Job Safety Analysis Punch Point Attending

The document outlines a Job Safety Analysis (JSA) for performing Punch point Attending work on equipment IW-P-418-J scheduled for March 5, 2025, in the RJ North business unit. It details the hazards associated with the task, including pinch points and ergonomic risks, along with preventive measures to mitigate these risks. The JSA includes sections for preparation, review, and approval by various personnel involved in the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views2 pages

Job Safety Analysis Punch Point Attending

The document outlines a Job Safety Analysis (JSA) for performing Punch point Attending work on equipment IW-P-418-J scheduled for March 5, 2025, in the RJ North business unit. It details the hazards associated with the task, including pinch points and ergonomic risks, along with preventive measures to mitigate these risks. The JSA includes sections for preparation, review, and approval by various personnel involved in the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

JOB SAFETY ANALYSIS

JSA Reference Number : SMARK/MECH/JSA/004

Planned Date : 05/03/2025

BU (Business Unit) : RJ North

Permit Number :
1 Work Order Number :

Department : Projects

Equipment : IW-P-418-J

Functional Location : Water Injection

Work Description : To carry out Punch point Attending work for IW-P-418-J

2 JSA Templates : Select JSA Templates

Prepared By

Name : Mahendra Singh Sign : - Date : -


3
Name : Amit Bose Sign : - Date : -

Name : M.A.S. Biswas Sign : - Date : -

Reviewed By

Name : Ghanshyam K./ Birbal ram C. Sign : - Date : -

4 Name : Anish Anand/ Pranay K. Sign : - Date : -

Name : Sign : - Date : -

Name : P.S.(MPT) Sign : - Date : -

Approved By
5
Name : P.M.(MPT) Sign : - Date : -

Performing Authority
6
Name : Akhilesh Prasad Sign : - Date : -
JSA PLAN
Hazards effects
Activity Description Hazards Initial Risk Preventive & Mitigation Measures Residual Risk
(Consequence)

● All tools are to be used in safe manner. ● All tools have to be


required guard. ● All tools are to be used by trained personnel.
● Right Tools are to be being used for each job. ● Ensure all
are using adequate PPEs while working with hand tools. ●
6 3
Cairn Oil & Gas inspection colour code shall be ensured on all
7 Medium Low
"● Pinch Point ● service tools.● Pinch point hazards related awareness to be
Repetitive "● Back Strain ● Pinch ensured with all via tool box talk. ● Ensure pre-use inspection
Punch point
movements ● Injury ● Caught in / Likelihood : Likelihood :
Attending for tools before each use. ● Ensure all are using adequate
Ergonomics ● Fatigue between" Possible Possible
● Stress" PPEs while working with hand tools. ● Ensure crew are using
Severity : tools with protective handle. ● Ensure all hand tools are
Severity :
Minor storing in tool boxes. ● Ensure all tools/tackles must be Negligible
inspected and provided with sticker/colour code. ● Ensure all
defective/damaged tools are to be replaced. ● Ensure crew
rotation to avoid long awkward positions and fatigue.

Additional Inputs
Additional Hazards :
Enter Additional Hazards

Additional Controls :
Enter Additional Controls