them to field
engineering department at site for master copies mark up and final incorporation on the
as-built drawings. Those deviations will be managed according to the approved project
Field Engineering Management Procedure.

5.2. Inspection Scheduling


Aiming to prevent findings at the late stage and minimize delays due to their
rectifications, the piping inspection (P&ID’s conformity check) shall be executed in two
steps:
it is specifically furnished or outside the extent of the agreed upon right of use.

• Preliminary P&ID’ check: Internal check done by Subcontractor Precommissioning


Team, aimed to minimize findings during next steps (including Licensor’s conformity
check);
• Final P&ID’s check: Check executed during official joint walkdown between
Subcontractor, Contractor and Company representatives as part of Mechanical
Completion prerequisites and in the frame of handover process.

Plant piping inspections (both internal Preliminary P&ID’s check and Final P&ID’s check)
shall be organized by Subcontractor according to project procedures with a sub-

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 5/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

system/system-wise approach in order to ensure the entire plant will be inspected


according to the latest revision of P&ID’s.

When the Vendor representative is required to be involved in the inspections,


Subcontractor shall properly schedule and coordinate the activity with Contractor.

Preliminary P&ID’s conformity check shall be performed by sub-system/system-wise


approach when sub-system/system piping erection is over 75%.

Considering the early phase of P&ID’s check execution, missing plant items shall not be
recorded as punch item unless it’s confirmed that such item will not be installed prior the
expected Mechanical Completion date.

Final piping inspection shall be performed in the frame of the official sub-system/system
joint walkdown prior sub-system/system Mechanical Completion.

During the final P&ID’s check, previously open punches holding the Mechanical
Completion of the sub-system/system shall be checked for close out.

A further piping inspection shall be executed by Licensor, in accordance with Licensor’s


procedure and check lists, to ensure that the plant meets the Licensor’s technology
requirements.
Contractor shall define the right time for Licensor’s inspection execution considering that:
• It shall be early enough to avoid delaying of the overall completion of the project due
to corrective work required by Licensor;
• plant erection shall give the possibility to Licensor to check that all its technology
requirements have been incorporated.

5.3. Site preparation


Before any inspection/walkdown, Subcontractor shall ensure as a minimum the
following:
• Site area shall be cleaned and properly housekeeping has been carried out to
ensure a safe working area;
• All precautions has been taken to safely isolate piping/equipment to be inspected;
it is specifically furnished or outside the extent of the agreed upon right of use.

• Specific permit to work shall be prepared and validated by Subcontractor HSE


department;
• Prepare safe access way for piping inspection at height such as temporary
scaffolding or platform.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 6/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

6. PIPING INSPECTIONS CHECKLIST

The following list collects the general checks that Subcontractor shall systematically
address as a minimum during the system/sub-system P&ID’s conformity check. The
below list shall be supplemented by Subcontractor during site activities execution.
Subcontractor shall:

• Check-valves, control valves, globe valves and other unidirectional valves


o Ensure these are installed with the flow direction arrow (stamped or tagged on
the valve body) in the correct direction.
o Ensure that the correct type of valve internals have been installed or re-
installed in case of removal for cleaning purposes.
o Ensure that the correct type of check valve internals for welded valves have
been re-installed after piping PWHT.

• Butterfly valves
o Ensure the valve stem/shaft is installed as per manufacturer’s instructions and
project specifications (whenever is possible, horizontal to the pipeline).

• All valves
o Check that packing gland followers are correctly tightened and that the valves
opening and closure is smooth.
o Ensure there is enough room for packing gland followers re-tightening.
o Check valve position is conform with P&ID;
o Ensure valves are equipped with an identification plate showing the correct
tags as per P&ID
o Check valves are accessible and can be safely operated (with exception of
valves for which permanent accessibility is not required; e.g. root valves).

• Sample connections
it is specifically furnished or outside the extent of the agreed upon right of use.

o Verify correct installation, in particular that they are not placed in a dead-end.
o Verify the correct type of sample arrangement as indicated on the P&ID.
o Verify there is enough room to insert the sample bottle.

• Pump suction strainers


o Verify provision for drain and de-pressurization of the strainer body.
o Verify there is room enough to connect a hose to the drain.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 7/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

o Verify there is room enough to insert a bucket or can underneath the drain
point.
o Verify that the strainer can be pulled out without problem.
o Verify the correct direction of pump strainer.

• Spectacle blinds
o Verify that blinds can be swung easily.
o Verify proper blind installation, in particular that they can be swung without a
shutdown (provision of double block and bleed valves, drain and vent points,
etc.).
o Verify no temporary blinds or aluminum sheet have been forgotten in the
circuit;
o Verify blind position is conform to P&IDs.

• Piping low points, high points and slopes


o Check that slope and process drains/vents are in accordance with the P&IDs
o Check that process drains and vents are caped with end blinds and correct
type of gasket
o Check that pressure test vents are properly plugged and seal welded.

• Pipe supports
o Check spring hanger transit pins have been removed.
o Check piping bellows have been released
o Check slipper pads are situated correctly in their guides.
o Check pipe clamps type is as per specifications and bolts have been tightened.

• Steam traps
o Verify steam traps are correctly installed as per approved drawings.
it is specifically furnished or outside the extent of the agreed upon right of use.

o Ensure the discharge is connected to the proper network or routed to safe


location.
o Ensure internals have been installed or re-installed in case of removal for
cleaning purposes.

• Safety valves
o Check proper installation of safety valves, in particular verify that drain/vent
points and by-passes are as per P&ID.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 8/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

o Check isolation valves, vent, drains are accessible


o For safety valves discharging to atmosphere, check that the exhaust lines are
adequately supported and drainable in case of low point.
o For safety valves discharging to atmosphere, verify that discharge line is led
to a safe location.
o For paired safety valves equipped with lock system, check that lock device is
in good order and a procedure for handling of keys/locks is in place.
o Verify PSV outlet line is self-draining toward the flare header.
o In case of pilot operated valves, verify pilot tubing tapping point is installed as
per vendor recommendation.
o Ensure that PSV is provided with identification plate showing the correct tag
number as per P&ID.
o Ensure that for Balanced Bellows Safety Valves the vent is open to
atmosphere.
o Ensure that for conventional type safety valves the vent opening is plugged.

• Heat tracing
o Check that steam and/or electrical heat tracing installation has been
completed.

• Insulation
o Check that piping insulation on hot and cold service lines has been completed
and not damaged.
o Check that line numbers are clearly and properly marked on the insulation as
per P&ID.

• Gaskets and joints


o Check that permanent gasket is in place.
o Check the correct gasket rating has been used.
it is specifically furnished or outside the extent of the agreed upon right of use.

o Check the correct gasket material has been used (usually a gasket color
coding is in place according to ASME B16.20 and/or Company specification).
o Check proper bolts and nuts have been installed (type, size, material) and are
not loose.
o Check grease has been used during bolts installation.
o Check flange tags on joints, as per flange management procedure in place.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 9/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

• Rotating equipment
o Check that the pump can be properly and safely isolated, drained and vented
for maintenance.
o Check for the installation of commissioning strainer in the suction of the pump.
Check if it is marked on the outside.
o Verify that all maintenance activities can be executed normally; enough room
allowed to safely perform all tasks.
o Verify that start/stop switches are mounted in a logical and safe location.
o Check that equipment has been identified with the correct tag number as per
P&ID.

• Instruments
o Check correct tags as per P&ID on instrument installed.
o Check correct tapping on transmitter (+ branch upstream and – branch
downstream).
Note: the connection for liquids slopes down and for gas slopes upwards.
o Check the piping of the transmitter sensor lines have the correct tracing and
or insulation.
o Check that the orifice plate is properly installed, verifying the position of
vent/drain holes are according to the fluid passing through (for liquid, vent hole
upward; for gases, drain hole downward) and checking that the faces’ plate
orientation is according to flow direction, as needed by plate typology: e.g.,
orifice plates with beveled square edges must be installed with the beveled
end faces downstream the flow. Usually, the text label printed on the paddle
or handle of an orifice gives an identification of the upstream side of the plate.
o Verify that vessels on weigh cells are completely supported on the weigh cells
and not by any other support. Check that fixed pipes are not interfering with
the weight. Verify flexible hoses are used as indicated on the P&IDs.

• Accessibility
it is specifically furnished or outside the extent of the agreed upon right of use.

o Check accessibility of valves and other equipment, taking into consideration


the required maintenance activities and frequency of operation.

• Safety
o Check all safety aspects related to piping, e.g. protruding valves spindles, etc.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 10/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

• Operability
o Check operability aspects: typical examples are the location of pressure
gauges installed at pumps discharge that must be readable while operating
the discharge valves or the level gauges of vessels to be visible from the drain
valves locations.

7. REPORTS
Results of dedicated inspections shall be reported by Subcontractor in the appropriate
pre-commissioning quality control form or attachment to it (refer to 079254C-0000-QCP-
1300-051), to be completed by Subcontractor before system joint walkdown with
Contractor and Company.

Punch items from final joint walkdown shall be reported in the system punch list and
uploaded into Easyplant.

8. HSE PRECAUTIONS
During piping inspection as well as during any other site activity or walkdown, all the site
safety regulations must be observed.

Standard PPE (personal protective equipment) must be worn by Subcontractor


personnel as per project site regulations.

Subcontractor must pay maximum attention to all the surrounding activities and to the
additional hazards depending on the inspection location:
• Barricaded and striped bands areas shall not be entered unless with proper permit;
• Safety harness must be worn as per site regulations when inspections are above
ground in uncompleted structures or in grating removal areas – refer to site rules;
• Ear protection devices shall be used in high noise areas;
• Attention shall be paid to moving construction vehicles, cranes, flagmen, lifting in
progress, etc.;
• Only authorized communication devices shall be used having care not to lose
attention on the surrounding activities.
it is specifically furnished or outside the extent of the agreed upon right of use.

• Depending on the location, position and/or routing of the system/sub-system to be


inspected, a valid permit to work (PTW) for inspection in confined space might be
required. In this case, proper confined space behavior – safety harness,
watchman, proper permitting, LEL analysis, etc – shall be observed for inspections
in places considered “confined” as per site regulation.

Prior to beginning inspection operations, a specific Job Hazard Analysis with risk analysis
relating to the task shall be prepared by Subcontractor.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
079254C 0000 JSC 1393 014 0 11/11

ASSIUT HYDROCRACKING COMPLEX (AHC)


ANOPC

JOB SPECIFICATION FOR PIPING INSPECTION


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Subcontractor is responsible to ensure that all hazards and preventive measures


identified in the Job Hazard Analysis are well known, understood, followed and
implemented by all involved persons in the inspection.

Typical steps/preventive measures to be considered in the Job Hazard Analysis for


works in confined space and for piping inspection are given in Attachments 1 and 2 of
the present job specification; however, customization by Subcontractor is strictly required
with respect to project and site regulations.

9. ATTACHMENTS

9.1. Att. 1 – Typical Job Hazard Analysis for Works in Confined Spaces
9.2. Att. 2 – Typical Job Hazard Analysis for Piping Inspection
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68

You might also like