Job Safety Analysis Vessel

The document outlines a Job Safety Analysis (JSA) for cleaning work on the skimmer oil vessel V-120 scheduled for 10/03/2025. It identifies various hazards associated with the work, such as gas leaks, chemical exposure, and confined space risks, along with preventive measures to mitigate these risks. The JSA includes details on personnel responsibilities, risk assessments, and required safety protocols to ensure a safe working environment.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views

Job Safety Analysis Vessel

The document outlines a Job Safety Analysis (JSA) for cleaning work on the skimmer oil vessel V-120 scheduled for 10/03/2025. It identifies various hazards associated with the work, such as gas leaks, chemical exposure, and confined space risks, along with preventive measures to mitigate these risks. The JSA includes details on personnel responsibilities, risk assessments, and required safety protocols to ensure a safe working environment.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

JOB SAFETY ANALYSIS

JSA Reference Number : SMARK/MECH/JSA/005

Planned Date : 10/03/2025

BU (Business Unit) : RJ North

Permit Number :
1 Work Order Number :

Department : Process

Equipment : VESSEL-120

Functional Location : Water Injection

Work Description : To carry out skimmer oil vessel V-120 Cleaning work

2 JSA Templates : Select JSA Templates

Prepared By

Name : Mahendra Singh Sign : - Date : -


3
Name : Amit bose Sign : - Date : -

Name : M.A.S. Biswas Sign : - Date : -

Reviewed By

Name : Ghanshyam K. / Birbal Ram C. Sign : - Date : -

4 Name : Anish Anand / Pranay K. Sign : - Date : -

Name : Sign : - Date : -

Name : P.S.(MPT) Sign : - Date : -

Approved By
5
Name : P.M.(MPT) Sign : - Date : -

Performing Authority
6
Name : Arbind Gupta Sign : - Date : -
7
JSA PLAN
Activity Hazards effects
Hazards Initial Risk Preventive & Mitigation Measures Residual Risk
Description (Consequence)

6 ● Continuous gas monitoring shall be ensured.● Cairn Oil & 3


Medium Gas inspection colour code shall be ensured on all hand & Low
"● Pinch Point ● Gas power tools.● Competent personnel shall be deployed.●
Blanding / De- release while venting "● Pinch / Burn Injury ● Likelihood : Provision of temporary support for existing line.● In case of Likelihood :
Blanding the section H2S & Near by property damage" Possible Possible
any valve leak box up & informed CCR for further support
HC"
Severity : action (if required).● OPS HSE to be intimated before start of Severity :
Minor activity. Negligible

● All MSDS are to be available and / or communicated to


1. Hazardous 9 employees.● Eye protection to be used effectively. ● Face 6
chemicals &
Medium protection to be used effectively. ● Proper work clothing to Medium
concentration2.
1. Exposure to be used effectively. ● Protective clothing for special hazards
Untrained &
Vessel Cleaning inexperience
Concentrated chemical2. Likelihood : to be used effectively. ● Respiratory protection to be used Likelihood :
Personal Injury & Possible Possible
personnel3. lack of effectively in hazardous atmosphere. ● Proper foot
Environmental Damage
communication & Severity : protection to be used effectively. ● Gloves to be used Severity :
coordination4. effectively for hand protection. ● Hearing protection to be
Pressurised water jet. Moderate Minor
used effectively when required.

1.All isolation to be performed by competent /authorized


6 personnel.2. All isolation to be done with lock out /tag out 3
"1.Gas Leak2.Fire &
Medium and be reflected to P&ID.3.Positive isolation to be approved Low
explosion3.Loss of
containment /signed and done by Ops/PE.4.All blinds flings to be
Isolation -
/spillage4.Sudden
1.Asphysiation2.Personnel Likelihood : provided with engineered design and tested.5. Performing Likelihood :
Mechanical injury3.Environment issue Possible Possible
release of authority with Cairn Oil & Gas's supervision to be ensured.6.
containment with LOTO to be provided on live line to prevent unauthorized
Severity : Severity :
pressure" operation and release.7.PTW to be obtained, Positive
Minor Negligible
isolation to be done by Ops.

● Activity shall be performed under valid Job Specific PTW. ●


Confined space entry certificate shall be ensured. ● Initial
9 gas test shall be performed by AGT. ● Conduct tool box talk 6
Medium prior to entry. ● Ear plug and clear goggles to be ensured Medium
"● Oxygen Deficiency "● Asphyxiation ● Fire / with all & used. ● Use flame proof lights. ● Stand by man
Confined Space ● Toxic Environment Explosion ● Hearing Likelihood : shall be deployed for access control. ● Employees are to be Likelihood :
Work ● Flammable Material impairment ● Electric Possible Possible
trained in confined space. ● Permit recommendation to be
● Restricted egress" shock"
Severity : being followed. ● Rescue and retrieval system to be made Severity :
Moderate available. ● Air monitoring and ventilation to be adequate. ● Minor
Proper lighting / electrical system shall be ensured. ● Access
/ egress to be adequate and to be controlled effectively.

Work at Height "● Damaged tools "● Fatal Injury ● Fracture /


6 "● TBT to be done about work at height at scaffold.● Scaf 3
and equipment’s. ● broken bone ● Near by
Medium Tag Shall be ensured.● The persons employed in work at Low
Wrong selection of Property Damage"
tools and height must be Medically & Physically fit and undergone
equipment’s. ● Likelihood : work at height training & acrophobia & vertigo test.● Ensure Likelihood :
Unsafe scaffolding ● Possible that the scaffolding erection & dismantling shall be carried Possible
Shaking and vibration Severity : out by a competent scaffolder only. ● The Green tag-“SAFE Severity :
of scaffolding ● TO USE” must be displayed on the scaffolding after
Minor Negligible
Limited access. ● inspection and before use.● Ensure proper access to the
Inadequate working
platform ● Fall from scaffold and it is secured.● Barricaded the underneath area.
height ● Misuse of ● Inspect tools for its suitability and no makeshift
scaffolding ● Material arrangement is permitted.● Full body harness to be used in
handling" any work above 1.8 m height.● Harness shall be hooked to
rigid support during erection & dismantling. ● Ensure
adequate size of working platform with alternate escape
route is prepared. ● Secure all loose material while working
at height.● 100% tie off shall be ensured."

Additional Inputs
Additional Hazards :
Enter Additional Hazards

Additional Controls :
Enter Additional Controls