079254C 0000 JSC 1393 014 0 1/11
PIPING INSPECTION
(ex 079254C-0000-MS-1393-014)
it is specifically furnished or outside the extent of the agreed upon right of use.
Martina Pinto
2021.02.10 12:02:08 Nicola Perugini
Nicola Perugini
2021.02.10
Corrado Digitally signed by
Corrado Pigna
+01'00' 2021.02.10 12:37:37 +01'00' 12:37:55 +01'00'
Pigna Date: 2021.02.10
14:16:44 +01'00'
INDEX
1. PURPOSE 3
2. SCOPE 3
3. REFERENCE DOCUMENTS 3
4. RESPONSIBILITIES 3
5. PRELIMINARY ACTIVITIES 4
5.1. Documentation 4
5.2. Inspection Scheduling 4
5.3. Site preparation 5
6. PIPING INSPECTIONS CHECKLIST 6
7. REPORTS 10
8. HSE PRECAUTIONS 10
9. ATTACHMENTS 11
9.1. Att. 1 – Typical Job Hazard Analysis for Works in Confined Spaces 11
9.2. Att. 2 – Typical Job Hazard Analysis for Piping Inspection 11
it is specifically furnished or outside the extent of the agreed upon right of use.
1. PURPOSE
Purpose of the present job specification is to provide the minimum requirements, to be
integrated with manufacturer’s instructions, that Subcontractor shall apply to carry-out all
checks on piping systems during construction and precommissioning.
2. SCOPE
This job specification applies to the execution of piping inspection activities on the project
079254C.
3. REFERENCE DOCUMENTS
079254C-0000-QCP-1300-051 Precommissioning Quality Control Plan – Piping
4. RESPONSIBILITIES
Subcontractor is responsible to monitor all the activities, maintain track and document all
records.
Subcontractor is responsible in any case of the safety of the personnel directly working
on the piping inspection and the personnel working/present in the same area affected by
the execution of the activity.
procedure for each circuit. Moreover, Subcontractor is responsible to instruct its workers
and to monitor/supervise them during the execution of piping inspection activities. Before
starting the activity, Subcontractor shall have a Tool Box meeting. Company can attend
such tool box meeting at any time.
Subcontractor shall execute piping conformity check against ISO drawings before piping
pressure test execution. This conformity check is not of the present job specification.
5. PRELIMINARY ACTIVITIES
5.1. Documentation
Subcontractor shall check piping versus the up-to-date engineering documentation.
A dedicated piping inspection folder shall be prepared by Subcontractor prior each sub-
system/system inspection including the followings:
• Latest revision (red-marked) of sub-system/system marked up P&IDs;
• Latest revision of sub-system/system component list;
• Last status of sub-system/system Construction punch list;
• Punch list form;
• Vendor P&ID (if any).
Plant piping inspections (both internal Preliminary P&ID’s check and Final P&ID’s check)
shall be organized by Subcontractor according to project procedures with a sub-
Considering the early phase of P&ID’s check execution, missing plant items shall not be
recorded as punch item unless it’s confirmed that such item will not be installed prior the
expected Mechanical Completion date.
Final piping inspection shall be performed in the frame of the official sub-system/system
joint walkdown prior sub-system/system Mechanical Completion.
During the final P&ID’s check, previously open punches holding the Mechanical
Completion of the sub-system/system shall be checked for close out.
The following list collects the general checks that Subcontractor shall systematically
address as a minimum during the system/sub-system P&ID’s conformity check. The
below list shall be supplemented by Subcontractor during site activities execution.
Subcontractor shall:
• Butterfly valves
o Ensure the valve stem/shaft is installed as per manufacturer’s instructions and
project specifications (whenever is possible, horizontal to the pipeline).
• All valves
o Check that packing gland followers are correctly tightened and that the valves
opening and closure is smooth.
o Ensure there is enough room for packing gland followers re-tightening.
o Check valve position is conform with P&ID;
o Ensure valves are equipped with an identification plate showing the correct
tags as per P&ID
o Check valves are accessible and can be safely operated (with exception of
valves for which permanent accessibility is not required; e.g. root valves).
• Sample connections
it is specifically furnished or outside the extent of the agreed upon right of use.
o Verify correct installation, in particular that they are not placed in a dead-end.
o Verify the correct type of sample arrangement as indicated on the P&ID.
o Verify there is enough room to insert the sample bottle.
o Verify there is room enough to insert a bucket or can underneath the drain
point.
o Verify that the strainer can be pulled out without problem.
o Verify the correct direction of pump strainer.
• Spectacle blinds
o Verify that blinds can be swung easily.
o Verify proper blind installation, in particular that they can be swung without a
shutdown (provision of double block and bleed valves, drain and vent points,
etc.).
o Verify no temporary blinds or aluminum sheet have been forgotten in the
circuit;
o Verify blind position is conform to P&IDs.
• Pipe supports
o Check spring hanger transit pins have been removed.
o Check piping bellows have been released
o Check slipper pads are situated correctly in their guides.
o Check pipe clamps type is as per specifications and bolts have been tightened.
• Steam traps
o Verify steam traps are correctly installed as per approved drawings.
it is specifically furnished or outside the extent of the agreed upon right of use.
• Safety valves
o Check proper installation of safety valves, in particular verify that drain/vent
points and by-passes are as per P&ID.
• Heat tracing
o Check that steam and/or electrical heat tracing installation has been
completed.
• Insulation
o Check that piping insulation on hot and cold service lines has been completed
and not damaged.
o Check that line numbers are clearly and properly marked on the insulation as
per P&ID.
o Check the correct gasket material has been used (usually a gasket color
coding is in place according to ASME B16.20 and/or Company specification).
o Check proper bolts and nuts have been installed (type, size, material) and are
not loose.
o Check grease has been used during bolts installation.
o Check flange tags on joints, as per flange management procedure in place.
• Rotating equipment
o Check that the pump can be properly and safely isolated, drained and vented
for maintenance.
o Check for the installation of commissioning strainer in the suction of the pump.
Check if it is marked on the outside.
o Verify that all maintenance activities can be executed normally; enough room
allowed to safely perform all tasks.
o Verify that start/stop switches are mounted in a logical and safe location.
o Check that equipment has been identified with the correct tag number as per
P&ID.
• Instruments
o Check correct tags as per P&ID on instrument installed.
o Check correct tapping on transmitter (+ branch upstream and – branch
downstream).
Note: the connection for liquids slopes down and for gas slopes upwards.
o Check the piping of the transmitter sensor lines have the correct tracing and
or insulation.
o Check that the orifice plate is properly installed, verifying the position of
vent/drain holes are according to the fluid passing through (for liquid, vent hole
upward; for gases, drain hole downward) and checking that the faces’ plate
orientation is according to flow direction, as needed by plate typology: e.g.,
orifice plates with beveled square edges must be installed with the beveled
end faces downstream the flow. Usually, the text label printed on the paddle
or handle of an orifice gives an identification of the upstream side of the plate.
o Verify that vessels on weigh cells are completely supported on the weigh cells
and not by any other support. Check that fixed pipes are not interfering with
the weight. Verify flexible hoses are used as indicated on the P&IDs.
• Accessibility
it is specifically furnished or outside the extent of the agreed upon right of use.
• Safety
o Check all safety aspects related to piping, e.g. protruding valves spindles, etc.
• Operability
o Check operability aspects: typical examples are the location of pressure
gauges installed at pumps discharge that must be readable while operating
the discharge valves or the level gauges of vessels to be visible from the drain
valves locations.
7. REPORTS
Results of dedicated inspections shall be reported by Subcontractor in the appropriate
pre-commissioning quality control form or attachment to it (refer to 079254C-0000-QCP-
1300-051), to be completed by Subcontractor before system joint walkdown with
Contractor and Company.
Punch items from final joint walkdown shall be reported in the system punch list and
uploaded into Easyplant.
8. HSE PRECAUTIONS
During piping inspection as well as during any other site activity or walkdown, all the site
safety regulations must be observed.
Subcontractor must pay maximum attention to all the surrounding activities and to the
additional hazards depending on the inspection location:
• Barricaded and striped bands areas shall not be entered unless with proper permit;
• Safety harness must be worn as per site regulations when inspections are above
ground in uncompleted structures or in grating removal areas – refer to site rules;
• Ear protection devices shall be used in high noise areas;
• Attention shall be paid to moving construction vehicles, cranes, flagmen, lifting in
progress, etc.;
• Only authorized communication devices shall be used having care not to lose
attention on the surrounding activities.
it is specifically furnished or outside the extent of the agreed upon right of use.
Prior to beginning inspection operations, a specific Job Hazard Analysis with risk analysis
relating to the task shall be prepared by Subcontractor.
9. ATTACHMENTS
9.1. Att. 1 – Typical Job Hazard Analysis for Works in Confined Spaces
9.2. Att. 2 – Typical Job Hazard Analysis for Piping Inspection